Permit: T09CM01636
Permit Details
Apply Date:
06/25/2009
Applicant:
N/A
Description:
NEW TPD CRIME LAB
Contractors:
- WITHERS CONSTRUCTION L C , D L
Permit Reviews
Permit Number - T09CM01636
Permit Status: C of o
Permit Description: NEW TPD CRIME LAB
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/07/2011 | REVISION - - 4TH | 01/12/2011 | COMPLETED |
| 01/19/2010 | PLANS OK TO SUBMIT - COMM | 01/19/2010 | COMPLETED |
| 01/19/2010 | COMMERCIAL NEW | 02/25/2010 | COMPLETED |
| 02/02/2011 | REVISION - - 5TH | 02/16/2011 | COMPLETED |
| 02/02/2011 | REVISION - SITE | 02/16/2011 | COMPLETED |
| 02/25/2010 | RESUBMITTAL - TI ALL | 03/25/2010 | COMPLETED |
| 03/25/2010 | RESUBMITTAL | 03/30/2010 | COMPLETED |
| 03/30/2010 | RESUBMITTAL | 04/08/2010 | COMPLETED |
| 04/09/2010 | REVISION - - 1ST | 04/14/2010 | COMPLETED |
| 04/27/2010 | REVISION - - 2ND | 05/11/2010 | COMPLETED |
| 05/11/2010 | RESUBMITTAL | 05/13/2010 | COMPLETED |
| 05/11/2011 | REVISION - - 6TH | 05/11/2011 | COMPLETED |
| 05/31/2011 | REVISION - SITE | 06/27/2011 | COMPLETED |
| 06/25/2009 | PLANS OK TO SUBMIT - SITE | 06/25/2009 | COMPLETED |
| 06/25/2009 | SITE | 07/23/2009 | COMPLETED |
| 08/23/2010 | REVISION - - 3RD | 08/31/2010 | COMPLETED |
| 10/09/2009 | RESUBMITTAL - SITE ALL | 11/03/2009 | COMPLETED |
| 11/03/2009 | RESUBMITTAL - SITE | 11/03/2009 | COMPLETED |
| 11/24/2009 | REVISION - - 1ST | 11/24/2009 | COMPLETED |
| 12/15/2010 | REVISION - - 4TH | 01/07/2011 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T09CM01636
Permit Status: C of o
Permit Description: NEW TPD CRIME LAB
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 06/25/2009 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T09CM01636
Permit Description: NEW TPD CRIME LAB
Total Completed Inspections - 46
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/21/2010 | ELECTRIC - TEMPORARY SERVICE | DSANTACR | Approved | IVRS - Inspection :* 1) OK TEMP POWER AND PANEL AT N.W. PART OF JOB SITE ONLY |
| 07/21/2010 | ELECTRIC - TEMPORARY POLE | DSANTACR | Approved | IVRS - Inspection :* |
| 08/26/2010 | PLUMBING - ROUGH, SOIL | RMYERS | Approved | IVRS - Inspection :* 1) 4" CONNECTED TO HOLDING TANK OK 2) 8" PVC AT SAMPLING PORT AND DOMESTIC WASTE TO P.O.C. OK |
| 09/13/2010 | PLUMBING - PRE SLAB | RMYERS | Approved | IVRS - Inspection :* |
| 09/13/2010 | ELECTRIC - UNDERGROUND | DSANTACR | Approved | IVRS - Inspection :* |
| 09/29/2010 | BUILDING PRE-SLAB | AQUIROZ | Approved | IVRS - Inspection :* 1) MECH PADS ON ROOF OK |
| 10/20/2010 | REINFORCED MASONRY PRE-GROUT | AQUIROZ | Approved | 1) 8' LIFT AT ELECTRIC ROOM |
| 11/02/2010 | ELECTRIC - PROGRESS | DSANTACR | Approved | IVRS - Inspection :* 1) OK 1ST FLOOR LAB AND OFFICE WALLS EXCEPT EAST AREA OF EE.8-OPEN OFFICES |
| 11/15/2010 | PLUMBING - PROGRESS | RMYERS | Approved | IVRS - Inspection :* 1) BATHROOM GROUP N.E. QUAD OK TO COVER WALLS SUBJECT TO ENGINEERS APPROVAL OF PVCXCI 2) ABOVE GRADE TRANSITION 3) ROOF DRAINS N.E. QUAD OK |
| 11/18/2010 | BUILDING - PROGRESS | AQUIROZ | Approved | IVRS - Inspection :* |
