Permit: T09CM00715
Permit Details
Status:
C of o
Type:
COMMERCIAL ADDITION
Address:
1200 N CAMPBELL AV
Address NEW:
1200 N CAMPBELL AV
Apply Date:
03/31/2009
Applicant:
N/A
Description:
ADDITION AND REMODEL TO CHURCH ACTIVITY CENTER
Contractors:
- BARKER MORRISSEY CONTRACTING INC **C
Permit Reviews
Permit Number - T09CM00715
Permit Status: C of o
Permit Description: ADDITION AND REMODEL TO CHURCH ACTIVITY CENTER
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/31/2009 | PLANS OK TO SUBMIT - 3RD PARTY | 03/31/2009 | COMPLETED |
| 03/31/2009 | SITE | 05/06/2009 | COMPLETED |
| 03/31/2009 | 3RD PARTY REVIEW-COMMERCIAL | 05/05/2009 | COMPLETED |
| 05/05/2009 | POST 3RD PARTY REVIEW | 05/13/2009 | COMPLETED |
| 05/06/2009 | SITE | 05/12/2009 | COMPLETED |
| 05/12/2009 | RESUBMITTAL - SITE ALL | 05/21/2009 | COMPLETED |
| 05/13/2009 | RESUBMITTAL | 05/21/2009 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T09CM00715
Permit Status: C of o
Permit Description: ADDITION AND REMODEL TO CHURCH ACTIVITY CENTER
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 03/31/2009 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T09CM00715
Permit Description: ADDITION AND REMODEL TO CHURCH ACTIVITY CENTER
Total Completed Inspections - 42
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/22/2009 | PLUMBING - ROUGH, SOIL | RMYERS | Approved | 1. PIPING INTO, OUT OF AND VENT FOR INTERCEPTOR OK TO COVER 2. ABS UNDER SLAB OK TO COVER 3. WRAP ALL THRU SLAB PIPING |
| 06/29/2009 | PLUMBING - PRE SLAB | RMYERS | Approved | IVRS - Inspection :* 1) OK TO POUR UNDERGROUND AT INTERCEPTOR |
| 08/04/2009 | FIRE SPKLR - OH PIPING & HYDRO | LTHOMAS | Approved | |
| 08/04/2009 | FIRE SPKLR - UG, PIPING, HYDRO | LTHOMAS | Approved | |
| 08/06/2009 | FIRE SPKLR - UG PIPING FLUSH | LTHOMAS | Approved | |
| 08/11/2009 | PLUMBING - INTERMEDIATE | BBENEDON | Approved | IVRS - Inspection :* 1) CLOSET FLANGES OK, KEEP OPEN SEWER PIPING CAPPED OR PLUGGED DURING CONSTRUCTION FOR SAFETY 2) JANITOR SINK PIPING OK TO COVER |
| 08/12/2009 | ELECTRIC - UNDERGROUND | DSANTACR | Approved | IVRS - Inspection :* |
| 08/14/2009 | TEP CLEARANCE - PM | JWEATHER | Approved | INCR CLEARED PER L. HANLY |
| 08/14/2009 | ELECTRIC - UFER | LHANLY | Approved | |
| 08/18/2009 | PLUMBING - GAS PRESSURE TEST | BBENEDON | Approved | IVRS - Inspection :* |
| 08/19/2009 | BUILDING ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* 1) OK TO SET CEILING TILES (NO WORK IN EXISTING CHAPEL AREA) |
| 08/19/2009 | PLUMBING - ABOVE CEILING | BBENEDON | Approved | IVRS - Inspection :* |
| 08/21/2009 | NPPO - FINAL | ACONNOR | Approved | |
| 08/21/2009 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
| 08/24/2009 | RIGHT OF WAY - FINAL | LLOPEZ | Approved | PER EMAIL |
| 08/27/2009 | MECHANICAL - ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* |
| 08/27/2009 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
| 09/22/2009 | LANDSCAPE - FINAL | ACONNOR | Approved | |
| 09/24/2009 | OUTDOOR LIGHTING FINAL | DSANTACR | Approved | IVRS - Inspection :* |
| 10/14/2009 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | |
| 10/14/2009 | ELECTRIC - ABOVE CEILING | DSANTACR | Approved | |
| 10/14/2009 | ELECTRIC - CABLE DROP | DSANTACR | Approved | |
| 10/14/2009 | ELECTRIC - OUTDOOR LIGHTING | DSANTACR | Approved | |
| 10/14/2009 | FIRE - ALARM FINAL | DSIWARSKI | Approved | |
| 10/14/2009 | ELECTRIC - FINAL | DSANTACR | Approved | IVRS - Inspection :* |
| 10/14/2009 | MECHANICAL - HOOD SYSTEMS | MRAMBER | Approved | IVRS - Inspection :* |
| 10/14/2009 | MECHANICAL - HOODS | MRAMBER | Approved | IVRS - Inspection :* |
| 10/15/2009 | ENGINEERING - FINAL | DROBERTS | Approved | |
| 10/15/2009 | PLUMBING - FINAL | RMYERS | Approved | IVRS - Inspection :* |
| 10/15/2009 | PLUMBING - GAS PRESS TEST FNL | RMYERS | Approved | IVRS - Inspection :* |
| 10/16/2009 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
| 10/26/2009 | FIRE - KITCHEN EXH HOOD FINAL | LTHOMAS | Approved | |
| 10/26/2009 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
| 10/26/2009 | STUCCO MESH | AQUIROZ | Approved | |
| 10/26/2009 | FIRE - FINAL | LTHOMAS | Approved | Approved |
| 10/26/2009 | BUILDING - FINAL | AQUIROZ | Approved | IVRS - Inspection :* |
| 10/26/2009 | FRAMING | AQUIROZ | Approved | IVRS - Inspection :* |
| 10/26/2009 | SHEET ROCK NAILING | AQUIROZ | Approved | IVRS - Inspection :* |
| 10/26/2009 | REINFORCED MASONRY PRE-GROUT | AQUIROZ | Approved | IVRS - Inspection :* |
| 10/26/2009 | EXT METAL CLIPS/EXT SHEATHING | AQUIROZ | Approved | IVRS - Inspection :* |
| 10/26/2009 | BUILDING PRE-SLAB | AQUIROZ | Approved | IVRS - Inspection :* |
| 10/26/2009 | EXCAVATION/LAYOUT REBAR & ZON | AQUIROZ | Approved | IVRS - Inspection :* |