Permit: DP20-0042

Parcel: 11309225A


Addresses:

2402 N 1ST AV

Inspection Status: Passed

Inspection History: SITE - Stormwater Setup and Controls

Date Description Inspector Results Comments
11/24/2020 SITE - Stormwater Setup and Controls BBENEDON Approved Entered by PAHUMAD1 -
08/04/2020 SITE - Stormwater Setup and Controls BBENEDON Continued Entered by RSALDAT1 - Continued. Install controls around. material stock piles
07/14/2020 SITE - Stormwater Setup and Controls BBENEDON Partial Approval Entered by JSCHNEI2 - Partially approved. Waddle has been installed at Western low area
07/09/2020 SITE - Stormwater Setup and Controls BBENEDON Continued Entered by JSCHNEI2 - Continued. No controls installed.
06/29/2020 SITE - Stormwater Setup and Controls BBENEDON Continued Entered by RSALDAT1 - Continued. There are no issues at this time. Oscar A will contain all materials as necessary.
06/29/2020 SITE - Stormwater Setup and Controls BBENEDON Continued Entered by JSCHNEI2 - Continued. Controls installed as needed. Perimeter fencing installed. Oscar is equipped to clean any track out materials if necessary.
06/29/2020 SITE - Stormwater Setup and Controls BBENEDON Continued Entered by JSCHNEI2 - Continued. Controls installed as needed. Perimeter fencing installed. Oscar is equipped to clean any track out materials if necessary.
06/29/2020 SITE - Stormwater Setup and Controls BBENEDON Continued Entered by RSALDAT1 - Continued. Controls installed as needed. Perimeter fencing installed. Oscar is equipped to clean any track out materials if necessary.
06/24/2020 SITE - Stormwater Setup and Controls BBENEDON Continued Entered by RSALDAT1 - Continued. Oscar with Chesnut will install controls as needed, and is aware of the requirements to protect stormwater inlet structures and keep site materials and debris contained.