| 12/06/2010 | PLUMBING - GAS PRESSURE TEST | RMYERS | Approved | |
| 12/06/2010 | PLUMBING - ROOF DRAINS | RMYERS | Approved | IVRS - Inspection :* 1) ROOF DRAINS OK 2) GAS PRESSURE TEST |
| 12/16/2010 | MECHANICAL - ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* 1) FUTURE HYDRO PIPING FROM MECH ROOM TO FIRING RANGE PRESS. TEST OK, OK TO INSULATE |
| 12/17/2010 | ELECTRIC - OUTDOOR LIGHTING | DSANTACR | Approved | IVRS - Inspection :* 1) OK SOUTH 2ND FLOOR EXTERIOR SOFFITS |
| 12/28/2010 | MECHANICAL - HYDRONIC PIPING | JMILITEL | Approved | IVRS - Inspection :* 1) HEATING HOT WATER PIPING 2ND FLOOR LAB EAST MAINS AND BRANCHES-OK TO INSULATE |
| 12/28/2010 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection :* |
| 12/29/2010 | PLUMBING - INTERMEDIATE | RMYERS | Approved | IVRS - Inspection :* 1) 2ND FLOOR N/H DWV OK TO COVER |
| 12/29/2010 | SHEET ROCK NAILING | AQUIROZ | Approved | IVRS - Inspection :* 1) 1ST LAYER ON OFFICES 2ND FLOOR |
| 12/29/2010 | FRAMING | AQUIROZ | Approved | IVRS - Inspection :* 1) CEILING SOUTH EAST CORNER 2ND FLOOR |
| 02/17/2011 | TEP CLEARANCE - AM | JWEATHER | Approved | TMPP CLEARED PER R. HOLLANDER SENT TO TEP ON 02/16/11 IN THE AM |
| 04/22/2011 | PLUMBING - GAS PRESS TEST FNL | RMYERS | Approved | IVRS - Inspection :* |
| 06/28/2011 | PLUMBING - ABOVE CEILING | RMYERS | Approved | IVRS - Inspection :* |
| 06/28/2011 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
| 06/29/2011 | PLUMBING - YARD WTR LINE/TEST | RMYERS | Approved | |
| 06/29/2011 | PLUMBING - BACK WATER VALVE | RMYERS | Approved | |
| 06/29/2011 | PLUMBING - SEWER HCS CONNECT | RMYERS | Approved | IVRS - Inspection :* |
| 07/07/2011 | BUILDING ABOVE CEILING | AQUIROZ | Approved | IVRS - Inspection :* |
| 07/07/2011 | U VALUE FOR WINDOW | AQUIROZ | Approved | IVRS - Inspection :* |
| 07/07/2011 | ROOF NAILING | AQUIROZ | Approved | IVRS - Inspection :* |
| 07/18/2011 | MECHANICAL - PROGRESS | MRAMBER | Approved | IVRS - Inspection :* |
| 07/18/2011 | MECHANICAL - HOOD SYSTEMS | MRAMBER | Approved | IVRS - Inspection :* |
| 07/18/2011 | MECHANICAL - HOODS | MRAMBER | Approved | IVRS - Inspection :* |
| 07/19/2011 | OUTDOOR LIGHTING FINAL | RHOLLAND | Approved | IVRS - Inspection :* |
| 07/19/2011 | ELECTRIC - TEMP POWER FOR TEST | RHOLLAND | Approved | IVRS - Inspection :* |
| 07/19/2011 | ELECTRIC - ABOVE CEILING | RHOLLAND | Approved | IVRS - Inspection :* |
| 07/19/2011 | ELECTRIC - UFER | RHOLLAND | Approved | IVRS - Inspection :* |
| 07/26/2011 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
| 07/27/2011 | PLUMBING - FINAL | RMYERS | Approved | IVRS - Inspection :* |
| 08/24/2011 | FIRE - ALARM FINAL | WMOTTO | Approved | |
| 08/24/2011 | FIRE SPKLR - FINAL | WMOTTO | Approved | |
| 08/24/2011 | FIRE SPKLR - UG, PIPING, HYDRO | WMOTTO | Approved | |
| 08/26/2011 | NPPO - FINAL | MRUSSO | Approved | |
| 08/26/2011 | LANDSCAPE - FINAL | MRUSSO | Approved | |
| 08/26/2011 | ENGINEERING - FINAL | MRUSSO | Approved | |
| 08/31/2011 | ELECTRIC - FINAL | LHANLY | Approved | |
| 09/07/2011 | BUILDING - FINAL | JBURGE | Approved | IVRS - Inspection :* |