Inspection History Details
Inspection Status: Approved
Inspection History: ENGINEERING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/15/2009 | ENGINEERING - FINAL | Approved | ||
| 08/28/2009 | ENGINEERING - FINAL | Not ready for Inspection | 1) COMPLETE ALL EXTERIOR CONSTRUCTION. 2) PROVIDE AN APPROVED DRAWING SHOWING WHAT WAS BUILT - EXISTING PLAN DOES NOT MATCH SITE WORK |
|
| 08/21/2009 | ENGINEERING - FINAL | Denied | Separate all const. from public. | |
| 08/13/2009 | ENGINEERING - FINAL | Continued | CHANGE TO PARKING LOT, FROM 6" REVEAL VERT CURB TO CONCRETE HEADER AT GRADE. HC PARKING ACCESS TO SIDEWALK IS AT GRADE - NEED TRUNCATED DOMES AT ALL TRANSITION POINTS. ROOF DRAINS MAY NEED SCUPPERS. |