Permit: T07BU01158
Permit Details
Apply Date:
05/23/2007
Applicant:
DESIGN RESULTS
Description:
GRADING:2820CY CUT 1210CY FILL
Contractors:
- HALBERT BROS INC ,
Permit Reviews
Permit Number - T07BU01158
Permit Status: Final
Permit Description: GRADING:2820CY CUT 1210CY FILL
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/23/2007 | PLANS OK TO SUBMIT - GRADING | 05/23/2007 | COMPLETED |
| 05/23/2007 | GRADING | 06/28/2007 | COMPLETED |
| 06/28/2007 | RESUBMITTAL - GRADING ALL | 07/16/2007 | COMPLETED |
| 08/07/2007 | RESUBMITTAL - GRADING ALL | 08/16/2007 | COMPLETED |
| 11/05/2008 | REVISION - GRADING | 11/07/2008 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T07BU01158
Permit Status: Final
Permit Description: GRADING:2820CY CUT 1210CY FILL
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 05/23/2007 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T07BU01158
Permit Description: GRADING:2820CY CUT 1210CY FILL
Total Completed Inspections - 8
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/24/2007 | ENGINEERING PRE-CONSTRUCTION | NKALAHAR | Approved | MET WITH CLIFF HALBERT 444-9170 HAVE NOT RECVD THESE PLANS YET STAMPED APPROVED SET USED FOR PRECON THIS SITE IS PHASED GRUBBING TO START 8/28 MINIMAL CONTROLS ARE REQD FOR THIS SITE |
| 12/10/2007 | STORMWATER FOLLOW-UP INSP | NKALAHAR | Approved | NO CONCERNS |
| 11/13/2008 | GRADING - FINAL | NKALAHAR | Approved | STAMPED PLAN REVISION 11/7/8 BY PAUL MACHADO NEW "AS BUILT" -SHOWS NO BLDG 2 (PHASE LINE) -SHOWS BASIN RAMP REMOVAL (E BASIN) -SHOWS TRUNCATED DOMES AND WHEEL STOPS IN THE OFFICE-ALLOWING FOR PEDESTRIAN REFUGE AREA ON N SIDE OF SHOP AREA |
| 11/13/2008 | GRADING - INTERMEDIATE | NKALAHAR | Approved | |
| 11/13/2008 | STORMWATER INSTALL OF CONTROLS | NKALAHAR | Approved | |
| 03/01/2011 | LANDSCAPE INSPECTION | JFEMLING | Approved | Approved |
| 03/01/2011 | NPPO PRE PERMIT INSPECTION | JFEMLING | Approved | Approved |
| 03/10/2011 | PERMIT FINALED | KMEDINA | Approved |