Permit: T05CM01744
Permit Details
Apply Date:
04/20/2005
Applicant:
N/A
Description:
NEW OFFICE BUILDING
Contractors:
- VENTURE WEST INC
Permit Reviews
Permit Number - T05CM01744
Permit Status: Final
Permit Description: NEW OFFICE BUILDING
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/18/2006 | 3RD PARTY REVIEW-REVISION/OTHER | 02/22/2006 | COMPLETED |
| 04/10/2006 | 3RD PARTY REVIEW-REVISION/OTHER | 04/19/2006 | COMPLETED |
| 04/18/2006 | 3RD PARTY REVIEW-REVISION/OTHER | 07/24/2006 | COMPLETED |
| 04/20/2005 | PLANS OK TO SUBMIT - COMM | 04/20/2005 | COMPLETED |
| 04/20/2005 | 3RD PARTY REVIEW-COMMERCIAL | 05/20/2005 | COMPLETED |
| 05/20/2005 | POST 3RD PARTY REVIEW | 06/21/2005 | COMPLETED |
| 07/12/2006 | OTHER | 07/12/2006 | COMPLETED |
| 07/17/2006 | 3RD PARTY REVIEW-REVISION/OTHER-2ND | 08/16/2006 | COMPLETED |
| 10/18/2005 | 3RD PARTY REVIEW-REVISION/OTHER | 10/25/2005 | COMPLETED |
| 11/15/2005 | 3RD PARTY REVIEW-REVISION/OTHER | 11/17/2005 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T05CM01744
Permit Status: Final
Permit Description: NEW OFFICE BUILDING
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 04/20/2005 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T05CM01744
Permit Description: NEW OFFICE BUILDING
Total Completed Inspections - 33
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/03/2005 | ELECTRIC - UFER | RHOLLAND | Approved | IVRS - Inspection :* 1) OK 3-4/0 TO REBAR |
| 09/20/2005 | SITE - SEWER | TRINIVJR | Approved | IVRS - Inspection :* |
| 10/04/2005 | PLUMBING - ROUGH, SOIL | TRINIVJR | Approved | DWV WATER TEST IS OK UNDERGROUND RWL WATER TEST IS OK OK TO BACKFILL TRENCH. IVRS - Inspection :* |
| 10/04/2005 | PLUMBING - ROOF DRAINS | TRINIVJR | Approved | IVRS - Inspection :* |
| 11/15/2005 | EXCAVATION/LAYOUT REBAR & ZON | JCAGLE | Approved | F 10 FOOTING AT EAST 1/2 ?? SHELL # 103, NEED 135 DEGREE HOOKS PER DETAIL 107 |
| 11/28/2005 | ELECTRIC - UNDERGROUND | RHOLLAND | Approved | IVRS - Inspection :* 1) OK 6 GROUND RODS AND CADWELDS UNDER SLAB 2) OK 1 FLOOR BOX ASSEMBLY UNDER SLAB |
| 11/30/2005 | BUILDING PRE-SLAB | JCAGLE | Approved | IVRS - Inspection :*SOUTH HALF OF SHELL # 103 |
| 12/29/2005 | REINFORCED MASONRY PRE-GROUT | JCAGLE | Approved | IVRS - Inspection :* LINES 1-5/K.5-N, 10.5-13/A-D, 1/N-Q (11' 4" - 13' 4") WALLS/COLUMNS @ LINES 11/S-V & SOUTH STAIRS (4'8" - 8'8") |
| 05/16/2006 | PLUMBING - YARD WTR LINE/TEST | RMYERS | Approved | IVRS - Inspection :* |
| 06/13/2006 | PLUMBING - PROGRESS | BBENEDON | Approved | IVRS - Inspection :* CLOSET FLANGES OK SHOWERS OK RUN TEST |
| 06/13/2006 | PLUMBING - INTERMEDIATE | BBENEDON | Approved | IVRS - Inspection :* |
| 06/22/2006 | SHEET ROCK NAILING | JBURGE | Approved | IVRS - Inspection :* |
| 06/22/2006 | STUCCO MESH | JBURGE | Approved | IVRS - Inspection :* |
| 06/22/2006 | ROOF NAILING | JBURGE | Approved | IVRS - Inspection :* |
| 06/22/2006 | EXT METAL CLIPS/EXT SHEATHING | JBURGE | Approved | IVRS - Inspection :* |
| 06/22/2006 | FIRE SPKLR - UG PIPING FLUSH | LTHOMAS | Approved | |
| 06/22/2006 | FIRE SPKLR - UG, PIPING, HYDRO | LTHOMAS | Approved | |
| 06/30/2006 | TEP CLEARANCE - AM | JWEATHER | Approved | TMPP CLEARED FOR OWNERS METER PER R. HOLLANDER |
| 07/14/2006 | BUILDING - PROGRESS | JBURGE | Approved | IVRS - Inspection :* |
| 07/14/2006 | U VALUE FOR WINDOW | JBURGE | Approved | IVRS - Inspection :* |
| 07/14/2006 | FRAMING | JBURGE | Approved | IVRS - Inspection :* |
| 07/17/2006 | ELECTRIC - OUTDOOR LIGHTING | RHOLLAND | Approved | IVRS - Inspection :* |
| 07/17/2006 | ELECTRIC - PROGRESS | RHOLLAND | Approved | IVRS - Inspection :* |
| 07/17/2006 | ELECTRIC - CABLE DROP | RHOLLAND | Approved | IVRS - Inspection :* |
| 07/17/2006 | ELECTRIC - INTERMEDIATE | RHOLLAND | Approved | IVRS - Inspection :* |
| 07/17/2006 | FIRE SPKLR - OH PIPING & HYDRO | LTHOMAS | Approved | |
| 07/19/2006 | PLUMBING - FINAL | RMYERS | Approved | IVRS - Inspection :* PLUMBING FINAL OK OK FOR C OF O S.T.O.I |
| 07/19/2006 | FIRE - FINAL | LTHOMAS | Approved | |
| 07/19/2006 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
| 07/19/2006 | ELECTRIC - TEMP POWER FOR TEST | RHOLLAND | Approved | IVRS - Inspection :* |
| 07/20/2006 | OUTDOOR LIGHTING FINAL | RHOLLAND | Approved | IVRS - Inspection :* |
| 07/20/2006 | ELECTRIC - FINAL | RHOLLAND | Approved | IVRS - Inspection :* |
| 07/21/2006 | BUILDING - FINAL | JBURGE | Approved | IVRS - Inspection :* |