Permit: TD-DEV-1223-00472
Permit Details
Status:
Inspections
Type:
Development Package
Address:
502 S FREMONT AV
Address NEW:
502 S FREMONT AV
Apply Date:
12/01/2023
Applicant:
Jesus Lozano
Description:
Development Package for Multifamily Triplex Building
Permit Reviews
Permit Number - TD-DEV-1223-00472
Permit Status: Inspections
Permit Description: Development Package for Multifamily Triplex Building
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/08/2025 | DEVELOPMENT PACKAGE NEW v.5 | 04/25/2025 | APPROVED |
| 12/26/2023 | DEVELOPMENT PACKAGE NEW v.2 | 01/26/2024 | REQUIRES RESUBMIT |
| 11/08/2024 | DEVELOPMENT PACKAGE NEW v.3 | 01/30/2025 | REQUIRES RESUBMIT |
| 02/19/2025 | DEVELOPMENT PACKAGE NEW v.4 | 03/17/2025 | REQUIRES RESUBMIT |
| 12/04/2023 | DEVELOPMENT PACKAGE NEW v.1 | 12/12/2023 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TD-DEV-1223-00472
Permit Status: Inspections
Permit Description: Development Package for Multifamily Triplex Building
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 10/02/2025 | CRWHPLAN NEEDS TO BE CREATED PRIOR TO CLOSEOUT |
Outstanding Inspections
Permit Status: Inspections
Permit Number: TD-DEV-1223-00472
Permite Description: Development Package for Multifamily Triplex Building
Total Outstanding Inspections - 9
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/20/2025 | Assurance - Initial (Roadways, Utilities, Basins) ENGR | N/A | Not Applicable | There is no assurance or basins on this site. |
| 06/12/2026 | Consultation SITE | N/A | Not Applicable | |
| 07/01/2026 | ENGR Engineering Final | N/A | Re-inspection required (with fee) | Three (3) sidewalks on north side are too steep, up to 15% running slope. These need to be 5% max without a railing or 8.33% max with a railing. These routes are indicated as the refuse container path for each unit. Scuppers have been excluded on the north side, pavers have been installed instead. The backup spur in the parking area is 18 inches shorter than the plan calls for. Walls have been excluded from this project. A revised plan reflecting the changes needs to be submitted and approved. Tree stakes are not complete, bike parking is not in place, parking stripes and parking stops are not in place. |
| 07/01/2026 | ENGR Paving | N/A | Re-inspection required (with fee) | Backup Spur isn’t per plan. parking blocks are missing, AB was not inspected. |
| 07/01/2026 | SITE - Zoning Final | N/A | Re-inspection required | 7/1/26 - Three (3) sidewalks on north side are too steep, up to 15% running slope. These need to be 5% max without a railing or 8.33% max with a railing. These routes are indicated as the refuse container path for each unit. Scuppers have been excluded on the north side, pavers have been installed instead. The backup spur in the parking area is 18 inches shorter than the plan calls for. Walls have been excluded from this project. A revised plan reflecting the changes needs to be submitted and approved. |
| 07/01/2026 | N/A | Re-inspection required (with fee) | 7/1/26 - Three (3) sidewalks on north side are too steep, up to 15% running slope. These need to be 5% max without a railing or 8.33% max with a railing. These routes are indicated as the refuse container path for each unit. Scuppers have been excluded on the north side, pavers have been installed instead. The backup spur in the parking area is 18 inches shorter than the plan calls for. Walls have been excluded from this project. A revised plan reflecting the changes needs to be submitted and approved. |
|
| 07/01/2026 | LAND Landscape Appearance & Function Final | N/A | Re-inspection required (with fee) | 7/1/26 - Three (3) sidewalks on north side are too steep, up to 15% running slope. These need to be 5% max without a railing or 8.33% max with a railing. These routes are indicated as the refuse container path for each unit. Scuppers have been excluded on the north side, pavers have been installed instead. The backup spur in the parking area is 18 inches shorter than the plan calls for. Walls have been excluded from this project. A revised plan reflecting the changes needs to be submitted and approved. |
| 07/01/2026 | N/A | Re-inspection required (with fee) | Striping, bike parking, and pedestrian circulation are not complete. | |
| 07/01/2026 | N/A | Re-inspection required (with fee) | 7/1/26 - Three (3) sidewalks on north side are too steep, up to 15% running slope. These need to be 5% max without a railing or 8.33% max with a railing. These routes are indicated as the refuse container path for each unit. Scuppers have been excluded on the north side, pavers have been installed instead. The backup spur in the parking area is 18 inches shorter than the plan calls for. Walls have been excluded from this project. A revised plan reflecting the changes needs to be submitted and approved. |
Completed Inspections
Permit Status: Inspections
Permit Number: TD-DEV-1223-00472
Permit Description: Development Package for Multifamily Triplex Building
Total Completed Inspections - 1
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/08/2025 | PDSD Engineering Division Pre-Construction SITE | Passed | Project has just started, they are doing their underground on the building. Wattle should be used on the street side of the project. Not sure if Jesus understands everything that needs to be called in for inspections. Paperwork was handed out as far as an inspection list. Address needs to also be put up. |