Permit: T03CM04894
Permit Details
Status:
Final
Type:
MULTI FAMILY NEW
Address:
2800 W BROADWAY BL BLDG #1
Address NEW:
2800 W BROADWAY BL BLDG #1
Apply Date:
10/10/2003
Applicant:
N/A
Description:
NEW APARTMENT BUILDING UNITS 111-119, 1110, 121-129, 1210
Architects:
- WONG, CLIFFORD
Contractors:
- FAIRFIELD DEVELOPMENT L P ,
Permit Reviews
Permit Number - T03CM04894
Permit Status: Final
Permit Description: NEW APARTMENT BUILDING UNITS 111-119, 1110, 121-129, 1210
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/21/2004 | 3RD PARTY REVIEW-COMMERCIAL | 02/03/2004 | COMPLETED |
| 02/19/2004 | 3RD PARTY REVIEW-COMMERCIAL | 04/01/2004 | COMPLETED |
| 03/15/2005 | 3RD PARTY REVIEW-REVISION/OTHER | 03/15/2005 | COMPLETED |
| 03/15/2005 | POST 3RD PARTY REVIEW | 03/18/2005 | COMPLETED |
| 04/23/2004 | RESUBMITTAL | 04/23/2004 | COMPLETED |
| 08/26/2004 | 3RD PARTY REVIEW-REVISION/OTHER | 08/26/2004 | COMPLETED |
| 10/10/2003 | PLANS OK TO SUBMIT - 3RD PARTY | 12/03/2003 | COMPLETED |
| 12/04/2003 | 3RD PARTY REVIEW-COMMERCIAL | 12/19/2003 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T03CM04894
Permit Status: Final
Permit Description: NEW APARTMENT BUILDING UNITS 111-119, 1110, 121-129, 1210
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 10/10/2003 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T03CM04894
Permit Description: NEW APARTMENT BUILDING UNITS 111-119, 1110, 121-129, 1210
Total Completed Inspections - 42
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/24/2004 | PLUMBING - ROUGH, SOIL | RMYERS | Approved | IVRS - Inspection :*/ 1) PVC UNDEGROUND OK. WATER TEST ? RISER TO 10 FEET 3) OK TO BACKFILL |
| 06/10/2004 | ELECTRIC - UFER | DSANTACR | Approved | IVRS - Inspection :*/ BLD #1, #4 UFER 20' COPPER. |
| 06/11/2004 | BUILDING PRE-SLAB | AMATHIES | Approved | IVRS - Inspection :* |
| 08/27/2004 | ELECTRIC - TEMPORARY POLE | DSANTACR | Approved | IVRS - Inspection :* |
| 09/01/2004 | ROOF NAILING | AQUIROZ | Approved | IVRS - Inspection :* |
| 09/10/2004 | EXT METAL CLIPS/EXT SHEATHING | AQUIROZ | Approved | IVRS - Inspection :* |
| 09/16/2004 | EXCAVATION/LAYOUT REBAR & ZON | AQUIROZ | Approved | IVRS - Inspection :* |
| 09/27/2004 | STEM WALL/RETAINING WALL | AQUIROZ | Approved | IVRS - Inspection :*APPROVED. |
| 10/05/2004 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection :*/ 1) CONTR. USED FIRE RATED BOXES FOR FIREWALLS, CHECK WITH BLDG INSP FOR APPROVAL OF FIRE STOP METHOD |
| 10/08/2004 | MECHANICAL - INTERMEDIATE | CWILLIAM | Approved | IVRS - Inspection :*/BLDG #1 |
| 10/12/2004 | PLUMBING - ROOF DRAINS | RMYERS | Approved | IVRS - Inspection :* |
| 10/15/2004 | BUILDING ABOVE CEILING | AQUIROZ | Approved | IVRS - Inspection :* |
