Permit: DP19-0294
Permit Details
Apply Date:
11/26/2019
Applicant:
Amaris Grimme
Description:
SITE/GRADING-TARP, Irvington. water treatment plant, storage, pumping system.
Permit Reviews
Permit Number - DP19-0294
Permit Status: Complete
Permit Description: SITE/GRADING-TARP, Irvington. water treatment plant, storage, pumping system.
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/06/2022 | DEV PKG - OK TO SUBMIT | 02/04/2022 | COMPLETED |
02/04/2022 | REVISION - - 2ND | 03/01/2022 | COMPLETED |
02/18/2020 | DEV PKG - RESUBMITTAL | 03/10/2020 | COMPLETED |
09/04/2020 | DEV PKG - OK TO SUBMIT | 10/22/2020 | COMPLETED |
09/05/2022 | DEV PKG - OK TO SUBMIT | 09/23/2022 | COMPLETED |
09/23/2022 | REVISION - - 3RD | 09/27/2022 | ACTIVE |
10/22/2020 | REVISION - - 1ST | 12/03/2020 | COMPLETED |
10/25/2019 | DEV PKG - OK TO SUBMIT | 12/02/2019 | COMPLETED |
11/19/2019 | DEV PKG - OK TO SUBMIT | 12/20/2019 | COMPLETED |
12/20/2019 | DEV PKG | 01/28/2020 | COMPLETED |
10/27/2022 | DEVELOPMENT PACKAGE REVIEW v.1 | 12/08/2022 | APPROVED |
Outstanding Inspections
Permit Status: Complete
Permit Number: DP19-0294
Permite Description: SITE/GRADING-TARP, Irvington. water treatment plant, storage, pumping system.
Total Outstanding Inspections - 6
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/05/2023 | ENGR - Drainage Structures | N/A | Not Ready | Nothing being done at this time, but will be looking at the slab on grade inlet structure that was poured earlier this week |
08/28/2023 | SITE - Stormwater Follow-up | N/A | Complete (Recurring) | Met with PCL and looked over the work that remains, Pavement placement is the largest amount of work that remains at this time. Weather Permitting they expect to be done in about 3 weeks except some general cleanup of the site. No concerns at this time |
05/25/2023 | SITE - Stormwater Setup and Controls | N/A | Partial Pass | No concerns at this time |
08/28/2023 | COT - ENGR - Stormwater | N/A | Complete (Recurring) | Met with PCL and looked over the work that remains, Pavement placement is the largest amount of work that remains at this time. Weather Permitting they expect to be done in about 3 weeks except some general cleanup of the site. No concerns at this time |
05/05/2023 | ENGR Grading Final | N/A | Not Ready | No concerns on this site at this time met with a contractor to discuss the future operations |
10/26/2022 | PDSD Engineering Division Pre-Construction SITE | N/A | Not Ready |
Completed Inspections
Permit Status: Complete
Permit Number: DP19-0294
Permit Description: SITE/GRADING-TARP, Irvington. water treatment plant, storage, pumping system.
Total Completed Inspections - 11
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/08/2024 | ENGR - Drainage Structures | Passed | ||
02/08/2024 | ENGR Engineering Final | Passed | ||
02/08/2024 | COT - SITE - Zoning Intermediate | Passed | ||
02/08/2024 | PDSD Site/Engineering Division - NPPO | Passed | ||
02/08/2024 | SITE - Stormwater Follow-up | Passed | ||
02/08/2024 | SITE - Stormwater Setup and Controls | Passed | ||
02/08/2024 | COT - ENGR - Stormwater | Passed | ||
03/18/2024 | PDSD Site/Engineering Division - Landscaping | Passed | ||
03/18/2024 | ENGR Grading Final | Passed | ||
03/18/2024 | SITE - Stormwater Final Inspection | Passed | ||
03/18/2024 | PDSD Engineering Division Pre-Construction SITE | Passed |