Inspection Status: Passed
Inspection History: ENGR Grading Final
| Date |
Description |
Inspector |
Results |
Comments |
| 09/17/2013 |
ENGR Grading Final |
MRUSSO |
Approved |
Entered by DROBERT5 - |
| 08/28/2013 |
ENGR Grading Final |
MRUSSO |
Continued |
Entered by DROBERT5 - AWAITING INSTALL OF HEAD WALLS FOR OUTLET SIDE OF STORM PIPE IN RET/DET BASIN. ALL OTHER STORM UNDERGROUND WORK HAS BEEN COMPLETED |
| 08/19/2013 |
ENGR Grading Final |
MRUSSO |
Continued |
Entered by DROBERT5 - INSPECTED TWO MANHOLES AND TRUNK LINE FOR STORM WATER.
WILL LOOK AT HEADWALL INSTALL AT RET/DET BASIN |
| 08/16/2013 |
ENGR Grading Final |
MRUSSO |
Continued |
Entered by DROBERT5 - LOOKED AT TWO MANHOLE FOR STORM DRAIN LINE.
INSPECTED THE ROOF DRAIN CONECTIONS TO STORM DRAIN.
WILL LOOK AT HEADWALL INSTALL NEXT WEEK |
| 07/26/2013 |
ENGR Grading Final |
MRUSSO |
Continued |
Entered by DROBERT5 - 1) CONTRACTOR INSTALLING CURB IN PARKING AND ACCESS AREA.
2) CONTRACTOR PREPING SUB-GRADE FOR PAVING
3)NEED TO RE-INSTALL/REPAIR/REPLACE SILT FENCE ALONG SOUTH EAST SIDE OF SITE.
4) CALL FOR INSPECTION PRIOR TO INSTALL OF STORM PIPE |
| 07/15/2013 |
ENGR Grading Final |
MRUSSO |
Continued |
Entered by DROBERT5 - NO SIGNIFICANT CHANGES AND/OR CONCERNS AT THIS TIME |
| 06/27/2013 |
ENGR Grading Final |
MRUSSO |
Continued |
Entered by DROBERT5 - 1) INSTALL OF 280LF OF 8" HDPE GRADED @ 1%
2) INSTALL OF 8X8" TEE CONNECTION FOR LATERAL LINE
3) PIPE WILL BE BEDDED AND COVERED W/ SCREENED MATERIAL
4) CALL FOR INSPECTION WHEN CATCH BASINS ARE FORMED PRIOR TO COVER
5) PICTURES TAKEN FOR VERIFICATION/DOCUMENTATION
OK TO BURY PIPE
6) NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME |
| 06/24/2013 |
ENGR Grading Final |
MRUSSO |
Continued |
Entered by DROBERT5 - NO CHANGES AT THIS TIME |
| 06/06/2013 |
ENGR Grading Final |
MRUSSO |
Continued |
Entered by DROBERT5 - CONTRACTOR STATED THAT THE STORM PIPING SHOWN ON THE APPROVED PLANS WILL BE INSTALLED NEXT WEEK.
NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME |
| 04/22/2013 |
ENGR Grading Final |
MRUSSO |
Continued |
Entered by DROBERT5 - 1) SEDIMENT CONTROLS IN PLACE
2) NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME
3) SITE BEING INSPECTED BY ADEQ
4) CONTRACTOR WORKING ON FOUNDATION AND STEM WALLS, NO SIGNIFICANT SITE WORK AT THIS TIME |