Permit: DP12-0103
Permit Details
Status:
Complete
Type:
Development Package
Address:
9398 E OLD VAIL RD
Address NEW:
9398 E OLD VAIL RD
Apply Date:
07/10/2012
Applicant:
Dustin Chisum
Description:
SITE/GRADING/SWPP/DP FOR NEW WAREHOUSE
Permit Reviews
Permit Number - DP12-0103
Permit Status: Complete
Permit Description: SITE/GRADING/SWPP/DP FOR NEW WAREHOUSE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/22/2013 | DEV PKG - RESUBMITTAL | 02/22/2013 | COMPLETED |
| 03/07/2013 | DEV PKG - RESUBMITTAL | 03/12/2013 | COMPLETED |
| 07/10/2012 | DEV PKG - OK TO SUBMIT | 07/10/2012 | COMPLETED |
| 07/10/2012 | DEV PKG | 08/15/2012 | COMPLETED |
| 11/05/2012 | DEV PKG - RESUBMITTAL | 12/10/2012 | COMPLETED |
Completed Inspections
Permit Status: Complete
Permit Number: DP12-0103
Permit Description: SITE/GRADING/SWPP/DP FOR NEW WAREHOUSE
Total Completed Inspections - 8
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/02/2013 | PDSD Engineering Division Pre-Construction SITE | Passed | {Activity date: 04/02/2013; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) MET WITH SUPERINTENDENT ON SITE. DUSTIN CHISUM 602-840-2929/602-999-8994 2) ROUGH GRADING HAS BEEN TAKING PLACE WITH NO INSPECTIONS. 3) SITE IS IN NON-COMPLIANCE WITH THE COT STORM WATER ORDINANCE AND ADEQ 4) CONTRACTOR MUST IMPLEMENT THE APPROVED STORM WATER PLAN FOR THE SITE AND CALL FOR RE-INSPECTION. 5) CONTINUED NON-COMPLIANCE WILL RESULT IN A STOP WORK UNTIL SEDIMENT CONTROLS ARE INSTALLED PER THE APPROVED PLAN} |
|
| 04/05/2013 | SITE - Stormwater Setup and Controls | Passed | {Activity date: 04/05/2013; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) CONTRACTOR HAS INSTALLED SEDIMENT CONTROLS PER THE APPROVED STORM WATER PLAN 2) ENSURE STORM WATER SELF INSPECTION ARE PERFORMED AND DOCUMENTED 3) SWEEP UP ANY TRACKED SOIL OFF PUBLIC ROADWAY 4) INSTALL A CONCRETE/MATERIALS WASH OUT WHEN NEEDED} |
|
| 08/19/2013 | COT - ENGR - Site - Assurance Release | Passed | {Activity date: 08/19/2013; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } ; {Activity date: 03/28/2013; Status: Continued; Inspector: DROBERTS; Comment: Entered by DROBERT5 - NO ONE ONSITE, ROUGH GRADING WORK HAS BEEN COMPLETED AT THIS TIME. CONSTRUCTION ENTRANCE INSTALLED, NO APPARENT SWPPP CONTROLS UP AT THIS TIME. NOTED BARRELL CACTUS IN THE REFUGE PILE, 3 BARRELL AND 4 OCOTILLO PLACED INTO A TEMPORARY NURSARY.} | |
| 09/17/2013 | PDSD Site/Engineering Division - Landscaping | Passed | {Activity date: 09/17/2013; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } | |
| 09/17/2013 | SITE - Stormwater Follow-up | Passed | {Activity date: 09/17/2013; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } ; {Activity date: 08/28/2013; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - SITE HAS BEEN PAVED. LANDSCAPING BEING DONE. MAJORITY OF SITE HAS BEEN STABILIZED. NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME} ; {Activity date: 08/19/2013; Status: Partial Approval; Inspector: MRUSSO; Comment: Entered by DROBERT5 - SITE HAS BEEN PAVED, HOWEVER ALL AREAS HAVE NOT BEEN LANDSCAPED OR HARDSCAPED. STILL NEE SEDIMENT CONTROLS IN THOSE AREAS} ; {Activity date: 08/16/2013; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - CONTRACTOR PAVING SITE, MAJORITY OF SEDIMENT CONTROLS HAVE BEEN REMOVED. ENSURE STORM WATER PLAN IS IMPLEMENTED UNTIL THE SITE IS 100% STABILIZED} ; {Activity date: 07/26/2013; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) CONTRACTOR INSTALLING CURB IN PARKING AND ACCESS AREA. 2) CONTRACTOR PREPING SUB-GRADE FOR PAVING 3)NEED TO RE-INSTALL/REPAIR/REPLACE SILT FENCE ALONG SOUTH EAST SIDE OF SITE. 4) CALL FOR INSPECTION PRIOR TO INSTALL OF STORM PIPE} ; {Activity date: 07/15/2013; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO SIGNIFICANT CHANGES AND/OR CONCERNS AT THIS TIME} ; {Activity date: 06/27/2013; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) INSTALL OF 280LF OF 8" HDPE GRADED @ 1% 2) INSTALL OF 8X8" TEE CONNECTION FOR LATERAL LINE 3) PIPE WILL BE BEDDED AND COVERED W/ SCREENED