Inspection Status: Passed
Inspection History: SITE - Stormwater Follow-up
| Date |
Description |
Inspector |
Results |
Comments |
| 07/01/2015 |
SITE - Stormwater Follow-up
|
MRUSSO |
Approved |
Entered by DROBERT5 - |
| 06/10/2015 |
SITE - Stormwater Follow-up
|
MRUSSO |
Continued |
Entered by DROBERT5 - 1) CONTRACTOR INSTALLING STORM DRAIN ALONG WEST SIDE PER APPROVED PLAN. PICTURES TAKEN
2) ENSURE PRIOR TO FINAL APPROVAL, PROVIDE A CERTIFICATION STATEMENT FROM THE ENGINEER OF RECORD IS PROVIDED AND ANY/ALL CHANGES ARE SHOWN ON PLANS
3) NO STORM WATER CONCERNS AT THIS TIME
|
| 06/02/2015 |
SITE - Stormwater Follow-up
|
MRUSSO |
Continued |
Entered by DROBERT5 - NO STORM WATER CONCERNS AT THIS TIME |
| 05/15/2015 |
SITE - Stormwater Follow-up
|
MRUSSO |
Continued |
Entered by DROBERT5 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME |
| 05/06/2015 |
SITE - Stormwater Follow-up
|
MRUSSO |
Continued |
Entered by DROBERT5 - ADD SEDIMENT CONTROLS AROUND EXISTING CATCH BASINS ALONG THE NE CORNER OF THE SITE WHERE TRENCHING IS TAKING PLACE.
SWEEP UP TRACKED SOIL ALONG TRENCHING |
| 04/03/2015 |
SITE - Stormwater Follow-up
|
MRUSSO |
Continued |
Entered by DROBERT5 - 1) CONTRACTOR WORKING ON BUILDING, NO SIGNIFICANT UNDERGROUND STORM OR SITE WORK AT THIS TIME
2) ENSURE SEDIMENT CONTROLS ARE MAINTAINED THROUGHOUT CONSTRUCTION
3) PERFORM STORM WATER SELF INSPECTIONS ROUTINELY |
| 03/12/2015 |
SITE - Stormwater Follow-up
|
MRUSSO |
Continued |
Entered by CSHARRA1 - 1. DISCUSSED FOUR MAIN ROOF DRAINS FOR BUILDING. ENSURE SCUPPER/ROOF LEADERS HAVE POSITIVE DRAINAGE
2. WILL REINSPECT WHEN SCUPPERS ARE SET PRIOR TO CONCRETE - TO VERIFY SLOPE
3. NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME
4. SWEEP UP TRADING ON A ROUTINE BASIS
5. EMPTY CONCRETE WASHOUT WHEN FULL |
| 03/09/2015 |
SITE - Stormwater Follow-up
|
MRUSSO |
Continued |
Entered by DROBERT5 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME |
| 03/02/2015 |
SITE - Stormwater Follow-up
|
MRUSSO |
Continued |
Entered by DROBERT5 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME |
| 02/19/2015 |
SITE - Stormwater Follow-up
|
MRUSSO |
Continued |
Entered by DROBERT5 - 1) SEDIMENT CONTROLS HAVE BEEN INSTALLED.
2) ENSURE EXISTING BUBBLER/CATCH BASIN IS PROTECTED FROM CONSTRUCTION.
3) ENSURE STORM WATER SELF INSPECTIONS ARE PERFORMED AND DOCUMENTED
4) INSTALL A CONCRETE/MATERIALS WASH OUT ON SITE
5) POST A COPY OF YOUR NOI
6) SWEEP UP TRACKING AS-NEEDED
7) CONTRACTOR DIGGING FOOTINGS FOR BLDG |