Permit: T10BU01146
Permit Details
Apply Date:
07/20/2010
Applicant:
MARK BERGQUIST
Description:
GRADING:
Permit Reviews
Permit Number - T10BU01146
Permit Status: Final
Permit Description: GRADING:
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/28/2011 | RESUBMITTAL - GRADING ALL | 08/09/2011 | COMPLETED |
| 07/20/2010 | PLANS OK TO SUBMIT - GRADING | 07/20/2010 | COMPLETED |
| 07/20/2010 | GRADING | 08/26/2010 | COMPLETED |
| 08/09/2011 | RESUBMITTAL - GRADING ALL | 09/09/2011 | COMPLETED |
| 09/09/2011 | RESUBMITTAL - GRADING ALL | 10/17/2011 | COMPLETED |
| 10/12/2010 | RESUBMITTAL - GRADING ALL | 11/09/2010 | COMPLETED |
| 10/17/2011 | RESUBMITTAL - GRADING | 09/17/2012 | COMPLETED |
| 12/13/2010 | RESUBMITTAL - GRADING ALL | 01/28/2011 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T10BU01146
Permit Status: Final
Permit Description: GRADING:
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 07/20/2010 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T10BU01146
Permit Description: GRADING:
Total Completed Inspections - 9
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/20/2011 | GRADING - CHECK FOR ACTIVITY | DROBERTS | Approved | NOTHING HAPPENING AT THIS TIME. |
| 09/19/2012 | ENGINEERING PRE-CONSTRUCTION | RLEDONNE | Approved | |
| 10/16/2012 | SWPPP CORRECTION NOTICE | RLEDONNE | Approved | STREET HAS BEEN CLEANED. |
| 12/19/2012 | STORMWATER FOLLOW-UP INSP | RLEDONNE | Approved | |
| 12/19/2012 | LANDSCAPE INSPECTION | RLEDONNE | Approved | |
| 12/19/2012 | GRADING - FINAL | RLEDONNE | Approved | |
| 12/19/2012 | GRADING - INTERMEDIATE | RLEDONNE | Approved | |
| 12/19/2012 | GRADING - REBAR | RLEDONNE | Approved | |
| 12/19/2012 | GRADING - TIER REV | RLEDONNE | Approved |