Permit Details

Status:
Final
Type:
COMMERCIAL OTHER
Address:
105 E YAVAPAI RD
Address NEW:
105 E YAVAPAI RD
Apply Date:
11/25/2003
Applicant:
ADG
Description:
GRADING:130CY CUT/2000 CY FILL

Permit Reviews

Permit Number - T03BU03025
Permit Status: Final
Permit Description: GRADING:130CY CUT/2000 CY FILL
Start Date Submittal Complete Date Status  
02/11/2004 RESUBMITTAL 03/16/2004 COMPLETED Review Details
03/29/2004 RESUBMITTAL - GRADING 06/17/2004 COMPLETED Review Details
06/17/2004 RESUBMITTAL - GRADING ALL 07/15/2005 COMPLETED Review Details
11/25/2003 PLANS OK TO SUBMIT - GRADING 11/25/2003 COMPLETED Review Details
11/25/2003 GRADING 01/06/2004 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T03BU03025
Permit Status: Final
Permit Description: GRADING:130CY CUT/2000 CY FILL
Total Outstanding Activity Conditions - 1
Date Name
11/25/2003 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: Final
Permit Number: T03BU03025
Permit Description: GRADING:130CY CUT/2000 CY FILL
Total Completed Inspections - 8
Date Description Inspector Results Comments
12/20/2005 NPPO PRE PERMIT INSPECTION ACONNOR Approved
12/21/2005 STORMWATER INSTALL OF CONTROLS MRUSSO Approved 1) SCHEDULE STORM WATER PRECONSTRUCTION MEETING IN ORDER TO DISCUSS STORM WATER MANAGEMENT AND RESPOSIBILITIES.
2) SWPPP NOT REQUIRED DUE TO THE FACT THAT THE PERMIT IS 3 YEARS OLD AND THE REQUIREMENT FOR A SWPPP WAS DISTURBANCE OF 5 ACRES AND LARGER AT THE TIME OF ISSUANCE; HOWEVER SEDIMENT CONTROLS MAY BE REQUIRED FOR THE SITE.
3) SEDIMENT CONTROLS HAVE BEEN INSTALLED ON SITE, (SILT FENCE, WADDLE, STABILIZED CONSTRUCTION ENTRANCE).
4) PROVIDE A POINT OF CONTACT, ( SITE SUPERINTENDENT OR EQUIVALENT) IN ORDER TO DISCUSS INSPECTION RESULTS.
01/05/2006 ENGINEERING PRE-CONSTRUCTION MRUSSO Approved AFTER RESEARCH INTO YOUR INITIAL SUBMITTAL AND REVIEW OF YOUR GRADING PLAN FOR THIS SITE, IT HAS COME TO MY ATTENTION THAT THE SITE IS REQUIERED TO HAVE A SWPPP AS STATED IN THE REVIEW COMMENTS DATED DEC 12TH, 2003. IN FACT WE HAVE A COPY OF YOUR APPROVED SWPPP ON FILE, WITH A SIGNED NOI. YOU MUST MEET ALL REQUIREMENTS STATED IN YOUR APPROVED SWPPP, DATED 6/23/04.
11/02/2006 STORMWATER FOLLOW-UP INSP MRUSSO Approved 1) CLEAN OUT CONCRETE WASH OUT, IT'S FULL.
2) STORM WATER CONTROLS ARE REQUIRED UNTIL THE SITE IS PAVED.
3) SEPARATE CONSTRUCTION FROM OCCUPIED BLDGS.

NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME.
10/11/2007 GRADING - FINAL MRUSSO Approved
10/11/2007 GRADING - INTERMEDIATE MRUSSO Approved
10/11/2007 STORMWATER FINAL INSPECTION MRUSSO Approved
10/12/2007 PERMIT FINALED KMEDINA Approved

Documents

File Name Document Type  
DRAINAGE STATEMENT.TIF DOCUMENTS VIEW
None DOCUMENTS VIEW
CERTIFICATION LETTER 2007_07_26.PDF DOCUMENTS VIEW
None DOCUMENTS VIEW
001_1 OF 1.TIF DOCUMENTS VIEW