Permit: T04CM03057
Permit Details
Status:
C of o
Type:
COMMERCIAL NEW
Address:
10701 E MARY ANN CLEVELAND WY 01
Address NEW:
10701 E MARY ANN CLEVELAND WY 01
Apply Date:
07/02/2004
Applicant:
LIZ SPIEWAK
Description:
NEW:HIGH SCHOOL ADMINISTRATION OFFICES
Contractors:
- LLOYD CONSTRUCTION COMPANY INC ,
Permit Reviews
Permit Number - T04CM03057
Permit Status: C of o
Permit Description: NEW:HIGH SCHOOL ADMINISTRATION OFFICES
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/19/2005 | 3RD PARTY REVIEW-REVISION/OTHER | 01/20/2005 | COMPLETED |
| 01/20/2005 | POST 3RD PARTY REVIEW | 01/20/2005 | COMPLETED |
| 03/07/2005 | 3RD PARTY REVIEW-REVISION/OTHER | 03/09/2005 | COMPLETED |
| 04/07/2005 | 3RD PARTY REVIEW-REVISION/OTHER | 04/11/2005 | COMPLETED |
| 04/11/2005 | POST 3RD PARTY REVIEW | 04/12/2005 | COMPLETED |
| 07/02/2004 | PLANS OK TO SUBMIT - 3RD PARTY | 07/02/2004 | COMPLETED |
| 07/02/2004 | PLANS OK TO SUBMIT - SITE | 07/02/2004 | COMPLETED |
| 07/02/2004 | 3RD PARTY REVIEW-COMMERCIAL | 08/27/2004 | COMPLETED |
| 07/06/2004 | SITE | 08/03/2004 | COMPLETED |
| 08/20/2004 | RESUBMITTAL - SITE | 10/07/2004 | COMPLETED |
| 08/27/2004 | POST 3RD PARTY REVIEW | 09/29/2004 | COMPLETED |
| 09/29/2004 | RESUBMITTAL | 10/07/2004 | COMPLETED |
| 10/22/2004 | 3RD PARTY REVIEW-REVISION/OTHER | 11/01/2004 | COMPLETED |
| 11/08/2004 | 3RD PARTY REVIEW-REVISION/OTHER | 11/09/2004 | COMPLETED |
| 11/09/2004 | REVISION | 11/15/2004 | COMPLETED |
| 12/07/2004 | 3RD PARTY REVIEW-REVISION/OTHER | 12/13/2004 | COMPLETED |
| 12/28/2004 | 3RD PARTY REVIEW-REVISION/OTHER | 12/30/2004 | COMPLETED |
| 12/28/2004 | 3RD PARTY REVIEW-REVISION/OTHER-2ND | 01/11/2005 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T04CM03057
Permit Status: C of o
Permit Description: NEW:HIGH SCHOOL ADMINISTRATION OFFICES
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 07/02/2004 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T04CM03057
Permit Description: NEW:HIGH SCHOOL ADMINISTRATION OFFICES
Total Completed Inspections - 42
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/14/2004 | PLUMBING - ROUGH, SOIL | RRICH | Approved | IVRS - Inspection :* 8"PVC SDR 35 FROM MANHOLE #9 (EXISTING) TO MANHOLE #1 (NOW) & FROM MANHOLE #1 EAST APP 100' OK. PERMITS ALL W/ 03055 CALL OUT BCD 1-4. WILL NEED VERIFICATION OF GRADE ON ALL SITE SEWER. WILL NEED AIR PRESSURE TEST @ LATER DATE. WILL NEED VACUUM TEST @ LATER DATE. NEED PDEQ CERTIFICATE OF CONFORMANCE. NEED TO VIEW FLEXIBLE CONNECTION @ ALL MANHOLE BASE ENTRY & EXIT. |
| 11/02/2004 | PLUMBING - SEWER HCS CONNECT | RRICH | Approved | IVRS - Inspection :*/8" SEWER FROM EXISTING MANHOLE #9 TO NEW MANHOLE #1, 8" SEWER FROM MANHOLE #1 EAST TO MANHOLE #5. FROM MANHOLE #1 NORTH TO 8" SEWER TO MANHOLE #2, FROM MANHOLE #2 TO MANHOLE #3 8" SEWER, FROM LATERALS, FROM MANHOLE #4 4" HCS LATERAL EAST 100', 6" HCS LATER 76.7 NORTH, 6" HCS LATERAL 34' WEST, FROM MANHOLE #2 6" HCS LATERAL 79' MORTH EAST. FROM MANHOLE #1 8" SEWER TO MANHOLE #5 OK. 1)WILL REQUIRE AIR TEST, MANDROL, VACUUM TEST AND VERIFICATION OF GRADE, WITH PDEQ CERTIFICATION AT LATER DATE |
| 12/16/2004 | ELECTRIC - UFER | LHANLY | Approved | IVRS - Inspection :* 1) 1-2/0 TO 1LP 2) 1-2/0 TO T1 3) 1 #4 TO FIRERISER 4) INDEPENDENT 20' CU EACH IN FOOTING |
| 12/16/2004 | EXCAVATION/LAYOUT REBAR & ZON | LHANLY | Approved | IVRS - Inspection :* 1) INTERIOR SPREAD FOOTINGS AND ALL PERIMETER |
| 12/17/2004 | TDOT - Road Project | AMCGOVER | Approved | No update this week on the road job. |
| 12/27/2004 | STEM WALL/RETAINING WALL | LHANLY | Approved | IVRS - Inspection :* |
