Permit Details

Status:
C of o
Type:
COMMERCIAL ALTERATION
Apply Date:
06/29/2006
Applicant:
N/A
Description:
TI: DRY CLEANER
Architects:
  • ARCHITECTURAL DESIGN GROUP INC
Contractors:
  • KACHINA GENERAL CONTRACTORS L L C

Permit Reviews

Permit Number - T06CM03829
Permit Status: C of o
Permit Description: TI: DRY CLEANER
Start Date Submittal Complete Date Status  
02/13/2007 3RD PARTY REVIEW-REVISION/OTHER 02/15/2007 COMPLETED Review Details
06/29/2006 PLANS OK TO SUBMIT - 3RD PARTY 06/29/2006 COMPLETED Review Details
06/29/2006 3RD PARTY REVIEW-COMMERCIAL TI 07/10/2006 COMPLETED Review Details
07/10/2006 POST 3RD PARTY REVIEW 07/19/2006 COMPLETED Review Details
08/11/2006 3RD PARTY REVIEW-REVISION/OTHER 08/11/2006 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T06CM03829
Permit Status: C of o
Permit Description: TI: DRY CLEANER
Total Outstanding Activity Conditions - 1
Date Name
06/29/2006 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T06CM03829
Permit Description: TI: DRY CLEANER
Total Completed Inspections - 31
Date Description Inspector Results Comments
08/15/2006 ELECTRIC - CONSTRUCTION POWER RSUBA Approved IVRS - Inspection :*
1) LABEL METER BASE PER TEP 7066 E. GOLF LINKS #108 WITH METAL LABEL
08/16/2006 TEP CLEARANCE - AM JWEATHER Approved TEC CLEARED PER R. SUBA
09/06/2006 ELECTRIC - UNDERGROUND RMAJUTA Approved IVRS - Inspection :*
2 - 3/4" PVC OK TO COVER
09/06/2006 PLUMBING - PRE SLAB RRICH Approved IVRS - Inspection :*
09/22/2006 ELECTRIC - INTERMEDIATE RMAJUTA Approved IVRS - Inspection :*
1. OK TO COVER BOILER RM WALL (3 WASHERS & 1 DRYER)
2. OK TO COVER BOILER RM SOUTH WALL
3. OK TO COVER BOILER RM NORTH WALL
09/22/2006 PLUMBING - ROUGH, SOIL RRICH Approved IVRS - Inspection :*
10/27/2006 FRAMING GDABBS Approved IVRS - Inspection :*
10/27/2006 PLUMBING - ABOVE CEILING BBENEDON Approved IVRS - Inspection :*
10/30/2006 SHEET ROCK NAILING GDABBS Approved IVRS - Inspection :*
NORTH WALL OF BOILER ROOM #103 MUST BE FIRE STOPPED AND HOLES IN NORTH WALL OF ROOM #101 MUST BE PATCHED ABOVE CEILING - 3M CP25WB+
11/03/2006 PLUMBING - INTERMEDIATE RRICH Approved IVRS - Inspection :*
1 1/2 COPPER BUILDING INTERIOR BACK TO
METER LOCATION OK

1. SHALL SEE RPBA INSTALL.
2. SHALL SEE COMPLETION OF WATER PIPING TO BOILER.
3. A BOILER INSPECTION & PERMIT SHALL BE OBTAINED FOR ALL BOILERS: IF MORE THAN (1) BOILER IS INSTALLED REVISED CITY APPROVED PLAN SHALL BE OBTAINED WITH PIPING DIAGRAMS, FOR WATER EXPANSION TANKS, GAS ETC.
11/14/2006 PLUMBING - GAS PRESSURE TEST RLEDONNE Approved IVRS - Inspection :*
COMPLETE GAS PIPING AND PROVIDE GAS PRESSURE TEST.
03/09/2007 PLUMBING - GAS PRESS TEST FNL RRICH Approved IVRS - Inspection :*
100 PSI TEST ON AIR PIPING OK
INSTALL PIPING PER PLAN
03/15/2007 ELECTRIC - TEMP POWER FOR TEST RMAJUTA Approved IVRS - Inspection :*
03/19/2007 MECHANICAL - FINAL JMILITEL Approved IVRS - Inspection :*
03/19/2007 MECHANICAL - ABOVE CEILING JMILITEL Approved IVRS - Inspection :*
03/19/2007 MECHANICAL - INTERMEDIATE JMILITEL Approved IVRS - Inspection :*
03/19/2007 ELECTRIC - FINAL RJIROUDE Approved IVRS - Inspection :*
03/19/2007 OUTDOOR LIGHTING FINAL RJIROUDE Approved IVRS - Inspection :*
03/19/2007 ELECTRIC - OUTDOOR LIGHTING RJIROUDE Approved IVRS - Inspection :*
03/19/2007 ELECTRIC - ABOVE CEILING RJIROUDE Approved IVRS - Inspection :*
03/20/2007 ELECTRIC - CABLE DROP RJIROUDE Approved
03/27/2007 PLUMBING - FINAL JMILITEL Approved IVRS - Inspection :*
OK FOR FINAL
03/28/2007 RIGHT OF WAY - FINAL SDAMRON Approved PER EMAIL
03/28/2007 PLUMBING - GAS RECONNECT RMYERS Approved
03/28/2007 NPPO - FINAL ACONNOR Approved N/A
03/28/2007 LANDSCAPE - FINAL ACONNOR Approved N/A
03/28/2007 FIRE - FINAL LTHOMAS Approved
03/28/2007 ENGINEERING - FINAL NKALAHAR Approved NO SITE WORK
03/29/2007 BUILDING ABOVE CEILING GDABBS Approved PER BU FINAL
03/29/2007 BUILDING - FINAL GDABBS Approved PER INSP CARD
03/29/2007 SIGN - FINAL JYBARRA Approved