Permit: T10BU01146

Parcel: 12705055A


Addresses:

4866 E SPEEDWAY BL

Inspection Status: Approved

Inspection History: GRADING - INTERMEDIATE

Date Description Inspector Results Comments
12/19/2012 GRADING - INTERMEDIATE Approved
12/14/2012 GRADING - INTERMEDIATE Continued WORKING ON BASIN.
12/12/2012 GRADING - INTERMEDIATE Continued PARKING AND DRIVE AREA READY FOR STRIPING .
12/05/2012 GRADING - INTERMEDIATE Continued NO GRADING ACTIVITY.
12/03/2012 GRADING - INTERMEDIATE Continued GOT WITH ART ABOUT AS-BUILTS AND CERT LETTER FOR GRADING AND DRAINAGE.
12/03/2012 GRADING - INTERMEDIATE Continued WORKING ON FINAL GRADING ON WEST SIDE OF BUILTING.
11/29/2012 GRADING - INTERMEDIATE Continued SIDE WALK ON SOUTH OF BUILDING IS READY TO POUR CONCRETE.
11/27/2012 GRADING - INTERMEDIATE Continued GRADING PARKING AREA.
11/26/2012 GRADING - INTERMEDIATE Continued STARTING GRADING IN PARKING AREA.
11/20/2012 GRADING - INTERMEDIATE Continued WORKING ON SIDE WALKS.
11/16/2012 GRADING - INTERMEDIATE Continued NO GRADING ACTIVITY ON SITE.
11/14/2012 GRADING - INTERMEDIATE Continued WORKING ON GRADING ON WEAT SIDE OF BUILDING .
11/08/2012 GRADING - INTERMEDIATE Continued GRADING WORK IN RIGHT-A-WAY AT THIS TIME.
10/29/2012 GRADING - INTERMEDIATE Continued CATCH BASIN ON SOUTHEAST SIDE REMOVE PER REDLINE ON AP PLANS. ON PAGE CC2.
10/26/2012 GRADING - INTERMEDIATE Continued GOT WITH G.C THE GRADING WORK STARTS 10-26-2012.
10/24/2012 GRADING - INTERMEDIATE Continued NO GARADING ACTIVITY ON SITE.
09/27/2012 GRADING - INTERMEDIATE Continued 1) CONTRACTOR INSTALLING 70 LF OF CONCRETE STORM DRAIN PIPE. PIPE IS SHOWN ON PLANS FROM NEW CATCH BASIN TO INVERT OF EXISTING STEEL PIPE.
2) NEW CATCH BASIN WILL BE CONSTRUCTED PER APPROVED PLAN W/#4 REBAR @ 12" OC.
3) TRENCH OF PIPE WAS COMPACTED AND PIPE CONNECTION WILL BE MADE USING CONCRETE.
4) PICTURES TAKEN FOR DOCUMENTATION. OK TO COVER PIPE.
5) NO STORM WATER CONCERNS AT THIS TIME
09/27/2012 GRADING - INTERMEDIATE Continued 1) BOTTOM FOR CATCH BASIN FORMED AND RE-BAR IN PLACE/PER APPROVED PLANS.
2) OK FOR CONCRETE.
3) NO STORM WATER CONCERNS AT THIS TIME
09/21/2012 GRADING - INTERMEDIATE Continued GOT WITH CONTRACTOR TO CLEAN STREETS.
09/21/2012 GRADING - INTERMEDIATE Continued TRACK OUT HAS BEEN CLEANED FROM STREET.
09/11/2012 GRADING - INTERMEDIATE Continued REMOVING OLD PARKING AREA.
09/04/2012 GRADING - INTERMEDIATE Continued NO ACTIVITY ON SITE. NO CHANGE FROM LAST INSPECTION.