Permit: T04CM05246
Permit Details
Apply Date:
12/02/2004
Applicant:
N/A
Description:
TI: NAIL SALON REVISION TO STRUCTURAL DETAIL ON DRAWING A-1.1
Contractors:
- CUSTOM TECH DESIGN AND C T SIGNS
Permit Reviews
Permit Number - T04CM05246
Permit Status: C of o
Permit Description: TI: NAIL SALON
REVISION TO STRUCTURAL DETAIL ON DRAWING A-1.1
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/21/2005 | COMMERCIAL TI | 01/21/2005 | COMPLETED |
02/09/2006 | REVISION - WALK THRU | 02/09/2006 | COMPLETED |
03/14/2005 | RESUBMITTAL | 08/08/2005 | COMPLETED |
10/10/2005 | REVISION - WALK THRU | 10/10/2005 | COMPLETED |
12/02/2004 | COMMERCIAL TI | 12/16/2004 | COMPLETED |
12/03/2004 | COMMERCIAL TI | 02/01/2005 | COMPLETED |
12/16/2004 | COMMERCIAL TI | 01/21/2005 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T04CM05246
Permit Status: C of o
Permit Description: TI: NAIL SALON
REVISION TO STRUCTURAL DETAIL ON DRAWING A-1.1
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
12/02/2004 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T04CM05246
Permit Description: TI: NAIL SALON
REVISION TO STRUCTURAL DETAIL ON DRAWING A-1.1
Total Completed Inspections - 25
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/03/2005 | ELECTRIC - UNDERGROUND | RMAJUTA | Approved | IVRS - Inspection :* |
05/05/2005 | PLUMBING - ROUGH, SOIL | TRINIVJR | Approved | IVRS - Inspection :* 1) SOIL WATER TEST IS OK 2) P.O.C. OF NEW BLDG DRAIN TO EXISTING BLDG DRAIN IS OK 3) NOTE: 4" FLOOR CLEANOUT IS LOCATED ON OPPISITE SIDE OF WALL 4) SHALL REMOVE BLAKE TEST TEE LOCATED UNDER SLAB AND REPLACE WITH SOLID 4" PIPE. NO THREADED FITTING MAY BE LOCATED IN A NON ACCESSIBLE LOCATION 5) OK TO BACKFILL TRENCH |
08/09/2005 | FRAMING | LHANLY | Approved | IVRS - Inspection :* |
09/27/2005 | ELECTRIC - INTERMEDIATE | RSUBA | Approved | IVRS - Inspection :* |
09/28/2005 | SHEET ROCK NAILING | LHANLY | Approved | IVRS - Inspection :* |
10/28/2005 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :*PROVIDE A WORKING PLATFORM TO SERVICE FAN COIL. STILL NEED TO CHECK FUSES, DATA PLATE, DUCT SMOKE DETECTORS CONDENSOR. OK FOR CEILING TILES. |
10/28/2005 | PLUMBING - INTERMEDIATE | RRICH | Approved | IVRS - Inspection :* |
10/28/2005 | PLUMBING - ABOVE CEILING | RRICH | Approved | IVRS - Inspection :* |
10/31/2005 | TEP CLEARANCE - PM | JKOZUCH | Approved | ECO |
10/31/2005 | ELECTRIC - ABOVE CEILING | RSUBA | Approved | IVRS - Inspection :* |
10/31/2005 | ELECTRIC - TEMP POWER FOR TEST | RSUBA | Approved | IVRS - Inspection :* |
11/01/2005 | TEP CLEARANCE - AM | RMAJUTA | Approved | OK TEMP POWER PER SUBA |
11/03/2005 | MECHANICAL - INTERMEDIATE | CWILLIAM | Approved | PER MECH FINAL |
11/03/2005 | BUILDING - FINAL | AMATHIES | Approved | IVRS - Inspection :* |
11/03/2005 | MECHANICAL - FINAL | CWILLIAM | Approved | IVRS - Inspection :* |
11/03/2005 | RIGHT OF WAY - FINAL | LLOPEZ | Approved | PER EMAIL |
11/04/2005 | ENGINEERING - FINAL | DROBERTS | Approved | PER INSP COPY |
11/04/2005 | PLUMBING - FINAL | RRICH | Approved | PER INSP CARD . PER APPROVED REVISED PLAN |
11/04/2005 | PLUMBING - PROGRESS | RRICH | Approved | PER INSP CARD |
11/04/2005 | ELECTRIC - UFER | RMAJUTA | Approved | PER ELEC FINAL |
11/04/2005 | ELECTRIC - FINAL | RMAJUTA | Approved | PER INSP COPY |
11/04/2005 | FIRE - FINAL | LTHOMAS | Approved | |
11/04/2005 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
11/04/2005 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
11/09/2005 | PERMIT FINALED | LJACKSON | Approved |