Permit: T07CM00650
Permit Details
Apply Date:
02/16/2007
Applicant:
JOSE TERAN M3 ENGINEERING
Description:
NEW MAINTENANCE BUILDING SITE IMPROVEMENTS BUILDING # 1
Architects:
- MULLIGAN, DENNIS MYLES
Contractors:
- LANG WYATT CONSTRUCTION ,
Permit Reviews
Permit Number - T07CM00650
Permit Status: C of o
Permit Description: NEW MAINTENANCE BUILDING
SITE IMPROVEMENTS
BUILDING # 1
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/15/2008 | 3RD PARTY REVIEW-REVISION/OTHER | 02/20/2008 | COMPLETED |
02/16/2007 | PLANS OK TO SUBMIT - SITE | 02/16/2007 | COMPLETED |
02/16/2007 | PLANS OK TO SUBMIT - COMM | 02/16/2007 | COMPLETED |
02/16/2007 | SITE | 06/06/2007 | COMPLETED |
02/16/2007 | 3RD PARTY REVIEW-COMMERCIAL | 04/17/2007 | COMPLETED |
04/10/2008 | 3RD PARTY REVIEW-REVISION/OTHER | 04/14/2008 | COMPLETED |
04/17/2007 | POST 3RD PARTY REVIEW | 06/06/2007 | COMPLETED |
06/21/2007 | RESUBMITTAL | 07/31/2007 | COMPLETED |
06/21/2007 | RESUBMITTAL - SITE | 07/31/2007 | COMPLETED |
09/04/2007 | POST 3RD PARTY REVIEW | 09/06/2007 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T07CM00650
Permit Status: C of o
Permit Description: NEW MAINTENANCE BUILDING
SITE IMPROVEMENTS
BUILDING # 1
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
02/16/2007 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T07CM00650
Permit Description: NEW MAINTENANCE BUILDING
SITE IMPROVEMENTS
BUILDING # 1
Total Completed Inspections - 44
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/20/2007 | SITE - SEWER | RLEDONNE | Approved | IVRS - Inspection :* 1. PROVIDE VERIFICATION OF GRADE 2. BENCH IN MANHOLE OK |
12/21/2007 | ELECTRIC - UNDERGROUND | DSANTACR | Approved | IVRS - Inspection :* 1) OK UNDER SLAB HOME RUNS OFFICE AREA LUNCH ROOM, OK SECONDARY STUB UP INTO SES |
12/27/2007 | PLUMBING - ROUGH, SOIL | RLEDONNE | Approved | IVRS - Inspection :* |
02/19/2008 | PLUMBING - PRE SLAB | RLEDONNE | Approved | IVRS - Inspection :* |
06/02/2008 | ROOF NAILING | MHENSON | Approved | IVRS - Inspection :* |
07/11/2008 | FIRE SPKLR - UG, PIPING, HYDRO | LTHOMAS | Approved | |
08/13/2008 | EXT METAL CLIPS/EXT SHEATHING | MHENSON | Approved | |
10/14/2008 | FRAMING | MHENSON | Approved | IVRS - Inspection :* |
10/20/2008 | SHEET ROCK NAILING | MHENSON | Approved | IVRS - Inspection :* |
10/21/2008 | U VALUE FOR WINDOW | MHENSON | Approved | IVRS - Inspection :* |
10/21/2008 | BUILDING ABOVE CEILING | MHENSON | Approved | IVRS - Inspection :* |
10/24/2008 | TEP CLEARANCE - AM | JWEATHER | Approved | TEC CLEARED PER D. SANTACRUZ |
10/31/2008 | MECHANICAL - ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* PROVIDE PROPER FILTER ASSEMBLY SECONDARY DRAIN RUNNING UPHILL OK FOR TILES |
11/03/2008 | PLUMBING - ABOVE CEILING | RLEDONNE | Approved | IVRS - Inspection :* |
11/18/2008 | ELECTRIC - UFER | DSANTACR | Approved | IVRS - Inspection :* TIE IN CIRCUIT GROUNDING TO POLE |
11/18/2008 | ELECTRIC - OUTDOOR LIGHTING | DSANTACR | Approved | IVRS - Inspection :* |
11/18/2008 | ELECTRIC - CABLE DROP | DSANTACR | Approved | IVRS - Inspection :* |
11/18/2008 | ELECTRIC - ABOVE CEILING | DSANTACR | Approved | IVRS - Inspection :* |
11/18/2008 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection :* |
11/19/2008 | EXCAVATION/LAYOUT REBAR & ZON | LHANLY | Approved | IVRS - Inspection :* 2 LIGHT POLE BASES @ SOUTH ENTRANCE |
11/20/2008 | PLUMBING - GAS PRESSURE TEST | RLEDONNE | Approved | IVRS - Inspection :* |
