Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Not Ready
Inspection History: SITE - Stormwater Setup and Controls
Permit Number - DP19-0294
Inspection Description - SITE - Stormwater Setup and Controls
Inspection Status - Not Ready
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/26/2022 | SITE - Stormwater Setup and Controls | Not Ready | ||
03/16/2020 | SITE - Stormwater Setup and Controls | BBENEDON | Partial Approval | Entered by SFLORES2 - Track out protections |
03/16/2020 | SITE - Stormwater Setup and Controls | BBENEDON | Partial Approval | Entered by SFLORES2 - Track out protections |
02/20/2020 | SITE - Stormwater Setup and Controls | RLEDONNE | Not ready for Inspection | Entered by DMERANZ1 - Met with GC on site he said that his first inspection was scheduled for 16 March. |
02/08/2024 | SITE - Stormwater Setup and Controls | Passed | ||
05/04/2023 | SITE - Stormwater Setup and Controls | Complete (Recurring) | no concerns at this time this is the first time I’ve been out here in about a year contractors getting ready to install some CMP . Who won the contractor that you need to call for inspection for the CMP | |
05/25/2023 | SITE - Stormwater Setup and Controls | Partial Pass | No concerns at this time |