Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Issued
Type:
Development Package
Apply Date:
01/17/2018
Applicant:
Kyle Shepherd
Description:
GRADING/SWPPP - La Estancia de Tucson, Phase 8. Lots 689-735 and 780-806, Common Areas A and B.

Permit Reviews

Permit Number - DP18-0015
Permit Status: Issued
Permit Description: GRADING/SWPPP - La Estancia de Tucson, Phase 8. Lots 689-735 and 780-806, Common Areas A and B.
Start Date Submittal Complete Date Status  
01/17/2018 DEV PKG - OK TO SUBMIT (GRADING ONLY) 01/17/2018 COMPLETED Review Details
01/25/2018 GRADING 03/23/2018 COMPLETED Review Details
03/23/2018 GRADING 02/19/2019 COMPLETED Review Details

Outstanding Inspections

Permit Status: Issued
Permit Number: DP18-0015
Permite Description: GRADING/SWPPP - La Estancia de Tucson, Phase 8. Lots 689-735 and 780-806, Common Areas A and B.
Total Outstanding Inspections - 2
Last Inspection Date Description Inspector Results Comments
05/01/2023 ENGR Engineering Final N/A Partial Pass Complete all work as shown on the approved plans prior to scheduling this site for a final. This will include all landscaping for the site That may be included on DP17-0037. This site will be rescheduled for a sidewalk inspection for May 4 to be done by David Roberts. After that inspection, it will be determined what punchlist items will be needed and required prior to the full approval on this site.
10/01/2023 PDSD Site/Engineering Division - Landscaping N/A Not Ready Site is not complete at this time, complete all work as shown on the Approved Landscape plans for this site before recalling the Inspection or Additional charges will be made if significant progress on this site since the last Inspection.

Completed Inspections

Permit Status: Issued
Permit Number: DP18-0015
Permit Description: GRADING/SWPPP - La Estancia de Tucson, Phase 8. Lots 689-735 and 780-806, Common Areas A and B.
Total Completed Inspections - 9
Date Description Inspector Results Comments
05/17/2019 SITE - Stormwater Setup and Controls Passed {Activity date: 05/17/2019; Status: Approved; Inspector: RLEDONNE; Comment: Entered by CBELL1 - } ; {Activity date: 04/19/2019; Status: Cancelled; Inspector: DROBERTS; Comment: Entered by CBELL1 - WILL BE RESCHEDULED FOR NEXT WEEK ONCE RON LE DONNE RETURNS} ; {Activity date: 04/05/2019; Status: Not ready for Inspection; Inspector: RLEDONNE; Comment: Entered by CBELL1 - }
10/18/2019 COT - ENGR - Signage Final Passed {Activity date: 10/18/2019; Status: Approved; Inspector: RLEDONNE; Comment: Entered by DMERANZ1 - }
01/20/2023 PDSD Engineering Division Pre-Construction SITE Passed N/A
02/03/2023 PDSD Site/Engineering Division - NPPO Passed N/A
05/02/2023 SITE - Stormwater Follow-up Passed N/A
08/04/2023 ENGR Engineering Final Passed
10/06/2023 SITE - Stormwater Final Inspection Passed
10/06/2023 PDSD Site/Engineering Division - Landscaping Passed
10/10/2023 ENGR Grading Final Passed

Documents

File Name Document Type  
001_SWPPP COVER_1 OF 5.TIF DEVELOPMENT PACKAGE VIEW
002_SWPPP NOTES_2 OF 5.TIF DEVELOPMENT PACKAGE VIEW
003_SWPPP INSPECTION SHEET_3 OF 5.TIF DEVELOPMENT PACKAGE VIEW
004_EROSION CONTROL PLAN_4 OF 5.TIF DEVELOPMENT PACKAGE VIEW
005_EROSION CONTROL DETAILS_5 OF 5.TIF DEVELOPMENT PACKAGE VIEW
006_COVER SHEET_1 OF 4.TIF DEVELOPMENT PACKAGE VIEW
007_NOTE SHEET_2 OF 4.TIF DEVELOPMENT PACKAGE VIEW
008_DETAIL / SECTIONS SHEET_3 OF 4.TIF DEVELOPMENT PACKAGE VIEW
009_GRADING PLAN_4 OF 4.TIF DEVELOPMENT PACKAGE VIEW
None DOCUMENTS VIEW