Permit Details

Status:
Complete
Type:
Development Package
Address NEW:
3541 E BROADWAY BL
Apply Date:
08/18/2014
Applicant:
Lisa Bowers
Description:
SITE/GRADING/SWPPP - MARSHALL'S

Permit Reviews

Permit Number - DP14-0140
Permit Status: Complete
Permit Description: SITE/GRADING/SWPPP - MARSHALL'S
Start Date Submittal Complete Date Status  
08/18/2014 DEV PKG - OK TO SUBMIT 08/18/2014 COMPLETED Review Details
08/18/2014 DEV PKG 09/24/2014 COMPLETED Review Details
09/24/2014 DEV PKG - RESUBMITTAL 01/13/2015 COMPLETED Review Details

Completed Inspections

Permit Status: Complete
Permit Number: DP14-0140
Permit Description: SITE/GRADING/SWPPP - MARSHALL'S
Total Completed Inspections - 7
Date Description Inspector Results Comments
01/28/2015 PDSD Engineering Division Pre-Construction SITE Passed {Activity date: 01/28/2015; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) INSTALL SEDIMENT CONTROLS PER ENGINEERING INSPECTION RECOMMENDATIONS AND PER SITE SPECIFICS - WILL RE-INSPECT FOR COMPLIANCE
2) ENSURE STORM WATER SELF INSPECTIONS ARE PERFORMED PER YOUR SWPPP
3) SWEEP UP TRACKING AS NEEDED
4) ENSURE A PHYSICAL SEPARATION BETWEEN PUBLIC ACCESS AND CONSTRUCTION IS MAINTAINED
5) INSTALL A STABILIZED ENTRANCE
6) INSTALL/USE CONCRETE WASH OUT
7) CALL FOR INSPECTION FOR ANY CHANGES AND/OR CONCERNS.}
02/19/2015 SITE - Stormwater Setup and Controls Passed {Activity date: 02/19/2015; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) SEDIMENT CONTROLS HAVE BEEN INSTALLED.
2) ENSURE EXISTING BUBBLER/CATCH BASIN IS PROTECTED FROM CONSTRUCTION.
3) ENSURE STORM WATER SELF INSPECTIONS ARE PERFORMED AND DOCUMENTED
4) INSTALL A CONCRETE/MATERIALS WASH OUT ON SITE
5) POST A COPY OF YOUR NOI
6) SWEEP UP TRACKING AS-NEEDED
7) CONTRACTOR DIGGING FOOTINGS FOR BLDG} ; {Activity date: 02/10/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) SEDIMENT CONTROLS HAVE BEEN INSTALLED.
2) CONTRACTOR HAS ROUGH GRADED SITE, AND ARE OVER EXCAVATING THE FOUNDATION}
07/01/2015 SITE - Stormwater Follow-up Passed {Activity date: 07/01/2015; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } ; {Activity date: 06/10/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) CONTRACTOR INSTALLING STORM DRAIN ALONG WEST SIDE PER APPROVED PLAN. PICTURES TAKEN
2) ENSURE PRIOR TO FINAL APPROVAL, PROVIDE A CERTIFICATION STATEMENT FROM THE ENGINEER OF RECORD IS PROVIDED AND ANY/ALL CHANGES ARE SHOWN ON PLANS
3) NO STORM WATER CONCERNS AT THIS TIME
} ; {Activity date: 06/02/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO STORM WATER CONCERNS AT THIS TIME} ; {Activity date: 05/15/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME} ; {Activity date: 05/06/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - ADD SEDIMENT CONTROLS AROUND EXISTING CATCH BASINS ALONG THE NE CORNER OF THE SITE WHERE TRENCHING IS TAKING PLACE.
SWEEP UP TRACKED SOIL ALONG TRENCHING} ; {Activity date: 04/03/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) CONTRACTOR WORKING ON BUILDING, NO SIGNIFICANT UNDERGROUND STORM OR SITE WORK AT THIS TIME
2) ENSURE SEDIMENT CONTROLS ARE MAINTAINED THROUGHOUT CONSTRUCTION
3) PERFORM STORM WATER SELF INSPECTIONS ROUTINELY} ; {Activity date: 03/12/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by CSHARRA1 - 1. DISCUSSED FOUR MAIN ROOF DRAINS FOR BUILDING. ENSURE SCUPPER/ROOF LEADERS HAVE POSITIVE DRAINAGE
2. WILL REINSPECT WHEN SCUPPERS ARE SET PRIOR TO CONCRETE - TO VERIFY SLOPE
3. NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME
4. SWEEP UP TRADING ON A ROUTINE BASIS
5. EMPTY CONCRETE WASHOUT WHEN FULL} ; {Activity date: 03/09/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME} ; {Activity date: 03/02/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME} ; {Activity date: 02/19/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) SEDIMENT CONTROLS HAVE BEEN INSTALLED.
2) ENSURE EXISTING BUBBLER/CATCH BASIN IS PROTECTED FROM CONSTRUCTION.
3) ENSURE STORM WATER SELF INSPECTIONS ARE PERFORMED AND DOCUMENTED
4) INSTALL A CONCRETE/MATERIALS WASH OUT ON SITE
5) POST A COPY OF YOUR NOI
6) SWEEP UP TRACKING AS-NEEDED
7) CONTRACTOR DIGGING FOOTINGS FOR BLDG}
07/01/2015 ENGR Grading Final Passed {Activity date: 07/01/2015; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } ; {Activity date: 03/12/2015; Status: Continued; Inspector: MRUSSO1; Comment: Entered by DROBERT5 - 1) FOUR MAIN ROOF DRAINS OFF SOUTH SIDE OF BLDG, ENSURE POSITIVE DRAINAGE, PLANS NOT CLEAR
2) NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME}
07/08/2015 PDSD Site/Engineering Division - Landscaping Passed {Activity date: 07/08/2015; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - }
07/08/2015 ENGR Engineering Final Passed {Activity date: 07/08/2015; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } ; {Activity date: 07/01/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - CLARIFY WHAT IS REQUIRED TO COMPLETE UNDER PHASE I AND WHAT WILL BE FUTURE CONSTRUCTION UNDER PHASE II.

COMPLETE ALL SITE/GRADING UNDER PHASE I .}
07/08/2015 SITE - Stormwater Final Inspection Passed {Activity date: 07/08/2015; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - }