Permit: T06CM04079
Permit Details
Apply Date:
07/12/2006
Applicant:
STEVEN C SHELL
Description:
TI:RETAIL
Contractors:
- EPSTEIN CONSTRUCTION L L C
Permit Reviews
Permit Number - T06CM04079
Permit Status: Expired
Permit Description: TI:RETAIL
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/26/2016 | REVISION - - 4TH | 03/31/2016 | COMPLETED |
03/31/2016 | REVISION - - 5TH | 03/31/2016 | COMPLETED |
04/08/2016 | REVISION - - 6TH | 04/08/2016 | COMPLETED |
05/14/2015 | REVISION - - 1ST | 05/20/2015 | COMPLETED |
05/20/2015 | REVISION - - 1ST | 08/17/2015 | COMPLETED |
06/13/2016 | REVISION - - 7TH | 06/13/2016 | COMPLETED |
07/12/2006 | COMMERCIAL TI | 07/12/2006 | COMPLETED |
07/12/2006 | COMMERCIAL TI | 06/28/2007 | COMPLETED |
08/17/2015 | REVISION - - 2ND | 09/17/2015 | COMPLETED |
10/29/2015 | REVISION - - 3RD | 10/29/2015 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T06CM04079
Permit Status: Expired
Permit Description: TI:RETAIL
Total Outstanding Activity Conditions - 8
Date | Name |
---|---|
07/12/2006 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
08/23/2006 | SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED. |
08/23/2006 | SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED. |
08/23/2006 | SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED. |
08/23/2006 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. |
08/23/2006 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
08/23/2006 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. |
08/23/2006 | SPECIAL INSPECTION IS REQUIRED FOR STRUCTURAL STEEL PER U.A.C. SECTION 306. |
Outstanding Inspections
Permit Status: Expired
Permit Number: T06CM04079
Permite Description: TI:RETAIL
Total Outstanding Inspections - 2
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/13/2015 | FIRE SPKLR - FINAL | N/A | Partial Approval | 1. Sprinkler system is not properly monitored ( informed by contractor that the flow and tamper was monitored as burgler alarm) - must be monitored by a UL listed company and water flow should trigger a fire alarm response. Need panel indicating alarm, trouble or supervisory and must have a smoke and pull above the panel. 2. may not place merchandise in phase 1 area until all ceiling tiles have been put in place ( unless 24 hour fire watch is provided until all ceiling tiles have been placed). NS - 11/13/15 |
12/28/2015 | ENGINEERING - FINAL | N/A | Not ready for Inspection |
Completed Inspections
Permit Status: Expired
Permit Number: T06CM04079
Permit Description: TI:RETAIL
Total Completed Inspections - 20
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/21/2008 | TEP CLEARANCE - AM | JWEATHER | Approved | INCR CLEARED PER R. JIROUDEK |
09/15/2009 | SHEET ROCK NAILING | JBURGE | Approved | IVRS - Inspection :* 1) NORTH MEZZANINE WALL-OK TO TAPE |
11/29/2011 | ELECTRIC - INTERMEDIATE | RMORENO | Approved | IVRS - Inspection :* |
01/17/2014 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
01/08/2015 | BUILDING ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* |
11/13/2015 | FRAMING | BBENEDOI | Approved | IVRS - Inspection :* |
11/16/2015 | ELECTRIC - ABOVE CEILING | RMORENO | Approved | IVRS - Inspection :* |
11/19/2015 | FIRE - ALARM FINAL | nsprenger | Approved | 1. still need to test the Sam Levits - Ashley side of the building once the devices are added. 2. Old Duct detector on roof unit that is not connected to the alarm system shall be removed ( it has been abandoned in place in between units #21 and 17) |
11/24/2015 | ELECTRIC - OUTDOOR LIGHTING | RMORENO | Approved | CONTRACTOR NOT ON SITE. OUTDOOR LIGHTING NOT READY. |
11/24/2015 | ELECTRIC - FINAL | RMORENO | Approved | IVRS - Inspection :* |
11/24/2015 | MECHANICAL - FINAL | RMORENO | Approved | IVRS - Inspection :* |
11/25/2015 | NPPO - FINAL | RLEDONNE | Approved | |
11/25/2015 | LANDSCAPE - FINAL | RLEDONNE | Approved | |
11/25/2015 | SIGN - FINAL | RLEDONNE | Approved | |
12/24/2015 | FIRE - FINAL | NSprenger | Approved | North showroom inspected and approved |
12/24/2015 | BUILDING - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
08/11/2016 | OUTDOOR LIGHTING FINAL | JMILITEL | Approved | IVRS - Inspection :* |
08/12/2016 | EXCAVATION/LAYOUT REBAR & ZON | JMILITELLO | Approved | |
08/12/2016 | PLUMBING - FINAL | JMILITELLO | Approved | |
08/22/2016 | RIGHT OF WAY - FINAL | mbravin | Approved |