Inspection History Details
Inspection Status: Approved
Inspection History: ENGINEERING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/11/2006 | ENGINEERING - FINAL | Approved | ||
| 07/26/2006 | ENGINEERING - FINAL | Partial Approval | PARTIAL APPROVAL FOR C OF O FOR ENGINEERING, PERMANENT C OF O NOT TO BE GIVEN UNTIL THE PUCHLIST BELOW IS COMPLETED: 1) INSTALL WALL OPENINGS ALONG EAST COURTYARD PER PLAN. 2) COMPLETE PARKING AREA STRIPING. 3) INSTALL H.C. SIGNS FOR ALL H.C. PARKING FOR YOUR BLDG. 4) RE-INSTALL HAND RAILING FOR H.C. ACCESS AT SE ENTRANCE TO ALLOW A MIN 36" 5) REPAIR SIDEWALK AT EAST ENTRANCE 6) STABILIZE EAST ENTRANCE COURTYARD 7) STABILIZE SLOPE ADJACENT TO H.C RAMP TO PREVENT DRAINAGE OVER RAMP. |
|
| 07/24/2006 | ENGINEERING - FINAL | Denied | COMPLETE ALL SITE WORK. CLEAN UP AND REMOVE ALL CONSTRUCTION MATERIAL AND DEBRIS. |