Inspection Status: Failed
Inspection History: ENGR Paving
| Date |
Description |
Inspector |
Results |
Comments |
| 06/12/2026 |
ENGR Paving |
|
Failed |
‘Parking area not ready for subgrade inspection |
| 07/01/2026 |
ENGR Paving |
|
Re-inspection required (with fee) |
Backup Spur isn’t per plan. parking blocks are missing, AB was not inspected. |
| 07/10/2026 |
ENGR Paving |
|
Passed |
Finished asphalt conditions are okay. Parking lines and stops are in place. Turn-around spur dimensions need to be included in the revision for the north sidewalk connections. |