| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/05/2005 | TDOT - Road Project | Approved | No activity | |
| 06/27/2005 | TDOT - Road Project | Approved | No activity....awaiting water source | |
| 06/20/2005 | TDOT - Road Project | Approved | Work this week : Landscape irrigation |
|
| 06/13/2005 | TDOT - Road Project | Approved | This and next week's activity: landscape irrigation manhole collars |
|
| 06/06/2005 | TDOT - Road Project | Approved | Work this week : riprap manhole adjustments landscaping |
|
| 05/23/2005 | TDOT - Road Project | Approved | The work this week and next: The road work was substantially completed on 5/19/05. Striping, signing, irrigation, and final SWPPPs will be done in the next two weeks. Ribbon cutting and road opening is Monday 5/23/05. Please note that we are at the end of the project except for the landscaping. We are awaiting a water source to complete the landscaping. No further reporting may be necessary. |
|
| 05/13/2005 | TDOT - Road Project | Approved | Work the next two weeks is as follows: Paving landscape irrigation utility adjustments temporary striping shoulder grading seeding |
|
| 05/09/2005 | TDOT - Road Project | Approved | Work the next two weeks is a follows: Aggregate base Paving curb, curb access ramps traffic signals landscape ririgation utility adjustments |
|
| 05/02/2005 | TDOT - Road Project | Approved | Progress this week includes the following: ABC Arch culvert backfill Manhole reconstructs |
|
| 04/22/2005 | TDOT - Road Project | Approved | The activity for this week and next week is as follows: Roadway grading ABC Con Arch construction structural backfill manhole reconstructs riprap |
|
| 04/19/2005 | TDOT - Road Project | Approved | Work scheduled for the next two weeks is as follows: ABC Arch culverts landscape irrigation drainage ex manhole reconstruction |
|
| 04/11/2005 | TDOT - Road Project | Approved | Progress this week and next week is as follows: Drainage ex Roadway ex ABC haul Manhole reconstructs con arch construction |
|
| 04/01/2005 | TDOT - Road Project | Approved | the contractor is working on the following the next two weeks: subgrade prep drainage grading and excavation manhole reconstruction con arch construction aggregate base |
|
| 02/14/2005 | TDOT - Road Project | Approved | Work this and next week will be to build pipe culverts and headwalls, fence construction,and utility trench overexcavation/recompaction. Roadway excavtion and subgrade buildup will begin this week. |
|
| 02/04/2005 | TDOT - Road Project | Approved | The contractor is working on the following this week and next week: ROW fence installation Pipe culvert installation Headwall construction Sanitary Sewer trench overexcavation and recompaction Roadway Grading and Excavation |
|
| 01/31/2005 | TDOT - Road Project | Approved | Work is continuing with ROW fence installation, clearing, overexcavation and compaction of existing sewer line trenches, and instalaltion of drainage culverts. | |
| 01/21/2005 | TDOT - Road Project | Approved | Work has begun on the east limit of the project and moving west. The installation of the north fence line has begun. Plant salvage work continuing ahead of road clearing and should be completed this week. Clearing and grubbing is progressing. Drainage pipe culvert and headwall work will begin next week. Compaction of of trench backfill over exisitng sanitary sewer line and roadway grading and excavtion expected next week. | |
| 01/14/2005 | TDOT - Road Project | Approved | Survey of property line on going. Contractor beginning plant salvage. Clearing for new fence line to begin Monday 1/17/05. Clear and grub expected to be done week of 1/17 to 1/21. Recompaction of existing sanitary sewer trenches to begin same week. Some culvert work to begin along with headwall construction. | |
| 01/07/2005 | TDOT - Road Project | Approved | Precon meeting was held on 1/4/05. Construction start date is 1/10/05. | |
| 12/17/2004 | TDOT - Road Project | Approved | No update this week on the road job. | |
| 12/10/2004 | TDOT - Road Project | Approved | The project was bid on 11/30/04. The low bid was $2, 715,734.90. Construction schedule is tentatively set to begin Jan 10, 2005 with completion by mid-May 2005. | |
| 12/10/2004 | TDOT - Road Project | Approved | No update on road project this week. | |
| 12/03/2004 | TDOT - Road Project | Approved | Here's the latest: Bids for the roadway construction project opened this week. Hunter Construction is the apparent low bidder, but a recommendation to award the construction contract to that company has not yet been made. Still on schedule for mid-January 2005 construction start. |
|
| 11/26/2004 | TDOT - Road Project | Approved | The road project is scheduled for bid opening on Tuesday, November 30. Anticipated construction start date of January 10, 2005 still holds. Project is scheduled for completion mid-May 2005. |