Permit Number - T05CM06362
Permit Status: C of o
Permit Description: TI: OFFICE
Start Date Submittal Complete Date Status  
01/24/2006 COMMERCIAL TI 02/09/2006 COMPLETED Review Details
02/15/2006 COMMERCIAL TI 02/21/2006 COMPLETED Review Details
02/21/2006 OTHER 03/07/2006 COMPLETED Review Details
03/16/2006 RESUBMITTAL 05/05/2006 COMPLETED Review Details
12/21/2005 COMMERCIAL TI 01/24/2006 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T05CM06362
Permit Status: C of o
Permit Description: TI: OFFICE
Total Outstanding Activity Conditions - 1
Date Name
12/21/2005 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T05CM06362
Permit Description: TI: OFFICE
Total Completed Inspections - 21
Date Description Inspector Results Comments
05/08/2006 PLUMBING - ROUGH, SOIL RRICH Approved IVRS - Inspection :*
WATER TEST UNDERGROUND ONLY OK PER REDLINE
PIPE WRAPS OK
06/06/2006 PLUMBING - ABOVE CEILING BBENEDON Approved IVRS - Inspection :*
PIPING IN WALLS AND ABOVE CEILING IS OK
CLOSET FLANGES ARE NOT.
ABS TO PVC TRANSITION GLUE IS FOR USE OUTSIDE BUILDING ONLY.
A 3" FLANGE SHALL NOT BE USED INSIDE 4" PIPE.
06/09/2006 ELECTRIC - INTERMEDIATE RHOLLAND Approved IVRS - Inspection :*
OK WALLS
06/12/2006 FRAMING JBURGE Approved IVRS - Inspection :*
OK TO SHEETROCK
06/19/2006 SHEET ROCK NAILING JBURGE Approved IVRS - Inspection :*
OK TO TAPE - TEXTURE
07/26/2006 MECHANICAL - ABOVE CEILING JMILITEL Approved IVRS - Inspection :*
OK FOR CEILING TILES
07/26/2006 FIRE - FINAL LTHOMAS Approved
07/26/2006 FIRE SPKLR - FINAL LTHOMAS Approved
07/31/2006 ELECTRIC - ABOVE CEILING RHOLLAND Approved IVRS - Inspection :*
OK TO TILE
08/31/2006 MECHANICAL - FINAL JMILITEL Approved IVRS - Inspection :*
08/31/2006 BUILDING ABOVE CEILING JBURGE Approved IVRS - Inspection :*
CEILING SYSTEM IN PLACE
09/05/2006 BUILDING - FINAL JBURGE Approved IVRS - Inspection :*
09/05/2006 PLUMBING - FINAL BBENEDON Approved IVRS - Inspection :*
09/05/2006 PLUMBING - INTERMEDIATE BBENEDON Approved IVRS - Inspection :*
09/05/2006 PLUMBING - PROGRESS BBENEDON Approved IVRS - Inspection :*
09/06/2006 ENGINEERING - FINAL JBRUCKME Approved OK FOR TEMPORARY C OF O.
1. CORRECT DRAINAGE PROBLEMS AROUND THIS BUILDING.
2. RE-INSTALL ROCK RIP RAP AT DRAINAGE INLETS AND OUTLETS.
09/06/2006 SIGN - FINAL JYBARRA Approved IVRS - Inspection :*
09/07/2006 RIGHT OF WAY - FINAL PWHIDDON Approved CLEAR
11/15/2006 ELECTRIC - FINAL RHOLLAND Approved IVRS - Inspection :*
11/16/2006 TEP CLEARANCE - AM JWEATHER Approved ECO CLEARED FOR #100 PER R. HOLLANDER
02/08/2007 PERMIT FINALED LJACKSON Approved

Documents

File Name Document Type  
None CERT OF OCC VIEW