Permit: T04CM04804
Permit Details
Apply Date:
11/01/2004
Applicant:
ROGER BROOKS
Description:
NEW:BATH HOUSE/SITE WORK POOL AREA & DECK = 10,918 SQ.FT BLDG. = 3723
Contractors:
- LLOYD CONSTRUCTION COMPANY INC ,
Permit Reviews
Permit Number - T04CM04804
Permit Status: C of o
Permit Description: NEW:BATH HOUSE/SITE WORK
POOL AREA & DECK = 10,918 SQ.FT
BLDG. = 3723
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/06/2005 | RESUBMITTAL | 02/04/2005 | COMPLETED |
01/28/2004 | RESUBMITTAL - SITE | 02/04/2005 | COMPLETED |
02/14/2005 | RESUBMITTAL | 03/21/2005 | COMPLETED |
04/13/2006 | REVISION - SITE | 04/14/2006 | COMPLETED |
07/29/2005 | REVISION | 08/18/2005 | COMPLETED |
11/01/2004 | PLANS OK TO SUBMIT - COMM | 11/01/2004 | COMPLETED |
11/01/2004 | PLANS OK TO SUBMIT - SITE | 11/01/2004 | COMPLETED |
11/02/2004 | COMMERCIAL NEW | 12/20/2004 | COMPLETED |
11/02/2004 | SITE | 12/20/2004 | COMPLETED |
Completed Inspections
Permit Status: C of o
Permit Number: T04CM04804
Permit Description: NEW:BATH HOUSE/SITE WORK
POOL AREA & DECK = 10,918 SQ.FT
BLDG. = 3723
Total Completed Inspections - 35
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/06/2005 | ELECTRIC - UFER | DSANTACR | Approved | IVRS - Inspection :* OK UFER FOR SERVICE & X FORMER. |
05/12/2005 | PLUMBING - SEWER HCS CONNECT | TRINIVJR | Approved | IVRS - Inspection :* 1) SITE SEWER AIR PRESSURE TEST IS OK MIN 5 LB. 2) HCS CONNECTION IS OK. 3) OK TO BACKFILL TRENCH. 4) SHALL SEE INSTALLATION OF BACK WATER VALVE |
05/17/2005 | SITE - SEWER | TRINIVJR | Approved | IVRS - Inspection :* 1) BACKWATER VALVE HAS BEEN INSTALLED. 2) OK TO BACKFILL TRENCH. |
06/28/2005 | PLUMBING - ROUGH, SOIL | TRINIVJR | Approved | IVRS - Inspection :* 1) ALL DWV RISERS HAVE BEEN WRAPED. 2) OK FOR CONCRETE. |
06/28/2005 | BUILDING PRE-SLAB | AMATHIES | Approved | IVRS - Inspection :* WOMEN/MENS LIFEGUARD EQUIP |
09/21/2005 | REINFORCED MASONRY PRE-GROUT | AMATHIES | Approved | IVRS - Inspection :* |
09/21/2005 | STEM WALL/RETAINING WALL | AMATHIES | Approved | IVRS - Inspection :* |
09/21/2005 | EXCAVATION/LAYOUT REBAR & ZON | AMATHIES | Approved | IVRS - Inspection :* |
10/14/2005 | PLUMBING - PROGRESS | RRICH | Approved | IVRS - Inspection :* 1) WASTE AND VENT WATER TEST THRU ROOF ALL AREAS OK 2) H20 PIPING THRU BLDG OK 3) PROVIDE INSULATION ON ALL HOT WATER PIPING 4) TERMINATE FLUSH VALVE SUPPLYS FOR STOOLS 5) CALL IN ALL PLUMBING INSPECTIONS THAT HAVE NOT BEEN APPROVED |
10/25/2005 | ELECTRIC - OUTDOOR LIGHTING | DSANTACR | Approved | IVRS - Inspection :* |
10/28/2005 | PLUMBING - YARD WTR LINE/TEST | RRICH | Approved | 3" H20 CONNECTION TO BUILDING AT EXTERIOR OK |
11/14/2005 | ELECTRIC - UNDERGROUND | RMAJUTA | Approved | IVRS - Inspection :*MECH YARD-??FOR SPRAY ???AND MECH SLIDE.OK TO COVER |
11/15/2005 | PLUMBING - GAS PRESSURE TEST | CWILLIAM | Approved | IVRS - Inspection :*CORRECTIONS OK 65 PSI |
01/03/2006 | PLUMBING - ABOVE CEILING | BBENEDON | Approved | IVRS - Inspection :* |
01/03/2006 | PLUMBING - INTERMEDIATE | BBENEDON | Approved | IVRS - Inspection :* |
01/27/2006 | ELECTRIC - ABOVE CEILING | DSANTACR | Approved | IVRS - Inspection :* |
01/27/2006 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection :* |
02/07/2006 | MECHANICAL - ABOVE CEILING | CWILLIAM | Approved | PER FINAL |
02/07/2006 | MECHANICAL - FINAL | CWILLIAM | Approved | IVRS - Inspection :* |
02/07/2006 | MECHANICAL - INTERMEDIATE | CWILLIAM | Approved | IVRS - Inspection :* |
02/09/2006 | ELECTRIC - FINAL | RSUBA | Approved | IVRS - Inspection :* |
02/23/2006 | SHEET ROCK NAILING | LHANLY | Approved | IVRS - Inspection :*NOT APPLICABLE |
02/23/2006 | EXT METAL CLIPS/EXT SHEATHING | LHANLY | Approved | IVRS - Inspection :*NOT APPICABLE |
03/02/2006 | PLUMBING - FINAL | BBENEDON | Approved | IVRS - Inspection :* |
03/03/2006 | BUILDING ABOVE CEILING | LHANLY | Approved | IVRS - Inspection :* APPROVED PER ENGINEER |
03/03/2006 | ROOF NAILING | LHANLY | Approved | IVRS - Inspection :* COVERED WITHOUT INSPECTION |
03/03/2006 | BUILDING - FINAL | LHANLY | Approved | IVRS - Inspection :* |
03/03/2006 | FRAMING | LHANLY | Approved | IVRS - Inspection :* |
03/06/2006 | FIRE - FINAL | JDAVIS | Approved | |
03/07/2006 | RIGHT OF WAY - FINAL | LLOPEZ | Approved | PER EMAIL |
03/16/2006 | SIGN - FINAL | JYBARRA | Approved | |
03/28/2006 | NPPO - FINAL | ACONNOR | Approved | |
03/28/2006 | LANDSCAPE - FINAL | ACONNOR | Approved | |
04/19/2006 | ENGINEERING - FINAL | MAVERY | Approved | Contractor completed punch list and stabilized area around project. |
04/28/2006 | PERMIT FINALED | LJACKSON | Approved |