MATERIAL 4) CALL FOR INSPECTION WHEN CATCH BASINS ARE FORMED PRIOR TO COVER 5) PICTURES TAKEN FOR VERIFICATION/DOCUMENTATION OK TO BURY PIPE 6) NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME} ; {Activity date: 06/24/2013; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME} ; {Activity date: 06/06/2013; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - CONTRACTOR STATED THAT THE STORM PIPING SHOWN ON THE APPROVED PLANS WILL BE INSTALLED NEXT WEEK. NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME} ; {Activity date: 04/22/2013; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) SEDIMENT CONTROLS IN PLACE 2) NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME 3) SITE BEING INSPECTED BY ADEQ 4) CONTRACTOR WORKING ON FOUNDATION AND STEM WALLS, NO SIGNIFICANT SITE WORK AT THIS TIME} |
|
| 09/17/2013 | ENGR Grading Final | Passed | {Activity date: 09/17/2013; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } ; {Activity date: 08/28/2013; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - AWAITING INSTALL OF HEAD WALLS FOR OUTLET SIDE OF STORM PIPE IN RET/DET BASIN. ALL OTHER STORM UNDERGROUND WORK HAS BEEN COMPLETED} ; {Activity date: 08/19/2013; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - INSPECTED TWO MANHOLES AND TRUNK LINE FOR STORM WATER. WILL LOOK AT HEADWALL INSTALL AT RET/DET BASIN} ; {Activity date: 08/16/2013; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - LOOKED AT TWO MANHOLE FOR STORM DRAIN LINE. INSPECTED THE ROOF DRAIN CONECTIONS TO STORM DRAIN. WILL LOOK AT HEADWALL INSTALL NEXT WEEK} ; {Activity date: 07/26/2013; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) CONTRACTOR INSTALLING CURB IN PARKING AND ACCESS AREA. 2) CONTRACTOR PREPING SUB-GRADE FOR PAVING 3)NEED TO RE-INSTALL/REPAIR/REPLACE SILT FENCE ALONG SOUTH EAST SIDE OF SITE. 4) CALL FOR INSPECTION PRIOR TO INSTALL OF STORM PIPE} ; {Activity date: 07/15/2013; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO SIGNIFICANT CHANGES AND/OR CONCERNS AT THIS TIME} ; {Activity date: 06/27/2013; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) INSTALL OF 280LF OF 8" HDPE GRADED @ 1% 2) INSTALL OF 8X8" TEE CONNECTION FOR LATERAL LINE 3) PIPE WILL BE BEDDED AND COVERED W/ SCREENED MATERIAL 4) CALL FOR INSPECTION WHEN CATCH BASINS ARE FORMED PRIOR TO COVER 5) PICTURES TAKEN FOR VERIFICATION/DOCUMENTATION OK TO BURY PIPE 6) NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME} ; {Activity date: 06/24/2013; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO CHANGES AT THIS TIME} ; {Activity date: 06/06/2013; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - CONTRACTOR STATED THAT THE STORM PIPING SHOWN ON THE APPROVED PLANS WILL BE INSTALLED NEXT WEEK. NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME} ; {Activity date: 04/22/2013; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) SEDIMENT CONTROLS IN PLACE 2) NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME 3) SITE BEING INSPECTED BY ADEQ 4) CONTRACTOR WORKING ON FOUNDATION AND STEM WALLS, NO SIGNIFICANT SITE WORK AT THIS TIME} |
|
| 09/17/2013 | SITE - Stormwater Final Inspection | Passed | {Activity date: 09/17/2013; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - ENSURE YOU FILE YOUR NOTICE OF TERMINATION "NOT" WITH ADEQ} | |
| 10/15/2013 | ENGR Engineering Final | Passed | {Activity date: 10/15/2013; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - CERTIFICATION LETTER RECEIVED} ; {Activity date: 09/25/2013; Status: Not ready for Inspection; Inspector: MRUSSO; Comment: Entered by DROBERT5 - MET WITH GENERAL CONTRACTOR, HE WILL E-MAIL SITE/GRADING CERT. AND SUBMIT AS-BUILT DRAWING} ; {Activity date: 09/17/2013; Status: Denied; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) PROVIDE A CERTIFICATION STATEMENT FROM THE ENG OF RECORD STATING THAT SITE/GRADING WAS COMPLETED PER THE APPROVED PLAN. 2) PROVIDE AN AS-BUILT DRAWING 3) INSTALL RIP RAP AT CURB OPENING INTO BASIN 4) COMPLETE SITE LIGHTING 5) CLEAN OUT CATCH BASIN ALONG SOUTHEAST SIDE OF SITE} |