Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Complete
Type:
Development Package
Address:
2402 N 1ST AV
Apply Date:
03/02/2020
Applicant:
Description:
SITE - Grant Rd. & 1st Avenue, parking.

Permit Reviews

Permit Number - DP20-0042
Permit Status: Complete
Permit Description: SITE - Grant Rd. & 1st Avenue, parking.
Start Date Submittal Complete Date Status  
02/14/2020 DEV PKG - OK TO SUBMIT 03/23/2020 COMPLETED Review Details
03/02/2020 DEV PKG - OK TO SUBMIT 03/05/2020 COMPLETED Review Details
03/23/2020 DEV PKG 04/06/2020 COMPLETED Review Details
04/03/2020 DEV PKG - RESUBMITTAL 04/16/2020 COMPLETED Review Details

Outstanding Inspections

Permit Status: Complete
Permit Number: DP20-0042
Permite Description: SITE - Grant Rd. & 1st Avenue, parking.
Total Outstanding Inspections - 1
Last Inspection Date Description Inspector Results Comments
11/24/2020 SITE - Stormwater Follow-up N/A Complete (Recurring) {Activity date: 11/24/2020; Status: Continued; Inspector: BBENEDON; Comment: Entered by PAHUMAD1 - Continued. No issues at this time.} ; {Activity date: 11/18/2020; Status: Continued; Inspector: BBENEDON; Comment: Entered by PAHUMAD1 - Continued. Most material stock piles have been removed and two remaining in the last unpaved portion of the site.

} ; {Activity date: 11/06/2020; Status: Continued; Inspector: BBENEDON; Comment: Entered by PAHUMAD1 - Continued. No issues at this time.

} ; {Activity date: 11/06/2020; Status: Continued; Inspector: BBENEDON; Comment: Entered by PAHUMAD1 - Continued. No issues at this time.} ; {Activity date: 10/09/2020; Status: Continued; Inspector: BBENEDON; Comment: Entered by PAHUMAD1 - No issues at this time. However many large unprotected stock piles of material on site at this time.

} ; {Activity date: 10/01/2020; Status: Approved; Inspector: BBENEDON; Comment: Entered by JSCHNEI2 - Continued.
} ; {Activity date: 10/01/2020; Status: Continued; Inspector: BBENEDON; Comment: Entered by JSCHNEI2 - Continued.} ; {Activity date: 10/01/2020; Status: Continued; Inspector: BBENEDON; Comment: Entered by JSCHNEI2 - Continued.} ; {Activity date: 10/01/2020; Status: Continued; Inspector: BBENEDON; Comment: Entered by JSCHNEI2 - Continued.} ; {Activity date: 10/01/2020; Status: Continued; Inspector: BBENEDON; Comment: Entered by JSCHNEI2 - Continued.
} ; {Activity date: 10/01/2020; Status: Continued; Inspector: BBENEDON; Comment: Entered by JSCHNEI2 - Continued.} ; {Activity date: 10/01/2020; Status: Continued; Inspector: BBENEDON; Comment: Entered by JSCHNEI2 - Continued.} ; {Activity date: 10/01/2020; Status: Continued; Inspector: BBENEDON; Comment: Entered by JSCHNEI2 - Continued.} ; {Activity date: 09/29/2020; Status: Continued; Inspector: BBENEDON; Comment: Entered by JSCHNEI2 - Continued. No issues at this time. Oscar with Chesnut} ; {Activity date: 09/17/2020; Status: Continued; Inspector: BBENEDON; Comment: Entered by JSCHNEI2 - Continued. No issues} ; {Activity date: 09/03/2020; Status: Continued; Inspector: BBENEDON; Comment: Entered by JSCHNEI2 - Continued. No issues at this time. Material stock piles and debris remain on site} ; {Activity date: 08/04/2020; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - continued. All stock piles of material have been removed. Perimeter controls are still in place.} ; {Activity date: 08/04/2020; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Continued. Install controls around. material stock piles} ; {Activity date: 08/04/2020; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - continued. All stock piles of material have been removed. Perimeter controls are still in place.} ; {Activity date: 07/22/2020; Status: Continued; Inspector: BBENEDON; Comment: Entered by JSCHNEI2 - Continued. No track out noted

} ; {Activity date: 07/09/2020; Status: Continued; Inspector: BBENEDON; Comment: Entered by JSCHNEI2 - Continue. No issues at this time.} ; {Activity date: 07/06/2020; Status: Continued; Inspector: BBENEDON; Comment: Entered by JSCHNEI2 - Continued. Minor track out on Grant Road. No controls in place.} ; {Activity date: 07/06/2020; Status: Continued; Inspector: BBENEDON; Comment: Entered by JSCHNEI2 - Continued. Minor track out on Grant Road. No controls in place.} ; {Activity date: 06/29/2020; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Continued. There are no issues at this time. Oscar A will contain all materials as necessary.} ; {Activity date: 06/29/2020; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Continued. There are no issues at this time. Oscar A will contain all materials as necessary.

