Permit: T05CM00653
Permit Details
Apply Date:
02/14/2005
Applicant:
N/A
Description:
NEW:VEHICLE MAINTENANCE BUILDING
Architects:
- BROOKS, ROGER WILLIAM
Contractors:
- TUCSON UNIFIED SCHOOL DIST #1
- CORONA SIERRA INC ,
Permit Reviews
Permit Number - T05CM00653
Permit Status: C of o
Permit Description: NEW:VEHICLE MAINTENANCE BUILDING
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/14/2005 | PLANS OK TO SUBMIT - COMM | 02/14/2005 | COMPLETED |
| 02/14/2005 | PLANS OK TO SUBMIT - SITE | 02/14/2005 | COMPLETED |
| 02/14/2005 | 3RD PARTY REVIEW-COMMERCIAL | 03/28/2005 | COMPLETED |
| 03/28/2005 | POST 3RD PARTY REVIEW | 05/09/2005 | COMPLETED |
| 04/04/2005 | SITE | 05/09/2005 | COMPLETED |
| 05/09/2006 | 3RD PARTY REVIEW-REVISION/OTHER | 07/05/2006 | COMPLETED |
| 05/25/2005 | RESUBMITTAL - SITE | 07/01/2005 | COMPLETED |
| 05/26/2005 | RESUBMITTAL | 05/26/2005 | COMPLETED |
| 06/29/2005 | RESUBMITTAL | 07/01/2005 | COMPLETED |
| 07/12/2006 | OTHER | 07/12/2006 | COMPLETED |
| 07/21/2005 | 3RD PARTY REVIEW-REVISION/OTHER | 08/08/2005 | COMPLETED |
| 08/08/2005 | POST 3RD PARTY REVIEW | 08/09/2005 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T05CM00653
Permit Status: C of o
Permit Description: NEW:VEHICLE MAINTENANCE BUILDING
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 02/14/2005 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T05CM00653
Permit Description: NEW:VEHICLE MAINTENANCE BUILDING
Total Completed Inspections - 40
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/16/2005 | SITE - SEWER | RRICH | Approved | IVRS - Inspection :* 4" REROUTE OF OIL SEPERATOR DRAINAGE WATER TEST OK |
| 09/28/2005 | BUILDING PRE-SLAB | AMATHIES | Approved | IVRS - Inspection :* |
| 11/14/2005 | EXCAVATION/LAYOUT REBAR & ZON | AMATHIES | Approved | IVRS - Inspection :*PERIMETER WALL FTGS OK |
| 12/13/2005 | REINFORCED MASONRY PRE-GROUT | AMATHIES | Approved | IVRS - Inspection :* 1) 2ND LIFT OK |
| 12/23/2005 | ELECTRIC - UNDERGROUND | RMAJUTA | Approved | PARTIAL OK TO COVER CLOSURE AREAS IN SHOP BLDG, CLOSURE POUR |
| 12/23/2005 | PLUMBING - ROUGH, SOIL | RMYERS | Approved | IVRS - Inspection :*PLEASE LEAVE A NAME AND CONTACT NUMBER WHEN SCHEDULING THIS INSPECTION. NO ADDRESS POSTED NO PERMITS POSTED PLANS NOT IDENTIFIED BY ACTIVITY NUMBER N/C CAST IRON WITH HUSKEE BANDS, AS HIGHLIGHTED ON PLAN OK TO COVER-WATER TEST ONE RISER TO TEN FEET. |
| 12/23/2005 | ELECTRIC - INTERMEDIATE | RMAJUTA | Approved | IVRS - Inspection :* |
| 12/29/2005 | ELECTRIC - PROGRESS | DSANTACR | Approved | IVRS - Inspection :* OK U.G. SECONDARY'S & COMM. CONDUITS FROM BUILDING TO 2ND 45 DEGREE BEND OUTSIDE. |
| 02/17/2006 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* |
| 05/17/2006 | ROOF NAILING | LHANLY | Approved | IVRS - Inspection :* |
| 05/17/2006 | SHEET ROCK NAILING | LHANLY | Approved | IVRS - Inspection :* |
| 06/16/2006 | ELECTRIC - FINAL | DSANTACR | Approved | IVRS - Inspection :* GOOD JOB! NICE WORK! |
| 06/16/2006 | OUTDOOR LIGHTING FINAL | DSANTACR | Approved | IVRS - Inspection :* |
| 06/16/2006 | ELECTRIC - OUTDOOR LIGHTING | DSANTACR | Approved | IVRS - Inspection :* |
| 06/16/2006 | ELECTRIC - CONSTRUCTION POWER | DSANTACR | Approved | IVRS - Inspection :* |
| 06/16/2006 | ELECTRIC - ABOVE CEILING | DSANTACR | Approved | IVRS - Inspection :* |
| 06/20/2006 | MECHANICAL - ABOVE CEILING | CWILLIAM | Approved | |
| 06/20/2006 | MECHANICAL - FINAL | CWILLIAM | Approved | IVRS - Inspection :* |
| 06/26/2006 | FRAMING | LHANLY | Approved | IVRS - Inspection :* |
| 06/26/2006 | U VALUE FOR WINDOW | LHANLY | Approved | IVRS - Inspection :* |
| 06/26/2006 | BUILDING ABOVE CEILING | LHANLY | Approved | IVRS - Inspection :* |
| 06/28/2006 | FIRE - FINAL | LTHOMAS | Approved | |
| 06/28/2006 | PLUMBING - GAS PRESS TEST FNL | BBENEDON | Approved | IVRS - Inspection :* |
| 06/28/2006 | PLUMBING - GAS PRESSURE TEST | BBENEDON | Approved | IVRS - Inspection :* |
| 06/28/2006 | FIRE SPKLR - UG, PIPING, HYDRO | LTHOMAS | Approved | |
| 06/28/2006 | FIRE SPKLR - UG PIPING FLUSH | LTHOMAS | Approved | |
| 06/28/2006 | FIRE SPKLR - OH PIPING & HYDRO | LTHOMAS | Approved | |
| 06/28/2006 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
| 06/28/2006 | SIGN - FINAL | LTHOMAS | Approved | |
| 06/28/2006 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
| 06/29/2006 | PLUMBING - YARD WTR LINE/TEST | BBENEDON | Approved | IVRS - Inspection :* |
| 06/29/2006 | PLUMBING - ABOVE CEILING | BBENEDON | Approved | IVRS - Inspection :* |
| 06/29/2006 | PLUMBING - INTERMEDIATE | BBENEDON | Approved | IVRS - Inspection :* |
| 06/30/2006 | PLUMBING - PROGRESS | RLEDONNE | Approved | |
| 06/30/2006 | BUILDING - PROGRESS | AALEGRIA | Approved | |
| 06/30/2006 | PLUMBING - FINAL | RLEDONNE | Approved | IVRS - Inspection :* |
| 06/30/2006 | BUILDING - FINAL | AALEGRIA | Approved | IVRS - Inspection :* |
| 07/03/2006 | RIGHT OF WAY - FINAL | LLOPEZ | Approved | PER EMAIL |
| 07/05/2006 | ENGINEERING - FINAL | DROBERTS | Approved | ALL REMAINING CONCRETE HAS BEEN COMPLETED AT THIS TIME. ADDITIONAL ASPHALT AROUND THIS SITE WILL BE DONE AT A LATER DATE BY ANOTHER CONTRACT AS APPROVED ON THE PLANS FOR THIS SITE. |
| 07/06/2006 | PERMIT FINALED | JMORALES | Approved |