Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: DP20-0060
Permit Details
Status:
Issued
Type:
Development Package
Address:
3205 N CAMPBELL AV
Address NEW:
3205 N CAMPBELL AV
Apply Date:
03/17/2020
Applicant:
Blake Junak
Description:
Revision 1-SITE/GRADING - Dutch Bros, new coffee shop, Ft. Lowell/Campbell.
Permit Reviews
Permit Number - DP20-0060
Permit Status: Issued
Permit Description: Revision 1-SITE/GRADING - Dutch Bros, new coffee shop, Ft. Lowell/Campbell.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/17/2020 | DEV PKG - OK TO SUBMIT | 03/18/2020 | COMPLETED |
| 03/18/2020 | DEV PKG | 05/04/2020 | COMPLETED |
| 07/30/2025 | DEVELOPMENT PACKAGE NEW REVISION v.2 | 08/07/2025 | APPROVED |
| 05/02/2023 | DEVELOPMENT PACKAGE REVIEW v.1 | 05/04/2023 | REQUIRES RESUBMIT |
| 06/25/2025 | DEVELOPMENT PACKAGE NEW REVISION v.1 | 07/22/2025 | REQUIRES RESUBMIT |
| 07/15/2024 | DEVELOPMENT PACKAGE NEW v.3 | 02/24/2025 | APPROVED |
| 05/15/2024 | DEVELOPMENT PACKAGE NEW v.2 | 06/20/2024 | REQUIRES RESUBMIT |
| 04/02/2024 | DEVELOPMENT PACKAGE NEW v.1 | 04/09/2024 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - DP20-0060
Permit Status: Issued
Permit Description: Revision 1-SITE/GRADING - Dutch Bros, new coffee shop, Ft. Lowell/Campbell.
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 10/02/2025 | CRWHPLAN NEEDS TO BE CREATED PRIOR TO CLOSEOUT |
Outstanding Inspections
Permit Status: Issued
Permit Number: DP20-0060
Permite Description: Revision 1-SITE/GRADING - Dutch Bros, new coffee shop, Ft. Lowell/Campbell.
Total Outstanding Inspections - 5
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/25/2025 | N/A | Not Ready | Superintendent not on site need to reschedule | |
| 10/15/2025 | For trash and recycling enclosures | N/A | Partial Pass | 9/30/25 Reinforcing correct. Slope correct. Submit compaction report to the permit. Okay to pour Apron. Clean street and sidewalk of dirt from storm...Recondition Trackout with 2" plus rock Call in inspection before pouring all sidewalk and other Flatwork. Submit compaction under sidewalk to portal |
| 11/18/2025 | N/A | Partial Pass | Contractors good to pour the sidewalk in between the two buildings with the scuppers in them | |
| 11/20/2025 | ENGR Paving | N/A | Partial Pass | I gave the contractor a partial pass. We strung line the Grade there was. some areas were high and other areas were low needs to re-grade it contractors would like to pave on Friday. contractor will call in for reinspection on Friday. |
| 11/21/2025 | Grading Progress ENGR | N/A | Partial Pass | 11/21/25 Grading inspection for ABC. Compaction testing good in subgrade and AB. Submit reports to the permit. Grade hubs look correct. Depths measured with string line from curb to hubs and curb to curb correct for 3" AC. Curb reveals correct. Paved Area will drain if paved correctly. Submit Grade changes in As-Builts to permit. Okay to pave parking areas and PAALS. |
Completed Inspections
Permit Status: Issued
Permit Number: DP20-0060
Permit Description: Revision 1-SITE/GRADING - Dutch Bros, new coffee shop, Ft. Lowell/Campbell.
Total Completed Inspections - 1
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/24/2025 | PDSD Engineering Division Pre-Construction SITE | Passed | For the contractor, he need to put wattles all around the perimeter and call in for swap inspection every two weeks. Also informed him about the material testing and the trash enclosures. |