Inspection History Details
Inspection Status: Partial Pass
Inspection History: Grading Progress ENGR
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/23/2026 | Grading Progress ENGR | Partial Pass | 01/23/26 Last area of asphalt paving at S Driveway onto Ft. Lowell. Basin along Ft. Lowell needs to made deeper to contain drainage from curb cut at drive through. When this is done grading will be completed. |
|
| 11/21/2025 | Grading Progress ENGR | Partial Pass | 11/21/25 Grading inspection for ABC. Compaction testing good in subgrade and AB. Submit reports to the permit. Grade hubs look correct. Depths measured with string line from curb to hubs and curb to curb correct for 3" AC. Curb reveals correct. Paved Area will drain if paved correctly. Submit Grade changes in As-Builts to permit. Okay to pave parking areas and PAALS. |