Permit Reviews

Permit Number - T04CM04523
Permit Status: C of o
Permit Description: TI:OFFICE
Start Date Submittal Complete Date Status  
01/28/2005 3RD PARTY REVIEW-REVISION/OTHER 02/01/2005 COMPLETED Review Details
02/01/2005 POST 3RD PARTY REVIEW 02/02/2005 COMPLETED Review Details
03/24/2005 3RD PARTY REVIEW-REVISION/OTHER 04/26/2005 COMPLETED Review Details
10/11/2004 PLANS OK TO SUBMIT - 3RD PARTY 10/12/2004 COMPLETED Review Details
10/12/2004 3RD PARTY REVIEW-COMMERCIAL TI 11/12/2004 COMPLETED Review Details
11/12/2004 POST 3RD PARTY REVIEW 11/12/2004 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T04CM04523
Permit Status: C of o
Permit Description: TI:OFFICE
Total Outstanding Activity Conditions - 1
Date Name
10/11/2004 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T04CM04523
Permit Description: TI:OFFICE
Total Completed Inspections - 38
Date Description Inspector Results Comments
12/20/2004 EXCAVATION/LAYOUT REBAR & ZON AMATHIES Approved IVRS - Inspection :*
1) INTERIOR FTGS OK
12/28/2004 PLUMBING - PROGRESS TRINIVJR Approved IVRS - Inspection :*/1)2ND FLOOR OVERHEAD WATER DISTRIBUTION IS OK UP TO FINAL CONNECTION TO EXSISTING 2" C.W.
12/29/2004 PLUMBING - INTERMEDIATE RRICH Approved IVRS - Inspection :*/WATER TEST WSTE & VENT FROM 4" DRAIN OVERHEAD 1ST FLOOR UP THRU SHOWER 245, MENS RESTROOM 246, WOMENS REST ROOM STOOL AREA (ONLY) 248, JANITOR 247 UP TO 3" UNIT AT FUTURE 4" THRU ROOF OK
12/29/2004 ELECTRIC - UNDERGROUND RSUBA Approved IVRS - Inspection :*
02/24/2005 PLUMBING - ROUGH, SOIL TRINIVJR Approved IVRS - Inspection :*
02/24/2005 MECHANICAL - PROGRESS CWILLIAM Approved IVRS - Inspection :*
03/09/2005 ELECTRIC - INTERMEDIATE DSANTACR Approved IVRS - Inspection :* APPROVED
04/26/2005 ROOF NAILING AMATHIES Approved IVRS - Inspection :*
04/26/2005 BUILDING PRE-SLAB AMATHIES Approved IVRS - Inspection :*
05/04/2005 U VALUE FOR WINDOW AMATHIES Approved IVRS - Inspection :*
05/04/2005 FRAMING AMATHIES Approved IVRS - Inspection :*
05/09/2005 ELECTRIC - CONSTRUCTION POWER DSANTACR Approved IVRS - Inspection :* OK TO CLEAR TEMP POWER
05/09/2005 ELECTRIC - TEMP POWER FOR TEST DSANTACR Approved OK FOR TEMP POWER WHEN BOND IS POSTED
05/09/2005 SHEET ROCK NAILING AMATHIES Approved IVRS - Inspection :*
05/10/2005 TEP CLEARANCE - AM JKOZUCH Approved ECO
05/23/2005 PLUMBING - ROOF DRAINS TRINIVJR Approved IVRS - Inspection :*
06/01/2005 PLUMBING - ABOVE CEILING TRINIVJR Approved IVRS - Inspection :* 1) ABOVE CEILING IS OK FOR GRID & TILE
06/07/2005 BUILDING ABOVE CEILING AMATHIES Approved IVRS - Inspection :* N OF EXP OK
06/07/2005 EXT METAL CLIPS/EXT SHEATHING AMATHIES Approved IVRS - Inspection :*
07/01/2005 ELECTRIC - ABOVE CEILING DSANTACR Approved IVRS - Inspection :*
07/15/2005 BUILDING - PROGRESS AMATHIES Approved IVRS - Inspection :*
07/15/2005 ELECTRIC - PROGRESS DSANTACR Approved IVRS - Inspection :*
07/18/2005 ENGINEERING - FINAL MAVERY Approved Keep construction material inside fenced area.
07/18/2005 OUTDOOR LIGHTING FINAL DSANTACR Approved IVRS - Inspection :*
07/18/2005 FIRE - FINAL LTHOMAS Approved
07/18/2005 FIRE SPKLR - FINAL LTHOMAS Approved
07/18/2005 FIRE SPKLR - OH PIPING & HYDRO LTHOMAS Approved
07/19/2005 SIGN - FINAL JYBARRA Approved IVRS - Inspection :*
09/09/2005 ELECTRIC - FINAL DSANTACR Approved IVRS - Inspection :*
1) OK C OF O
09/09/2005 MECHANICAL - FINAL CWILLIAM Approved IVRS - Inspection :*
1) UNIT #1-25 AMPS
09/09/2005 PLUMBING - FINAL TRINIVJR Approved IVRS - Inspection :*
1) PLUMBING FINAL IS OK
2) OK FOR C OF O
09/09/2005 MECHANICAL - INTERMEDIATE CWILLIAM Approved
09/09/2005 MECHANICAL - ABOVE CEILING CWILLIAM Approved
09/09/2005 MECHANICAL - HOODS CWILLIAM Approved
09/09/2005 REINFORCED MASONRY PRE-GROUT AMATHIES Approved
09/09/2005 STEM WALL/RETAINING WALL AMATHIES Approved
09/09/2005 BUILDING - FINAL AMATHIES Approved IVRS - Inspection :*
09/20/2005 PERMIT FINALED KMEDINA Approved

Documents

File Name Document Type  
C OF O_10-03-2005.TIF CERT OF OCC VIEW
SOILREPORT.TIF DOCUMENTS VIEW
MASONRYINSPREPORT.TIF DOCUMENTS VIEW
STRUCCALCSBULKTANK.TIF DOCUMENTS VIEW
STRUCCALCSMEZZANINE.TIF DOCUMENTS VIEW
None DOCUMENTS VIEW