Inspection History Details
Inspection Status: Passed
Inspection History: COT - ENGR - Stormwater
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/08/2024 | COT - ENGR - Stormwater | Passed | ||
| 02/08/2024 | COT - ENGR - Stormwater | Passed | ||
| 05/05/2023 | COT - ENGR - Stormwater | Complete (Recurring) | There are no concerns at this time | |
| 06/08/2023 | COT - ENGR - Stormwater | Not Ready | No one on site at 4:30. Will reschedule this inspection for tomorrow, Friday 6/9/23 | |
| 08/25/2023 | COT - ENGR - Stormwater | Complete (Recurring) | Walked site with Amaris from PCL Construction all wattle in place section surrounding grate on center of East wall section will be re-staked and adjusted to overlap. The South end of East wall grouted Rip Rap area is completed per Amaris they will clean the area to remove grout off exposed Rip Rap. |
|
| 08/28/2023 | COT - ENGR - Stormwater | Complete (Recurring) | Met with PCL and looked over the work that remains, Pavement placement is the largest amount of work that remains at this time. Weather Permitting they expect to be done in about 3 weeks except some general cleanup of the site. No concerns at this time |