Permit: T10CM01801
Permit Details
Apply Date:
06/30/2010
Applicant:
N/A
Description:
TI: COIN LAUNDRY
Architects:
- O'CONNOR, PAUL MICHAEL
Contractors:
- SUNCOR ENTERPRISES INC ,
Permit Reviews
Permit Number - T10CM01801
Permit Status: C of o
Permit Description: TI: COIN LAUNDRY
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/09/2011 | REVISION - - 1ST | 02/09/2011 | COMPLETED |
02/25/2011 | REVISION - - 2ND | 03/03/2011 | COMPLETED |
06/30/2010 | PLANS OK TO SUBMIT - COMM | 07/01/2010 | COMPLETED |
07/01/2010 | COMMERCIAL TI | 07/30/2010 | COMPLETED |
10/13/2011 | REVISION - - 3RD | 10/13/2011 | COMPLETED |
10/13/2011 | REVISION - - 3RD | 10/13/2011 | COMPLETED |
10/24/2011 | REVISION - - 4TH | 10/25/2011 | COMPLETED |
10/27/2011 | REVISION - - 5TH | 11/16/2011 | COMPLETED |
11/12/2010 | RESUBMITTAL | 11/18/2010 | COMPLETED |
11/16/2011 | REVISION - - 6TH | 11/16/2011 | COMPLETED |
11/18/2010 | RESUBMITTAL | 12/06/2010 | COMPLETED |
12/06/2010 | RESUBMITTAL | 02/09/2011 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T10CM01801
Permit Status: C of o
Permit Description: TI: COIN LAUNDRY
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
06/30/2010 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T10CM01801
Permit Description: TI: COIN LAUNDRY
Total Completed Inspections - 30
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/11/2011 | FRAMING | JBURGE | Approved | IVRS - Inspection :* |
02/11/2011 | ELECTRIC - UNDERGROUND | DSANTACR | Approved | IVRS - Inspection :* |
03/08/2011 | PLUMBING - ROUGH, SOIL | RRICH | Approved | IVRS - Inspection :* 1) CONTRATOR PROVIDED PCDEQ AUTHORIZATION TO DISCHARGE. DWV WATER TEST THRU ROOF |
03/17/2011 | PLUMBING - PRE SLAB | RRICH | Approved | IVRS - Inspection :* |
10/08/2011 | PLUMBING - YARD WTR LINE/TEST | RMYERS | Approved | IVRS - Inspection :* |
10/14/2011 | PLUMBING - GAS PRESS TEST FNL | RMYERS | Approved | IVRS - Inspection :* |
10/14/2011 | PLUMBING - GAS PRESSURE TEST | RMYERS | Approved | IVRS - Inspection :* |
10/14/2011 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
10/21/2011 | PLUMBING - PROGRESS | RRICH | Approved | IVRS - Inspection :* |
10/21/2011 | PLUMBING - SEWER HCS CONNECT | RRICH | Approved | IVRS - Inspection :* |
10/21/2011 | PLUMBING - ABOVE CEILING | RRICH | Approved | IVRS - Inspection :* |
10/21/2011 | PLUMBING - INTERMEDIATE | RRICH | Approved | IVRS - Inspection :* |
10/27/2011 | ELECTRIC - ABOVE CEILING | DSANTACR | Approved | IVRS - Inspection :* |
10/31/2011 | TEP CLEARANCE - AM | DROBEY | Approved | |
11/03/2011 | PLUMBING - FINAL | RMYERS | Approved | IVRS - Inspection :* |
11/04/2011 | MECHANICAL - PROGRESS | MRAMBER | Approved | IVRS - Inspection :* |
11/04/2011 | MECHANICAL - ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* |
11/04/2011 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
11/09/2011 | NPPO - FINAL | RLEDONNE | Approved | NA TO THIS ACTIVITY. |
11/09/2011 | LANDSCAPE - FINAL | RLEDONNE | Approved | NA TO THIS ACTIVITY. |
11/17/2011 | ELECTRIC - PROGRESS | LHANLY | Approved | |
11/17/2011 | ELECTRIC - INTERMEDIATE | LHANLY | Approved | |
11/17/2011 | ELECTRIC - FINAL | LHANLY | Approved | COMPLIANCE WITH NEC FOR ELECTRONIC CARD READERS AND BILL CHANGERS OK. ESD IS LISTED DEVICE; VENDRITE MEETS NEC REQUIREMENTS; BILL BREAKER IS FROM LISTED COMPANY. |
11/18/2011 | SIGN - FINAL | RLEDONNE | Approved | NA TO THIS ACTIVITY. |
11/18/2011 | ENGINEERING - FINAL | RLEDONNE | Approved | |
11/22/2011 | FIRE - FINAL | WMOTTO | Approved | |
11/23/2011 | BUILDING - FINAL | MHENSON | Approved | IVRS - Inspection :* |
11/23/2011 | BUILDING ABOVE CEILING | MHENSON | Approved | IVRS - Inspection :* |
11/23/2011 | SHEET ROCK NAILING | MHENSON | Approved | IVRS - Inspection :* |
12/19/2011 | RIGHT OF WAY - FINAL | MCASTRO | Approved |