| 03/21/2005 | BUILDING PRE-SLAB | LHANLY | Approved | IVRS - Inspection :* BASKETBALL COURTS OK |
| 04/05/2005 | ROOF NAILING | LHANLY | Approved | IVRS - Inspection :* 1) MAIN ROOF OK TO DRY IN 2) REMOVE PLYWOOD FORM @ GLULAM POCKET. |
| 04/07/2005 | FIRE - HYDRANTS | LTHOMAS | Approved | |
| 04/07/2005 | FIRE SPKLR - UG PIPING FLUSH | LTHOMAS | Approved | |
| 04/07/2005 | FIRE SPKLR - UG, PIPING, HYDRO | LTHOMAS | Approved | |
| 05/03/2005 | PLUMBING - INTERMEDIATE | TRINIVJR | Approved | IVRS - Inspection :* 1) GAS PRESSURE TEST IS OK. 2) OVERHEAD WATER DISTRIBUTION IS OK. 3) SOIL WATER TEST FOR DWV SYSTEM. 4) NOTE: SHALL SEE CLOSET FLANGE INSTALLATION PRIOR TO SETTING WATER CLOSTES |
| 05/05/2005 | PLUMBING - GAS PRESSURE TEST | RRICH | Approved | IVRS - Inspection :* APPROVED BY TRINI JR 5/3/05 |
| 05/18/2005 | FIRE SPKLR - OH PIPING & HYDRO | LTHOMAS | Approved | |
| 05/19/2005 | FRAMING | LHANLY | Approved | IVRS - Inspection :* ADMIN BUILD COMPLETE. |
| 06/21/2005 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* OK FOR CEILING TILES |
| 06/21/2005 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* |
| 06/21/2005 | PLUMBING - ABOVE CEILING | RRICH | Approved | IVRS - Inspection :* |
| 06/21/2005 | ELECTRIC - ABOVE CEILING | RSUBA | Approved | IVRS - Inspection :* |
| 06/21/2005 | REINFORCED MASONRY PRE-GROUT | LHANLY | Approved | IVRS - Inspection :* NEAR TOP OUT OF CANOPY WALL # 2 |
| 06/24/2005 | TEP CLEARANCE - AM | JKOZUCH | Approved | PER R SUBA LETTER SUBMITTED OK TO CLEAR |
| 07/11/2005 | PLUMBING - GAS PRESS TEST FNL | RRICH | Approved | IVRS - Inspection :* 1) GAS CLEARANCE CARD ISSUED METER MAY BE ORDERED. GAS IS NOT TO BE ENERGIZED UNTIL FIRE PROTECTION SYSTEM IS ACTIVATED. |
| 07/15/2005 | ELECTRIC - INTERMEDIATE | RSUBA | Approved | IVRS - Inspection :* |
| 07/15/2005 | ELECTRIC - UNDERGROUND | RSUBA | Approved | IVRS - Inspection :* |
| 07/15/2005 | PLUMBING - YARD WTR LINE/TEST | RRICH | Approved | IVRS - Inspection :* |
| 07/15/2005 | FIRE - LANE SIGNS | LTHOMAS | Approved | |
| 07/15/2005 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
| 07/15/2005 | FIRE - ALARM FINAL | LTHOMAS | Approved | |
| 07/18/2005 | FIRE - FINAL | LTHOMAS | Approved | |
| 07/20/2005 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* 1) OK FOR FINAL C OF O |
| 07/20/2005 | SHEET ROCK NAILING | LHANLY | Approved | IVRS - Inspection :* |
| 07/20/2005 | BUILDING ABOVE CEILING | LHANLY | Approved | IVRS - Inspection :* |
| 07/20/2005 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
| 07/21/2005 | BUILDING - FINAL | LHANLY | Approved | IVRS - Inspection :* 1) OK TCO STUDENTS AND ADMINISTRATION |
| 07/21/2005 | ENGINEERING - FINAL | JSALINE | Approved | TEMPORARY C OF O APPROVED. FINAL C OF O TO BE ISSUED AFTER COMPLETION OF CONCRETE PER APPPROVED PLANS. COMPLETION OF ALL DRAINAGE REQUIREMENTS PER APPROVED PLANS. INSTALLATION OF ADDITIONAL SCUPPERS AS EXPLAINED TO CONTRACTOR, (LLOYDS CONSTRUCTION). COMPLETION OF ALL ROCK-RIP-RAP PER APPROVED PLANS. |
| 07/21/2005 | BUILDING - FINAL | LHANLY | Approved | |
| 08/08/2005 | PLUMBING - FINAL | RRICH | Approved | IVRS - Inspection :* 1) CORRECTION MADE |
| 02/09/2006 | U VALUE FOR WINDOW | LHANLY | Approved | IVRS - Inspection :* |
| 07/27/2006 | ELECTRIC - TEMP POWER FOR TEST | RSUBA | Approved | PER EL FINAL |
| 07/27/2006 | RIGHT OF WAY - FINAL | NBRIGGS | Approved | |
| 07/27/2006 | OUTDOOR LIGHTING FINAL | RSUBA | Approved | PER TELEPHONE CALL |
| 07/27/2006 | ELECTRIC - FINAL | RSUBA | Approved | PER TELEPHONE CALL |