Inspection Status: Approved
Inspection History: ENGINEERING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/14/2006 | ENGINEERING - FINAL | Approved | PER PH CALL | |
| 07/21/2005 | ENGINEERING - FINAL | Partial Approval | TEMPORARY C OF O APPROVED. FINAL C OF O TO BE ISSUED AFTER COMPLETION OF CONCRETE PER APPPROVED PLANS. COMPLETION OF ALL DRAINAGE REQUIREMENTS PER APPROVED PLANS. INSTALLATION OF ADDITIONAL SCUPPERS AS EXPLAINED TO CONTRACTOR, (LLOYDS CONSTRUCTION). COMPLETION OF ALL ROCK-RIP-RAP PER APPROVED PLANS. |
|
| 07/20/2005 | ENGINEERING - FINAL | Denied | SITE DENIED FOR TEMPORARY C OF O. 1) COMPLETE ASPHALT PAVING AND STRIPING FOR STUDENT/TEACHER PARKING AREAS. 2) COMPLETE EXTRUDED CURB CONSTRUCTION FOR PARKING AREAS. 3) PROVIDE STORM WATER CONTROLS FOR STORM DRAINS WITHIN COURTYARD AND ALONG THE WEST PERIMETER. 4) DIRECT ALL DOWN SPOUT WATER RUN-OFF AWAY FROM TEMPORARY WALKWAYS. |