Permit: DP21-0237
Permit Details
Status:
Inspections
Type:
Development Package
Address:
4025 E MONTE VISTA DR
Address NEW:
4025 E MONTE VISTA DR
Apply Date:
09/07/2021
Applicant:
Jeff Gereke
Description:
Tentative Plat / Flexible Lot Development - Oasis Subdivision, Lots 1 thru 23, plus Common Areas "A"
Permit Reviews
Permit Number - DP21-0237
Permit Status: Inspections
Permit Description: Tentative Plat / Flexible Lot Development - Oasis Subdivision, Lots 1 thru 23, plus Common Areas "A"
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/26/2022 | TENTATIVE PLAT REVIEW | 03/30/2022 | COMPLETED |
| 05/20/2022 | TENTATIVE PLAT REVIEW | 05/25/2022 | COMPLETED |
| 08/24/2022 | TENTATIVE PLAT REVIEW | 09/05/2022 | COMPLETED |
| 09/07/2021 | DEV PKG - OK TO SUBMIT | 09/15/2021 | COMPLETED |
| 09/15/2021 | TENTATIVE PLAT REVIEW | 11/12/2021 | COMPLETED |
Outstanding Inspections
Permit Status: Inspections
Permit Number: DP21-0237
Permite Description: Tentative Plat / Flexible Lot Development - Oasis Subdivision, Lots 1 thru 23, plus Common Areas "A"
Total Outstanding Inspections - 6
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/27/2022 | ENGR Engineering Final | N/A | Not Ready | |
| 10/26/2022 | SITE - Stormwater Final Inspection | N/A | Not Ready | |
| 11/22/2023 | SITE - SWPPP Correction Notice | N/A | Not Ready | no activity |
| 10/26/2022 | SITE - Stormwater Follow-up | N/A | Not Ready | |
| 10/26/2022 | SITE - SWPPP Violation Notice | N/A | Not Ready | |
| 07/10/2026 | ENGR Paving | N/A | Partial Pass | AB depth , slopes, and compaction are good. Okay to pave. |
Completed Inspections
Permit Status: Inspections
Permit Number: DP21-0237
Permit Description: Tentative Plat / Flexible Lot Development - Oasis Subdivision, Lots 1 thru 23, plus Common Areas "A"
Total Completed Inspections - 3
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/27/2026 | PDSD Engineering Division Pre-Construction SITE | Passed | Super will be emailing me today the NOI, It is still current CGP 2025 has been issued. Tentative plat has been approved/issued. NPPO will be revised and submitted-plants no longer exist. Old SWPPP Board is on Fence and SWPPP book included. This will be updated. SWPPP plan will revised and Submitted for 2025 CGP Contractors okay to install BMPs for and will Request storm water initial when ready. |
|
| 06/29/2026 | SITE - Stormwater Setup and Controls | Passed | Keep dirt and sediment on site and off roads. If there’s any dirt in the road, it must be swept up promptly. If this becomes a problem, trackout will have to be placed at entrances again. | |
| 08/07/2026 | ENGR Grading Final | Passed | Not all sidewalks are installed for sequence of construction but grading in these areas are correct. Lot elevations hubbed and correct. Compaction testing all complies. Submit all Reports to the Portal. Cuts and fills good basins good. Contractor will backfill areas that need it at walls etc later as needed. |