} ; {Activity date: 06/29/2020; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Continued. There are no issues at this time. Oscar A will contain all materials as necessary.}

Completed Inspections

Permit Status: Complete
Permit Number: DP20-0042
Permit Description: SITE - Grant Rd. & 1st Avenue, parking.
Total Completed Inspections - 8
Date Description Inspector Results Comments
06/24/2020 PDSD Engineering Division Pre-Construction SITE Passed {Activity date: 06/24/2020; Status: Approved; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Approved} ; {Activity date: 06/24/2020; Status: Approved; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Approved. Preconstruction meeting with Oscar from Chestnut at 576-8005. Steve Shell Architect, alex Hines city project manager.
Repaving shopping center in three phases. Reconstructing accessible parking, and ramps. Contractor will install stormwater protections as needed.}
10/01/2020 PDSD Site/Engineering Division - NPPO Passed {Activity date: 10/01/2020; Status: Approved; Inspector: BBENEDON; Comment: Entered by JSCHNEI2 - Approved} ; {Activity date: 10/01/2020; Status: Approved; Inspector: BBENEDON; Comment: Entered by JSCHNEI2 - Approved.} ; {Activity date: 10/01/2020; Status: Approved; Inspector: BBENEDON; Comment: Entered by JSCHNEI2 - Approved.} ; {Activity date: 10/01/2020; Status: Approved; Inspector: BBENEDON; Comment: Entered by JSCHNEI2 - Approved.}
11/24/2020 SITE - Stormwater Setup and Controls Passed {Activity date: 11/24/2020; Status: Approved; Inspector: BBENEDON; Comment: Entered by PAHUMAD1 - } ; {Activity date: 08/04/2020; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Continued. Install controls around. material stock piles} ; {Activity date: 07/14/2020; Status: Partial Approval; Inspector: BBENEDON; Comment: Entered by JSCHNEI2 - Partially approved. Waddle has been installed at Western low area} ; {Activity date: 07/09/2020; Status: Continued; Inspector: BBENEDON; Comment: Entered by JSCHNEI2 - Continued. No controls installed.} ; {Activity date: 06/29/2020; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Continued. There are no issues at this time. Oscar A will contain all materials as necessary.

} ; {Activity date: 06/29/2020; Status: Continued; Inspector: BBENEDON; Comment: Entered by JSCHNEI2 - Continued. Controls installed as needed. Perimeter fencing installed. Oscar is equipped to clean any track out materials if necessary.

} ; {Activity date: 06/29/2020; Status: Continued; Inspector: BBENEDON; Comment: Entered by JSCHNEI2 - Continued. Controls installed as needed. Perimeter fencing installed. Oscar is equipped to clean any track out materials if necessary.} ; {Activity date: 06/29/2020; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Continued. Controls installed as needed. Perimeter fencing installed. Oscar is equipped to clean any track out materials if necessary.

} ; {Activity date: 06/24/2020; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Continued. Oscar with Chesnut will install controls as needed, and is aware of the requirements to protect stormwater inlet structures and keep site materials and debris contained.

}
12/03/2020 PDSD Site/Engineering Division - Landscaping Passed {Activity date: 12/03/2020; Status: Approved; Inspector: BBENEDON; Comment: Entered by PAHUMAD1 - } ; {Activity date: 11/18/2020; Status: Partial Approval; Inspector: BBENENDON; Comment: Entered by PAHUMAD1 - Partially approved.} ; {Activity date: 11/18/2020; Status: Partial Approval; Inspector: BBENEDON; Comment: Entered by PAHUMAD1 - Partially approved} ; {Activity date: 11/18/2020; Status: Partial Approval; Inspector: BBENEDON; Comment: Entered by PAHUMAD1 - Partially approved.} ; {Activity date: 11/18/2020; Status: Partial Approval; Inspector: BBENEDON; Comment: Entered by PAHUMAD1 - Partially approved.} ; {Activity date: 11/18/2020; Status: Partial Approval; Inspector: BBENEDON; Comment: Entered by PAHUMAD1 - Partially approved.} ; {Activity date: 11/18/2020; Status: Partial Approval; Inspector: BBENEDON; Comment: Entered by PAHUMAD1 - Partially approved.} ; {Activity date: 11/18/2020; Status: Partial Approval; Inspector: BBENEDON; Comment: Entered by PAHUMAD1 - Partially approved. Plants and trees.} ; {Activity date: 11/18/2020; Status: Partial Approval; Inspector: BBENEDON; Comment: Entered by PAHUMAD1 - Partially approved. Plants and trees.} ; {Activity date: 11/06/2020; Status: Continued; Inspector: BBENEDON; Comment: Entered by PAHUMAD1 - Continued. Landscaping.} ; {Activity date: 11/06/2020; Status: Partial Approval; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Partially approved. Landscaping.}
12/03/2020 SITE - Stormwater Final Inspection Passed {Activity date: 12/03/2020; Status: Approved; Inspector: BBENEDON; Comment: Entered by PAHUMAD1 - } ; {Activity date: 11/24/2020; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by PAHUMAD1 - } ; {Activity date: 11/24/2020; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by PAHUMAD1 - Not ready. Work still in progress. Small material stock piles on site Controls are still in place

}
05/18/2023 ENGR Engineering Final Passed
05/18/2023 ENGR Grading Final Passed
05/18/2023 COT - ENGR - Signage Final Passed

Documents

File Name Document Type  
1-19 OF 18.PDF DEVELOPMENT PACKAGE VIEW
PERMIT.PDF DOCUMENTS VIEW
CONTRACTOR LETTER.PDF DOCUMENTS VIEW
REVIEW COMMENTS, 04.03.2020.PDF DOCUMENTS VIEW
APPLICATION.PDF DOCUMENTS VIEW
DRAINAGE STATEMENT.PDF DOCUMENTS VIEW
SWPP REPORT.PDF DOCUMENTS VIEW
CITYAPPROVEDDP15-0142(PSOMAS-AUG 2015).PDF DOCUMENTS VIEW