Permit: TD-DEV-1224-00324
Permit Details
Status:
Inspections
Type:
Development Package
Address:
1767 E BENSON HY
Address NEW:
1767 E BENSON HY
Apply Date:
12/03/2024
Applicant:
Angela Gee
Description:
Development package for multi-family residential
Permit Reviews
Permit Number - TD-DEV-1224-00324
Permit Status: Inspections
Permit Description: Development package for multi-family residential
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/05/2026 | DEVELOPMENT PACKAGE NEW v.5 | 05/19/2026 | REQUIRES RESUBMIT |
| 02/13/2026 | DEVELOPMENT PACKAGE NEW v.3 | 03/17/2026 | REQUIRES RESUBMIT |
| 04/06/2026 | DEVELOPMENT PACKAGE NEW v.4 | 04/30/2026 | REQUIRES RESUBMIT |
| 12/06/2024 | DEVELOPMENT PACKAGE NEW v.1 | 03/27/2025 | REQUIRES RESUBMIT |
| 04/21/2025 | DEVELOPMENT PACKAGE NEW v.2 | 06/24/2025 | REQUIRES RESUBMIT |
| 05/21/2026 | DEVELOPMENT PACKAGE NEW v.6 | 05/21/2026 | APPROVED |
Conditions
Permit Number - TD-DEV-1224-00324
Permit Status: Inspections
Permit Description: Development package for multi-family residential
| Date | Description | Comments |
|---|---|---|
| 05/21/2026 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 05/21/2026 | Dust Control/Air Quality Permit is Required. (Utilized with DP's & TP's) |
Outstanding Inspections
Permit Status: Inspections
Permit Number: TD-DEV-1224-00324
Permite Description: Development package for multi-family residential
Total Outstanding Inspections - 4
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/29/2026 | SITE - Stormwater Setup and Controls | N/A | Not Ready | 9/29/26 -Track out rock needs to be 2 to 3". Current rock is too small. fFix this and build it per plan From SWPPP. -Wattle needs to be placed so that the overlaps are side-by-side and it needs to overlap 2 feet at the end of sections. The drainage coming out of the storage unit units needs a more wattle check dams before it reaches the drainage channel. Fix the waddle so it is per plan where this drainage meets the main channel. -Install SWPPP board at Entrance. SWPPP book needs to be on site and accessible. |
| 10/20/2026 | N/A | Failed | Per keynote 22 on sheet 6 of 59, Retaining Wall to be built under separate permit. Do Not Pour Wall Footing. Apply for a separate wall permit. | |
| 10/20/2026 | For trash and recycling enclosures | N/A | Partial Pass | Footing on NE enclosure okay to pour. Ensure that Bollards are poured or block outs are provided. See detail L on sheet 21 of 59. |
| 10/28/2026 | ENGR - Drainage Structures | N/A | Partial Pass | Okay to install embedment stone on chambers |
Completed Inspections
Permit Status: Inspections
Permit Number: TD-DEV-1224-00324
Permit Description: Development package for multi-family residential
Total Completed Inspections - 4
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/29/2026 | NPPO Pre-Construction | Passed | Mr Tree has put in Nursery at S end of site and All TOS plants are accounted for | |
| 10/16/2026 | PDSD Engineering Division Pre-Construction SITE | Passed | NDC on file. | |
| 10/16/2026 | SITE - Stormwater Setup and Controls | Passed | Non Discharge Certificate on file. Ensure site is maintained to prevent any stormwater discharges. | |
| 10/20/2026 | Passed |