| 10/27/2004 | PLUMBING - INTERMEDIATE | RMYERS | Approved | IVRS - Inspection :*/1)CORRECTIONS MADE OK. OK TO COVER ALL AREAS |
| 10/29/2004 | FRAMING | AQUIROZ | Approved | IVRS - Inspection :* |
| 11/02/2004 | STUCCO MESH | AQUIROZ | Approved | IVRS - Inspection :* |
| 11/09/2004 | ELECTRIC - UNDERGROUND | MCAPISTR | Approved | IVRS - Inspection :*/ 1) SOUTH FRONT: WEST OF CLUB HOUSE FOR POLE LIGHTS |
| 11/17/2004 | SHEET ROCK NAILING | AQUIROZ | Approved | IVRS - Inspection :* |
| 12/07/2004 | PLUMBING - SEWER HCS CONNECT | RMYERS | Approved | IVRS - Inspection :*/1)CONNECTIONS TO PRIVATE SEWER OK. 2)OK TO COVER SUBJECT TO LOW PRESSURE AIR TEST ON PRIVATE SEWER |
| 12/17/2004 | PLUMBING - PROGRESS | RMYERS | Approved | IVRS - Inspection :* 1) CONNECTION BETWEEN TWO WAY CLEANOUT AND HCS OK-ENGINEER REDLINED AS BUILT INVERTS 2) OK TO COVER |
| 12/23/2004 | PLUMBING - YARD WTR LINE/TEST | RMYERS | Approved | IVRS - Inspection :*/CONNECTIONS AT METER OK. OK TO COVER |
| 01/13/2005 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
| 01/18/2005 | MECHANICAL - FINAL | CWILLIAM | Approved | IVRS - Inspection :* |
| 01/25/2005 | RIGHT OF WAY - FINAL | MOTERO | Approved | |
| 02/03/2005 | FIRE - FINAL | LTHOMAS | Approved | |
| 02/03/2005 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
| 02/03/2005 | FIRE SPKLR - OH PIPING & HYDRO | LTHOMAS | Approved | |
| 02/03/2005 | FIRE SPKLR - UG PIPING FLUSH | LTHOMAS | Approved | |
| 02/03/2005 | FIRE SPKLR - UG, PIPING, HYDRO | LTHOMAS | Approved | |
| 02/04/2005 | U VALUE FOR WINDOW | AQUIROZ | Approved | IVRS - Inspection :* |
| 02/04/2005 | BUILDING - PROGRESS | AQUIROZ | Approved | IVRS - Inspection :* |
| 02/07/2005 | PLUMBING - FINAL | RMYERS | Approved | IVRS - Inspection :* 1) CORRECTIONS MADE OK 2) PLUMBING FINAL OK. 30 OK FOR C OF O PENDING ANY OTHER INSPECTION |
| 02/07/2005 | PLUMBING - GAS PRESS TEST FNL | RMYERS | Approved | IVRS - Inspection :*APPROVED |
| 02/07/2005 | PLUMBING - ABOVE CEILING | RMYERS | Approved | IVRS - Inspection :*APPROVED |
| 02/07/2005 | PLUMBING - GAS PRESSURE TEST | RMYERS | Approved | IVRS - Inspection :* |
| 06/23/2005 | ENGINEERING - FINAL | MRUSSO | Approved | |
| 06/23/2005 | NPPO - FINAL | ACONNOR | Approved | |
| 06/23/2005 | LANDSCAPE - FINAL | ACONNOR | Approved | |
| 06/28/2005 | OUTDOOR LIGHTING FINAL | MCAPISTR | Approved | IVRS - Inspection :* |
| 06/28/2005 | ELECTRIC - ABOVE CEILING | MCAPISTR | Approved | IVRS - Inspection :* |
| 06/28/2005 | ELECTRIC - FINAL | MCAPISTR | Approved | IVRS - Inspection :* |
| 07/28/2005 | PERMIT FINALED | AQUIROZ | Approved | |
| 07/28/2005 | BUILDING - FINAL | AQUIROZ | Approved |