Inspection Status: Passed
Inspection History: ENGR Engineering Final
| Date |
Description |
Inspector |
Results |
Comments |
| 07/17/2020 |
ENGR Engineering Final
|
BBENEDON |
Approved |
Entered by JSCHNEI2 - Approved |
| 06/22/2020 |
ENGR Engineering Final
|
BBENEDON |
Not ready for Inspection |
Entered by RSALDAT1 - Not ready. Remove concrete and other debris from landscaped areas. Fill in the hole in the Bank of the depressed landscaped area. Shannon was informed that the work outside of the property line requires right of way permit and inspections. |
| 06/19/2020 |
ENGR Engineering Final
|
BBENEDON |
Partial Approval |
Entered by RSALDAT1 - Partially approved. OK for TCO. Waiting for completion of landscaping. |
| 06/18/2020 |
ENGR Engineering Final
|
BBENEDON |
Not ready for Inspection |
Entered by RSALDAT1 - Not ready. Grade and stabilize all disturbed areas. Remove debris. Remove trash dumpster in the parking area. Remove all leftover stormwater controls.
Shannon with bespoke Builder’s at 602-318-6969
Note, all work within city of Tucson right of way, outside of property line requires a department of transportation permit and inspection. |
| 06/17/2020 |
ENGR Engineering Final
|
BBENEDON |
Not ready for Inspection |
Entered by RSALDAT1 - Not ready. Chris or Shannon Will schedule all required final inspections and will send pictures of the site, parking lot, landscaping, existing basin for final inspections. |
| 06/03/2020 |
ENGR Engineering Final
|
BBENEDON |
Not ready for Inspection |
Entered by RSALDAT1 - Not ready. Chris at 909-4628. Has been told to contact his right of way Inspector with the department of transportation to inspect work done outside of the property line. |
| 07/17/2020 |
ENGR Engineering Final
|
BBENEDON |
Approved |
Entered by JSCHNEI2 - Approved |
| 06/22/2020 |
ENGR Engineering Final
|
BBENEDON |
Not ready for Inspection |
Entered by RSALDAT1 - Not ready. There is still some remaining concrete debris and a hole in the side of the depressed landscaped water harvesting area on the north side of the site |
| 06/19/2020 |
ENGR Engineering Final
|
BBENEDON |
Partial Approval |
Entered by RSALDAT1 - Partially approved. OK for TCO. Waiting for completion of landscaping. |
| 06/18/2020 |
ENGR Engineering Final
|
BBENEDON |
Not ready for Inspection |
Entered by RSALDAT1 - Not ready. Grade and stabilize all disturbed areas. Remove debris. Remove trash dumpster in the parking area. Remove all leftover stormwater controls.
Shannon with bespoke Builder’s at 602-318-6969
Note, all work within city of Tucson right of way, outside of property line requires a department of transportation permit and inspection. |
| 06/17/2020 |
ENGR Engineering Final
|
BBENEDON |
Not ready for Inspection |
Entered by RSALDAT1 - Not ready. Chris or Shannon Will schedule all required final inspections and will send pictures of the site, parking lot, landscaping, existing basin for final inspections. |
| 06/08/2020 |
ENGR Engineering Final
|
BBENEDON |
Not ready for Inspection |
Entered by RSALDAT1 - Not ready. Chris will reschedule for finals and ready. |
| 06/02/2020 |
ENGR Engineering Final
|
BBENEDON |
Not ready for Inspection |
Entered by RSALDAT1 - Not ready. Chris expects to call for final inspections later this week. |