Permit: TD-DEV-1222-00061
Permit Details
Apply Date:
12/05/2022
Applicant:
Evan Bowen
Description:
New 52,000 SF School Building
Permit Reviews
Permit Number - TD-DEV-1222-00061
Permit Status: Complete
Permit Description: New 52,000 SF School Building
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/15/2023 | DEVELOPMENT PACKAGE REVIEW v.2 | 02/16/2023 | REQUIRES RESUBMIT |
12/14/2022 | DEVELOPMENT PACKAGE REVIEW v.1 | 01/20/2023 | REQUIRES RESUBMIT |
10/02/2023 | DEVELOPMENT PACKAGE NEW v.1 | 12/04/2023 | REQUIRES RESUBMIT |
03/20/2023 | DEVELOPMENT PACKAGE REVIEW v.1 | 04/04/2023 | APPROVED |
01/02/2024 | DEVELOPMENT PACKAGE NEW v.2 | 01/02/2024 | APPROVED |
Outstanding Inspections
Permit Status: Complete
Permit Number: TD-DEV-1222-00061
Permite Description: New 52,000 SF School Building
Total Outstanding Inspections - 6
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/01/2023 | COT - FCON - Fire - Final | N/A | Not Applicable | |
09/21/2023 | ENGR - Drainage Structures | N/A | Partial Pass | |
06/30/2023 | Final inspection to ensure all landscape and water harvesting SITE | N/A | Partial Pass | Box culvert lid, number eight |
09/21/2023 | SITE | N/A | Partial Pass | |
07/12/2024 | ENGR Engineering Final | N/A | Not Ready | The contract is still working on this site at various locations and one need to have all work completed prior to scheduling this inspection since this inspection is for a Temporary Certificate of Occupancy for the school. Also, the retention detention basin on the site is holding water past the 12 hour maximum limit, and will need to be checked by the engineer of record. I have advised BFL do you have the engineer of record look at the site and come up with a solution that will help eliminate all of the water within the 12 hour maximum limit. |
07/12/2024 | COT - ENGR - Stormwater | N/A | Complete (Recurring) | No concerns at this time with the storm water for this construction site. But do you have concerns at this time for the existing retention detention basins that are holding water past 12 hours. I have advised the contractor BFL to contact Rick engineering and let them figure out a solution to the problem of the standing water past 12 hours. They will be seeking a TCO for the new building in the next few weeks, but have been advised they will probably get their TC vote, but will not get a final CofO till all the drainage issues have been resolved. |
Completed Inspections
Permit Status: Complete
Permit Number: TD-DEV-1222-00061
Permit Description: New 52,000 SF School Building
Total Completed Inspections - 11
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/04/2023 | PDSD Engineering Division Pre-Construction SITE | Passed | Met with a contractor on site to discuss a future project and all the requirements | |
06/21/2024 | COT - SITE - Zoning Intermediate | Passed | There are no pending issues for this site that I am aware of | |
07/03/2024 | SITE - Zoning Final | Passed | ||
07/15/2024 | Final inspection to ensure all landscape and water harvesting SITE | Passed | ||
07/15/2024 | SITE - Stormwater Final Inspection | Passed | Storm water is ready to close out on this site | |
07/15/2024 | SITE | Passed | ||
07/15/2024 | SITE - Stormwater Follow-up | Passed | Storm water is ready to close out on this site | |
07/24/2024 | PDSD Site/Engineering Division - Landscaping | Passed | ||
07/24/2024 | ENGR Engineering Final | Passed | ||
07/24/2024 | COT - ENGR - Stormwater | Passed | ||
07/24/2024 | COT - ENGR - Signage Final | Passed |