Permit: DP19-0042
Permit Details
Apply Date:
02/15/2019
Applicant:
David Little
Description:
SITE/GRADING/SWPPP - Dynamite 1 Car Wash.
Permit Reviews
Permit Number - DP19-0042
Permit Status: Complete
Permit Description: SITE/GRADING/SWPPP - Dynamite 1 Car Wash.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/16/2019 | DEV PKG - OK TO SUBMIT | 02/20/2019 | COMPLETED |
| 02/21/2019 | DEV PKG | 04/01/2019 | COMPLETED |
| 05/30/2019 | DEV PKG - RESUBMITTAL | 07/02/2019 | COMPLETED |
| 07/10/2019 | DEV PKG - RESUBMITTAL | 07/12/2019 | COMPLETED |
| 07/31/2019 | DEV PKG - RESUBMITTAL | 08/08/2019 | COMPLETED |
Completed Inspections
Permit Status: Complete
Permit Number: DP19-0042
Permit Description: SITE/GRADING/SWPPP - Dynamite 1 Car Wash.
Total Completed Inspections - 9
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/17/2019 | PDSD Engineering Division Pre-Construction SITE | Passed | {Activity date: 10/17/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - Superintendent Chris 909-4628. WLB engineering. Dynamite car wash expansion. The site is .7 acres. Controls have been installed. Schedule inspections to the IVR system or through velocity hall. Obtain a copy of your development package permit. Schedule stormwater follow up inspections biweekly. The majority of theLandscaping and drainage work appears to be existing. Trash enclosure is existing. The plans call for no accessible parking spaces and no bicycle parking. Post your address.} |
|
| 10/18/2019 | SITE - Stormwater Setup and Controls | Passed | {Activity date: 10/18/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - } | |
| 06/05/2020 | SITE - Stormwater Final Inspection | Passed | {Activity date: 06/05/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - } | |
| 06/08/2020 | PDSD Site/Engineering Division - NPPO | Passed | {Activity date: 06/08/2020; Status: Approved; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - } | |
| 06/08/2020 | SITE - Stormwater Follow-up | Passed | {Activity date: 06/08/2020; Status: Approved; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - } ; {Activity date: 05/19/2020; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Material stock pile in driveway.} ; {Activity date: 03/05/2020; Status: Continued; Inspector: DROBERTS; Comment: Entered by DMERANZ1 - } ; {Activity date: 11/25/2019; Status: Continued; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - No issues.} ; {Activity date: 11/07/2019; Status: Continued; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - Controls are in place and there is no track out} | |
| 06/08/2020 | ENGR Grading Final | Passed | {Activity date: 06/08/2020; Status: Approved; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - } ; {Activity date: 05/19/2020; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Contractor installing landscape in right of way. New accessible route through ROW is out of compliance as shown on plan.} ; {Activity date: 03/05/2020; Status: Continued; Inspector: DROBERTS; Comment: Entered by DMERANZ1 - THE CREWS ARE WORKING ON THE SITE WORK ALONG WITH THE BUILDING GOING VERTICAL. CURRENTLY THERE IS A CREW WORKING ON DREXEL DOING WHAT APPEARS TO BE THE SEWER TIE-IN. THIS AREA IS UNDER A TRAFFIC CONTROL PLAN FROM TRANSPORTATION DEPARTMENT.} | |
| 07/17/2020 | PDSD Site/Engineering Division - Landscaping | Passed | {Activity date: 07/17/2020; Status: Approved; Inspector: BBENEDON; Comment: Entered by JSCHNEI2 - Approved} ; {Activity date: 06/22/2020; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Not ready. There is still some remaining concrete debris and a hole in the side of the depressed landscaped water harvesting area on the north side of the site} ; {Activity date: 06/19/2020; Status: Partial Approval; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Partially approved. OK for TCO. Waiting for completion of landscaping.} ; {Activity date: 06/18/2020; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Not ready. Grade and stabilize all disturbed areas. Remove debris. Remove trash dumpster in the parking area. Remove all leftover stormwater controls. Shannon with bespoke Builder’s at 602-318-6969 Note, all work within city of Tucson right of way, outside of property line requires a department of transportation permit and inspection.} ; {Activity date: 06/17/2020; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Not ready. Chris or Shannon Will schedule all required final inspections and will send pictures of the site, parking lot, landscaping, existing basin for final inspections.} |
|
| 07/17/2020 | ENGR Engineering Final | Passed | {Activity date: 07/17/2020; Status: Approved; Inspector: BBENEDON; Comment: Entered by JSCHNEI2 - Approved} ; {Activity date: 06/22/2020; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Not ready. There is still some remaining concrete debris and a hole in the side of the depressed landscaped water harvesting area on the north side of the site} ; {Activity date: 06/19/2020; Status: Partial Approval; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Partially approved. OK for TCO. Waiting for completion of landscaping.} ; {Activity date: 06/18/2020; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Not ready. Grade and stabilize all disturbed areas. Remove debris. Remove trash dumpster in the parking area. Remove all leftover stormwater controls. Shannon with bespoke Builder’s at 602-318-6969 Note, all work within city of Tucson right of way, outside of property line requires a department of transportation permit and inspection.} ; {Activity date: 06/17/2020; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Not ready. Chris or Shannon Will schedule all required final inspections and will send pictures of the site, parking lot, landscaping, existing basin for final inspections.} ; {Activity date: 06/08/2020; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Not ready. Chris will reschedule for finals and ready.} ; {Activity date: 06/02/2020; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Not ready. Chris expects to call for final inspections later this week.} |
|
| 07/17/2020 | COT - ENGR - Signage Final | Passed | {Activity date: 07/17/2020; Status: Approved; Inspector: BBENEDON; Comment: Entered by JSCHNEI2 - Approved} ; {Activity date: 06/17/2020; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Not ready. Chris or Shannon Will schedule all required final inspections and will send pictures of the site, parking lot, landscaping, existing basin for final inspections.} |