Permit: T04CM02883
Permit Details
Status:
Final
Type:
SINGLE FAMILY NEW
Address:
10950 E ESCALANTE RD
Address NEW:
10950 E ESCALANTE RD
Apply Date:
06/22/2004
Applicant:
GRAFFAM RAY
Description:
SFR:NEW
Permit Reviews
Permit Number - T04CM02883
Permit Status: Final
Permit Description: SFR:NEW
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/14/2005 | REVISION - WALK THRU | 02/14/2005 | COMPLETED |
| 06/22/2004 | PLANS OK TO SUBMIT - RES | 07/07/2004 | COMPLETED |
| 06/22/2004 | RESIDENTIAL BLDG/ZONING/ENGINE/WWM | 08/03/2004 | COMPLETED |
| 08/19/2004 | RESUBMITTAL | 10/12/2004 | COMPLETED |
| 10/12/2004 | PLANS OK TO SUBMIT - RES | 10/12/2004 | COMPLETED |
| 10/12/2004 | RESIDENTIAL BLDG/WWM | 11/22/2004 | COMPLETED |
| 12/15/2004 | RESUBMITTAL | 01/11/2005 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T04CM02883
Permit Status: Final
Permit Description: SFR:NEW
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 06/22/2004 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T04CM02883
Permit Description: SFR:NEW
Total Completed Inspections - 25
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/02/2005 | PLUMBING - ROUGH, SOIL | RFREIDIN | Approved | IVRS - Inspection :* |
| 02/15/2005 | ELECTRIC - UNDERGROUND | DQUINN | Approved | IVRS - Inspection :* |
| 02/15/2005 | ELECTRIC - UFER | DQUINN | Approved | IVRS - Inspection :* |
| 02/15/2005 | BUILDING PRE-SLAB | DQUINN | Approved | IVRS - Inspection :* |
| 02/15/2005 | STEM WALL/RETAINING WALL | DQUINN | Approved | IVRS - Inspection :* |
| 03/01/2005 | ELECTRIC - CABLE DROP | RFREIDIN | Approved | IVRS - Inspection :* 1) UFER, COVERED IN CONCRETE, TWO GROUND RODS INSTALLED |
| 03/01/2005 | ELECTRIC - TEMPORARY SERVICE | RFREIDIN | Approved | IVRS - Inspection :* |
| 03/02/2005 | TEP CLEARANCE - AM | HLEYVA | Approved | ECO CLEARED BY FREIDINGER |
| 03/23/2005 | PLUMBING - YARD WTR LINE/TEST | RFREIDIN | Approved | IVRS - Inspection :* |
| 03/23/2005 | ROOF NAILING | RFREIDIN | Approved | IVRS - Inspection :* |
| 03/23/2005 | EXT METAL CLIPS/EXT SHEATHING | RFREIDIN | Approved | IVRS - Inspection :* |
| 05/06/2005 | FRAMING | RFREIDIN | Approved | IVRS - Inspection :* 1) LAST INSPECTION #2 (ITEM) FILL TUB WITH H20, CHECK FOR LEAK IN TUB SHOE, OK TO INSULATE RECALL PLUMBING 2) MORE NAILS IN SIDE BLOCKS SUPPORTING VIEGA LOGS, YOU USED GUN NAILS THEY ARE NOT 16D'S, THEY ARE 10D OR 12D |
| 05/06/2005 | MECHANICAL - INTERMEDIATE | RFREIDIN | Approved | IVRS - Inspection :* |
| 05/06/2005 | PLUMBING - GAS PRESSURE TEST | RFREIDIN | Approved | IVRS - Inspection :* |
| 05/06/2005 | ELECTRIC - INTERMEDIATE | RFREIDIN | Approved | IVRS - Inspection :* |
| 05/10/2005 | PLUMBING - INTERMEDIATE | RFREIDIN | Approved | IVRS - Inspection :* |
| 05/10/2005 | STUCCO MESH | RFREIDIN | Approved | IVRS - Inspection :* |
| 06/01/2005 | EXCAVATION/LAYOUT REBAR & ZON | RFREIDIN | Approved | IVRS - Inspection :* |
| 06/01/2005 | SHEET ROCK NAILING | RFREIDIN | Approved | IVRS - Inspection :* |
| 12/09/2005 | U VALUE FOR WINDOW | RFREIDIN | Approved | |
| 12/09/2005 | MECHANICAL - FINAL | RFREIDIN | Approved | IVRS - Inspection :* |
| 12/09/2005 | PLUMBING - FINAL | RFREIDIN | Approved | IVRS - Inspection :* |
| 12/09/2005 | ELECTRIC - FINAL | RFREIDIN | Approved | IVRS - Inspection :* |
| 12/09/2005 | BUILDING - FINAL | RFREIDIN | Approved | IVRS - Inspection :* |
| 06/14/2006 | PERMIT FINALED | LJACKSON | Approved |