Inspection Status: Passed

Inspection History: ENGR Grading Final

Permit Number - DP14-0140

Inspection Description - ENGR Grading Final

Inspection Status - Passed

Date Description Inspector Results Comments
07/01/2015 ENGR Grading Final MRUSSO Approved Entered by DROBERT5 -
07/01/2015 ENGR Grading Final MRUSSO Approved Entered by DROBERT5 -
07/01/2015 ENGR Grading Final MRUSSO Approved Entered by DROBERT5 -
03/12/2015 ENGR Grading Final MRUSSO1 Continued Entered by DROBERT5 - 1) FOUR MAIN ROOF DRAINS OFF SOUTH SIDE OF BLDG, ENSURE POSITIVE DRAINAGE, PLANS NOT CLEAR 2) NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME
07/01/2015 ENGR Grading Final MRUSSO Approved Entered by DROBERT5 -
06/10/2015 ENGR Grading Final MRUSSO Continued Entered by DROBERT5 - 1) CONTRACTOR INSTALLING STORM DRAIN ALONG WEST SIDE PER APPROVED PLAN. PICTURES TAKEN 2) ENSURE PRIOR TO FINAL APPROVAL, PROVIDE A CERTIFICATION STATEMENT FROM THE ENGINEER OF RECORD IS PROVIDED AND ANY/ALL CHANGES ARE SHOWN ON PLANS 3) NO STORM WATER CONCERNS AT THIS TIME
06/02/2015 ENGR Grading Final MRUSSO Continued Entered by DROBERT5 - 1) STORM DRAINAGE LINE ALONG WEST SIDE OF BLDG INSTALLED 2) AREA DRAINS AND RISERS IN PLACE. 3) LINE SET AT GRADE AND BEDDED TO THE SPRING LINE - OK TO COVER PICTURES TAKEN
06/01/2015 ENGR Grading Final MRUSSO Continued Entered by DROBERT5 - 1) CONTRACTOR INSTALLING STORM PIPE ALONG THE WEST SIDE OF THE BLDG - PIPE WILL TIE INTO EXISTING DRAINAGE 2) INSTALLED PER APPROVED PLANS - OK TO BURY 3) NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME
04/23/2015 ENGR Grading Final MRUSSO Continued Entered by DROBERT5 - 1) PLEASE CALL FOR INSPECTION FOR ANY UNDERGROUND STORM DRAIN WORK. I WILL NOT APPROVE A STORM DRAIN LINE I DO NOT SEE INSTALLED. 2) CONTINUE TO MAINTAIN SEDIMENT CONTROLS UNTIL THE SITE IS STABILIZED 3) ENSURE YOU PERFORMED STORM WATER SELF INSPECTIONS AND DOCUMENT THEM
04/16/2015 ENGR Grading Final MRUSSO Continued Entered by DROBERT5 - ENSURE STORM WATER SELF INSPECTIONS ARE PERFORMED AND DOCUMENTED. NO OTHER STORM WATER CONCERNS AT THIS TIME
04/13/2015 ENGR Grading Final MRUSSO Continued Entered by DROBERT5 - NO SIGNIFICANT STORM WATER /SITE CONCERNS AT THIS TIME
04/03/2015 ENGR Grading Final MRUSSO Continued Entered by DROBERT5 - 1) CONTRACTOR WORKING ON BUILDING, NO SIGNIFICANT UNDERGROUND STORM OR SITE WORK AT THIS TIME 2) ENSURE SEDIMENT CONTROLS ARE MAINTAINED THROUGHOUT CONSTRUCTION 3) PERFORM STORM WATER SELF INSPECTIONS ROUTINELY
03/26/2015 ENGR Grading Final MRUSSO Continued Entered by DROBERT5 - NO SITE/GRADING CHANGES OR CONCERNS AT THIS TIME
03/17/2015 ENGR Grading Final MRUSSO Continued Entered by CSHARRA1 - 1. PROVIDE A LETTER/COMMUNICATION FROM THE ENG OF RECORD STATING THAT CHANGES MADE TO INSTALL OF ROOF DRAIN SCUPPERS ARE APPROVED 2. ENSURE POSITIVE DRAINAGE FROM BUILDING 3. PROVIDE CLARIFICATION OF ROOF DRAIN DESIGN
03/02/2015 ENGR Grading Final MRUSSO Continued Entered by DROBERT5 - NO CHANGES AND OR CONCERNS AT THIS TIME
02/19/2015 ENGR Grading Final MRUSSO Continued Entered by DROBERT5 - 1) SEDIMENT CONTROLS HAVE BEEN INSTALLED. 2) ENSURE EXISTING BUBBLER/CATCH BASIN IS PROTECTED FROM CONSTRUCTION. 3) ENSURE STORM WATER SELF INSPECTIONS ARE PERFORMED AND DOCUMENTED 4) INSTALL A CONCRETE/MATERIALS WASH OUT ON SITE 5) POST A COPY OF YOUR NOI 6) SWEEP UP TRACKING AS-NEEDED 7) CONTRACTOR DIGGING FOOTINGS FOR BLDG
02/10/2015 ENGR Grading Final MRUSSO Continued Entered by DROBERT5 - 1) SEDIMENT CONTROLS HAVE BEEN INSTALLED. 2) CONTRACTOR HAS ROUGH GRADED SITE, AND ARE OVER EXCAVATING THE FOUNDATION