Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T05CM05367
Permit Details
Apply Date:
10/21/2005
Applicant:
KUYKENDALL ENTERPRISES INC , DAN
Description:
TI: GROCERY STORE
Contractors:
- KUYKENDALL ENTERPRISES INC , DAN
Permit Reviews
Permit Number - T05CM05367
Permit Status: C of o
Permit Description: TI: GROCERY STORE
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/28/2006 | 3RD PARTY REVIEW-REVISION/OTHER | 03/06/2006 | COMPLETED |
10/21/2005 | COMMERCIAL TI | 11/01/2005 | COMPLETED |
11/01/2005 | 3RD PARTY REVIEW-COMMERCIAL TI | 11/21/2005 | COMPLETED |
11/21/2005 | POST 3RD PARTY REVIEW | 11/28/2005 | COMPLETED |
11/28/2005 | RESUBMITTAL | 12/20/2005 | COMPLETED |
12/20/2005 | 3RD PARTY REVIEW-REVISION/OTHER | 12/20/2005 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T05CM05367
Permit Status: C of o
Permit Description: TI: GROCERY STORE
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
10/21/2005 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T05CM05367
Permit Description: TI: GROCERY STORE
Total Completed Inspections - 23
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/27/2005 | ELECTRIC - UNDERGROUND | RSUBA | Approved | IVRS - Inspection :* |
12/29/2005 | PLUMBING - ROUGH, SOIL | BBENEDON | Approved | IVRS - Inspection : See detailed listing on site.| 999* A STAMPED, SIGNED LETTER FROM ARCHITECT WILL BE REQUIRED FOR USE OF ABS. SWEEPS ARE REQUIRED FOR VERTICAL TO HORIZONTAL CHANGE OF DIRECTIONS. SEC. 910.3 REQUIRES THAT ANY BRANCH MORE THAN 15' IN LENGTH SHALL BE SEPARATELY VENTED 910.3 ALSO REQUIRES THAT THE MINIMUM AREA OF EVERY VENT INSTALLED IN A COMBINATION WASTE & VENT SYSTEM SHALL BE AT LEAST 1/2 OF THE CROSS SECTIONAL AREA OF THE DRAIN SERVED. SEC 910.6 - AN ACCESSIBLE CLEANOUT SHALL BE INSTALLED IN EACH VENT. SEC 910.5 - NO VERTICAL WASTE PIPE SHALL BE USED IN ANY SUCH SYSTEM SEC 905.2 - REQUIRES THAT EACH VENT SHALL HAVE ITS TAKEN OFF ABOVE THE DRAINAGE CENTER LINE. PROVIDE MIN 1% SLOPE ON 4" DWV PER PLAN FLOOR DRAIN IN RESTROOMS REQUIRE VENTING. |
01/17/2006 | FRAMING | LHANLY | Approved | IVRS - Inspection :* |
01/18/2006 | ELECTRIC - INTERMEDIATE | RSUBA | Approved | IVRS - Inspection :* |
01/23/2006 | BUILDING PRE-SLAB | LHANLY | Approved | IVRS - Inspection :* |
01/23/2006 | SHEET ROCK NAILING | LHANLY | Approved | IVRS - Inspection :* |
02/06/2006 | ELECTRIC - ABOVE CEILING | RSUBA | Approved | IVRS - Inspection :* |
02/08/2006 | PLUMBING - ABOVE CEILING | RRICH | Approved | IVRS - Inspection :* |
02/10/2006 | FIRE - FINAL | LTHOMAS | Approved | |
02/10/2006 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
02/10/2006 | BUILDING ABOVE CEILING | LHANLY | Approved | IVRS - Inspection :* |
02/13/2006 | HEALTH DEPT - FINAL 724-7908 | RPEYTON | Approved | |
02/13/2006 | RIGHT OF WAY - FINAL | PWHIDDON | Approved | PER EMAIL |
02/15/2006 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
02/21/2006 | ELECTRIC - FINAL | RSUBA | Approved | IVRS - Inspection :* |
03/09/2006 | PLUMBING - GAS PRESSURE TEST | RRICH | Approved | 1) 15 PSI TEST FROM METER TO BOILER ONLY FOR APPROVED PLAN ON GAS CARD AT METER |
03/16/2006 | MECHANICAL - FINAL | JMILITEL | Approved | PER INSP CARD |
03/16/2006 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | PER INSP CARD |
03/16/2006 | ENGINEERING - FINAL | NKALAHAR | Approved | PER INSP CARD |
03/16/2006 | PLUMBING - GAS PRESS TEST FNL | RRICH | Approved | PER INSP CARD |
03/16/2006 | PLUMBING - FINAL | RRICH | Approved | PER INSP CARD |
03/16/2006 | BUILDING - FINAL | RRICH | Approved | PER INSP CARD |
04/05/2006 | PERMIT FINALED | LJACKSON | Approved |