Permit: T05CM04175
Permit Details
Apply Date:
08/09/2005
Applicant:
METRO PERMIT EXPRESS, INC *C
Description:
NEW: MEDICAL OFFICE SHELL BLDG
Contractors:
- CHESTNUT CONSTRUCTION CORPORATIO
Permit Reviews
Permit Number - T05CM04175
Permit Status: Final
Permit Description: NEW: MEDICAL OFFICE SHELL BLDG
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/09/2005 | PLANS OK TO SUBMIT - 3RD PARTY | 09/19/2005 | COMPLETED |
| 09/15/2005 | PLANS OK TO SUBMIT - SITE | 09/15/2005 | COMPLETED |
| 09/19/2005 | SITE | 10/19/2005 | COMPLETED |
| 09/19/2005 | 3RD PARTY REVIEW-COMMERCIAL | 11/01/2005 | COMPLETED |
| 11/01/2005 | POST 3RD PARTY REVIEW | 02/07/2006 | COMPLETED |
| 11/03/2005 | SITE | 02/07/2006 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T05CM04175
Permit Status: Final
Permit Description: NEW: MEDICAL OFFICE SHELL BLDG
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 08/09/2005 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T05CM04175
Permit Description: NEW: MEDICAL OFFICE SHELL BLDG
Total Completed Inspections - 28
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/30/2005 | ELECTRIC - UNDERGROUND | CCLEMENS | Approved | IVRS - Inspection :*OK TO COVER UFER ( 20' BARE) |
| 12/30/2005 | EXCAVATION/LAYOUT REBAR & ZON | LHANLY | Approved | IVRS - Inspection :* 1) MAIN BLDG FOOTINGS OK, EXCEPT: SITE WALL LINE DIAMETER/A-F AND ELEVATOR SHAFT |
| 01/19/2006 | STEM WALL/RETAINING WALL | AQUIROZ | Approved | IVRS - Inspection :* |
| 04/02/2006 | BUILDING PRE-SLAB | AQUIROZ | Approved | IVRS - Inspection :* |
| 04/03/2006 | PLUMBING - ROUGH, SOIL | RMYERS | Approved | IVRS - Inspection :* |
| 04/17/2006 | SITE - SEWER | RMYERS | Approved | IVRS - Inspection :* |
| 05/03/2006 | ROOF NAILING | AQUIROZ | Approved | IVRS - Inspection :* |
| 05/25/2006 | STUCCO MESH | AQUIROZ | Approved | IVRS - Inspection :* |
| 06/14/2006 | PLUMBING - ROOF DRAINS | RMYERS | Approved | IVRS - Inspection :* |
| 07/12/2006 | RIGHT OF WAY - FINAL | MOTERO | Approved | PER EMAIL |
| 07/13/2006 | PLUMBING - YARD WTR LINE/TEST | RMYERS | Approved | IVRS - Inspection :* 1. YARDWATER OK 2. FINAL NOT READY |
| 07/19/2006 | U VALUE FOR WINDOW | AQUIROZ | Approved | IVRS - Inspection :* |
| 07/19/2006 | FIRE SPKLR - UG PIPING FLUSH | LTHOMAS | Approved | |
| 07/19/2006 | FIRE SPKLR - OH PIPING & HYDRO | LTHOMAS | Approved | |
| 07/19/2006 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
| 07/19/2006 | FIRE - FINAL | LTHOMAS | Approved | |
| 07/19/2006 | FIRE SPKLR - UG, PIPING, HYDRO | LTHOMAS | Approved | |
| 07/25/2006 | FRAMING | JBURGE | Approved | IVRS - Inspection :* |
| 07/25/2006 | REINFORCED MASONRY PRE-GROUT | JBURGE | Approved | IVRS - Inspection :* |
| 07/25/2006 | BUILDING - PROGRESS | JBURGE | Approved | IVRS - Inspection :* |
| 07/25/2006 | PLUMBING - FINAL | RMYERS | Approved | IVRS - Inspection :* 1. PLUMBING FINAL OK 2. SHELL COMPLETE |
| 08/10/2006 | ELECTRIC - TEMP POWER FOR TEST | CCLEMENS | Approved | PER EL FINAL |
| 08/10/2006 | ELECTRIC - FINAL | CCLEMENS | Approved | IVRS - Inspection :* |
| 08/10/2006 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
| 08/11/2006 | LANDSCAPE - FINAL | ACONNOR | Approved | |
| 08/11/2006 | ENGINEERING - FINAL | MRUSSO | Approved | |
| 08/14/2006 | SHEET ROCK NAILING | JBURGE | Approved | PER BU FINAL |
| 08/14/2006 | BUILDING - FINAL | JBURGE | Approved | PER INSP COPY |