11/20/2008 | FIRE SPKLR - OH PIPING & HYDRO | LTHOMAS | Approved | |
11/20/2008 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
11/20/2008 | FIRE - ALARM FINAL | LTHOMAS | Approved | |
11/20/2008 | FIRE SPKLR - UG PIPING FLUSH | LTHOMAS | Approved | |
11/20/2008 | FIRE - FINAL | LTHOMAS | Approved | |
11/25/2008 | PLUMBING - INTERMEDIATE | RLEDONNE | Approved | IVRS - Inspection :* |
11/26/2008 | PLUMBING - YARD WTR LINE/TEST | RLEDONNE | Approved | IVRS - Inspection :* 1) COMPLETE INSTALL AND ? ALL BACKFLOW PROTECTION |
11/26/2008 | PLUMBING - SEWER HCS CONNECT | RLEDONNE | Approved | IVRS - Inspection :* |
11/26/2008 | PLUMBING - GAS PRESS TEST FNL | RLEDONNE | Approved | IVRS - Inspection :* |
11/26/2008 | PLUMBING - ROOF DRAINS | RLEDONNE | Approved | IVRS - Inspection :* |
12/04/2008 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | |
12/04/2008 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection :* 1. ALL LIFE SAFETY ISSUES OBSERVED SEE BUILDING INSPECTOR FOR TEMP C OF O 2. PROVIDE FLEX CONNECTORS ON GAS PIPING PER (11) PL501 3. ISOLATE COPPER "T's" ON ROOF 4. PROVIDE GAS PIPING SUPPORT ON WATER HEATER 5. PROVIDE VENT PIPING INSTALLATION INSTRUCTIONS ON WATER HEATER 90% 6. PROVIDE AIR BALANCE REPORT 7. DUCT SMOKE DETECTOR TEST OK X5 |
12/09/2008 | PLUMBING - FINAL | RLEDONNE | Approved | IVRS - Inspection :* 1. REPAIR LEAK AT SINKS 2. PROVIDE BACKFLOW CERT. FOR ICE MAKER IN BREAKROOM 3. INSTALL ALL BACKFLOWS 4. COMPLETE LIST FROM 11/28/2008 |
12/09/2008 | BUILDING - FINAL | MHENSON | Approved | IVRS - Inspection :* 1. FIRE SPRINKLER, C OF O, ALARM APPROVED 2. SPOKE WITH TRADES E, P, M OK WITH TEMP C OF O 3. OK FOR TEMP C OF O WITH ENGINEERING |
12/09/2008 | ENGINEERING - FINAL | MAVERY | Approved | Contractor needs to complete punch list. (See Below) PRELIM PUNCH LIST. CONTRACTOR NEEDS TO ADDRESS ITEMS AND CALL IN FOR RE-INSPECTION. 1- Complete all grading activity. 2- Provide site cert from engineer, per C.O.T. D.M. chapter XIV, section 14.2(7). 3- Pin down all wheel stops. 4- Provide wheel stops for north building parking. 5- Stabilize all areas distrubed by construction. 6- Complete all sidewalk work. 7- Complete retention/detention basin. 8- Complete all drainage and drainage structures. 9- Install all bollers for trash enclosures. 10- Clean all wash out on site. 11- Grade basin to drain. 12- Have engineer address all slopes steeper then 3 to 1. 13- Keep all SWPPP controls in working order until all areas stabilized. 14- Engineer needs to provide approved revised drawing showing all changes to drainage. 15- Address all erosion on site. 16- Complete all construction around building. 17- Backfill all open holes. 18- Remove all port-a-pottys from site. 19- Address holes southwest corner of project. 20- Install all traffic islands. 21- Complete all striping. 22- Complete outlet for basin, per approved drawings. |
12/12/2008 | ELECTRIC - FINAL | DSANTACR | Approved | IVRS - Inspection :* |
12/15/2008 | OUTDOOR LIGHTING FINAL | DSANTACR | Approved | |
12/15/2008 | ELECTRIC - TEMP POWER FOR TEST | DSANTACR | Approved | |
05/06/2009 | RIGHT OF WAY - FINAL | LLOPEZ | Approved | PER EMAIL |
05/06/2009 | SIGN - FINAL | JYBARRA | Approved | |
06/12/2009 | BUILDING PRE-SLAB | MHENSON | Approved | |
06/12/2009 | REINFORCED MASONRY PRE-GROUT | MHENSON | Approved | |
08/14/2009 | PERMIT FINALED | DROBERTS | Approved |