Permit: T09CM02154
Permit Details
Apply Date:
08/11/2009
Applicant:
N/A
Description:
TI:OFFICE
Architects:
- JONES BRUCE
Contractors:
- R AND L BUILDERS L L C
Permit Reviews
Permit Number - T09CM02154
Permit Status: C of o
Permit Description: TI:OFFICE
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/18/2010 | REVISION - - 2ND | 02/18/2010 | ACTIVE |
08/11/2009 | COMMERCIAL TI | 08/21/2009 | COMPLETED |
08/21/2009 | COMMERCIAL TI | 09/25/2009 | COMPLETED |
09/25/2009 | COMMERCIAL TI | 10/06/2009 | COMPLETED |
10/06/2009 | RESUBMITTAL | 12/16/2009 | COMPLETED |
12/17/2009 | REVISION - - 1ST | 12/17/2009 | COMPLETED |
12/17/2009 | REVISION - - 1ST | 12/18/2009 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T09CM02154
Permit Status: C of o
Permit Description: TI:OFFICE
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
08/11/2009 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T09CM02154
Permit Description: TI:OFFICE
Total Completed Inspections - 35
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/09/2009 | PLUMBING - ROUGH, SOIL | RMYERS | Approved | IVRS - Inspection :* 1) DEMO OK 2) OK TO COVER UNDEGROUND 3) ABS WATER TEST THRU CEILING OK |
11/09/2009 | PLUMBING - PRE SLAB | RMYERS | Approved | IVRS - Inspection :* |
11/10/2009 | EXCAVATION/LAYOUT REBAR & ZON | GDABBS | Approved | IVRS - Inspection :* 1) ALL INTERIOR POUR BACKS AT UNDERGROUND AND COLUMNS OK |
12/01/2009 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* 1) SUSPENDED ROUGH DUCT OK TO PROCEED 2) OK SHEETROCK SOFFIT ROOMS 112 & 113 |
12/04/2009 | PLUMBING - INTERMEDIATE | RLEDONNE | Approved | IVRS - Inspection :* 1) COMPLETE ROOMS 101 AND 102, OTHER WALLS OK |
12/07/2009 | BUILDING - PROGRESS | JBURGE | Approved | IVRS - Inspection :* 1) NEW WALLS; PATCHES AND CONFERENCE OK TO TAPE PROGRESS AREAS-SHEETROCK |
12/16/2009 | SHEET ROCK NAILING | MHENSON | Approved | IVRS - Inspection :* 1) WALL OK, DROP & CEILINGS LEFT |
12/16/2009 | FRAMING | MHENSON | Approved | IVRS - Inspection :* 1) BEAM AT ENTRY SOUTH SIDE DETAIL 210 AND 206 NOT DONE PER DETAILS 2) STEEL LINTEL OK |
12/30/2009 | MECHANICAL - ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* RESTROOMS & SOFFIT ROOMS 135-136a OK TO COVER |
12/30/2009 | ELECTRIC - INTERMEDIATE | RHOLLAND | Approved | IVRS - Inspection :* OK LIDS & SOFFITS ROOMS 116, 117, 124, 129, 130, 134 OK LOBBY WALL & 101, 102 UDD CABLING TO BE AS PER 725.24, 800.24, 300.11 |
12/30/2009 | ELECTRIC - PROGRESS | RHOLLAND | Approved | IVRS - Inspection :* |
01/13/2010 | PLUMBING - ABOVE CEILING | RLEDONNE | Approved | IVRS - Inspection :* |
02/10/2010 | BUILDING ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* 1) OK TO SET CEILING TILES |
02/12/2010 | PLUMBING - GAS PRESSURE TEST | RLEDONNE | Approved | IVRS - Inspection :* |
02/17/2010 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
02/17/2010 | NPPO - FINAL | ACONNOR | Approved | N/A |
02/17/2010 | LANDSCAPE - FINAL | ACONNOR | Approved | N/A |
02/18/2010 | FIRE - ALARM FINAL | LTHOMAS | Approved | |
02/18/2010 | RIGHT OF WAY - FINAL | LLopez | Approved | |
02/19/2010 | ELECTRIC - FINAL | RHOLLAND | Approved | IVRS - Inspection :* 1) OK ELECTRIC |
02/19/2010 | PLUMBING - PROGRESS | RLEDONNE | Approved | IVRS - Inspection :* |
02/19/2010 | PLUMBING - GAS PRESS TEST FNL | RLEDONNE | Approved | IVRS - Inspection :* |
02/19/2010 | OUTDOOR LIGHTING FINAL | RHOLLAND | Approved | IVRS - Inspection :* |
02/19/2010 | ELECTRIC - OUTDOOR LIGHTING | RHOLLAND | Approved | IVRS - Inspection :* |
02/19/2010 | ELECTRIC - ABOVE CEILING | RHOLLAND | Approved | IVRS - Inspection :* |
02/19/2010 | ELECTRIC - UNDERGROUND | RHOLLAND | Approved | IVRS - Inspection :* |
02/23/2010 | FIRE SPKLR - FINAL | DRAMIREZ | Approved | |
02/23/2010 | FIRE SPKLR - UG, PIPING, HYDRO | JBURGE | Approved | |
02/23/2010 | PLUMBING - FINAL | JBURGE | Approved | |
02/23/2010 | FIRE - KITCHEN EXH HOOD FINAL | DRAMIREZ | Approved | |
02/23/2010 | FIRE - FINAL | DRAMIREZ | Approved | |
02/23/2010 | ENGINEERING - FINAL | JFEMLING | Approved | Approved |
02/23/2010 | MECHANICAL - HOODS | MRAMBER | Approved | |
02/23/2010 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
02/23/2010 | BUILDING - FINAL | JBURGE | Approved | IVRS - Inspection :* |