Inspection Status: Passed
Inspection History: PDSD Engineering Division Pre-Construction SITE
| Date |
Description |
Inspector |
Results |
Comments |
| 06/24/2020 |
PDSD Engineering Division Pre-Construction SITE |
BBENEDON |
Approved |
Entered by RSALDAT1 - Approved |
| 06/24/2020 |
PDSD Engineering Division Pre-Construction SITE |
BBENEDON |
Approved |
Entered by RSALDAT1 - Approved. Preconstruction meeting with Oscar from Chestnut at 576-8005. Steve Shell Architect, alex Hines city project manager.
Repaving shopping center in three phases. Reconstructing accessible parking, and ramps. Contractor will install stormwater protections as needed. |