Inspection History Details
Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/22/2006 | EXCAVATION/LAYOUT REBAR & ZON | Approved | IVRS - Inspection :* | |
| 11/15/2005 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | F 10 FOOTING AT EAST 1/2 ?? SHELL # 103, NEED 135 DEGREE HOOKS PER DETAIL 107 | |
| 08/25/2005 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* OK TO POUR WHEN SPEC INSP CONFIRMS 1) FINISH VERTICALS AT ELEVATOR PIT AND FOR MASENRY WALLS LINE 15.5 AND LINE Q.5 2) BULK HEAD AT LAST 6' AT F10 FOOTINGS |
|
| 08/16/2005 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) WEST PERIMETER 2) NOTE: GRID LINE 14 AND GRID LINE A NORTH SECTION DO NOT POUR UNTIL WATER LINE ISSUE IS RESLOVED |
|
| 08/10/2005 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) GL 16-23; A-L PERIMETER FOOTINGS OK TO POUR |
|
| 08/03/2005 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) C1 F3 AND C3 F4 SPREAD FOOTINGS OK |
|
| 08/02/2005 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection |