Inspection History Details
Inspection Status: Complete (Recurring)
Inspection History: COT - ENGR - Stormwater
Permit Number - TD-DEV-1222-00061
Inspection Description - COT - ENGR - Stormwater
Inspection Status - Complete (Recurring)
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/25/2023 | COT - ENGR - Stormwater | Complete (Recurring) | Installing 24 inch HP on the southside of the project | |
06/22/2023 | COT - ENGR - Stormwater | Complete (Recurring) | Contractor is pouring for the top of box culvert | |
06/26/2023 | COT - ENGR - Stormwater | Complete (Recurring) | No concerns at this time for stormwater follow up | |
07/01/2024 | COT - ENGR - Stormwater | Complete (Recurring) | ||
07/07/2023 | COT - ENGR - Stormwater | Partial Pass | covert lid, number 10 | |
07/12/2024 | COT - ENGR - Stormwater | Complete (Recurring) | No concerns at this time with the storm water for this construction site. But do you have concerns at this time for the existing retention detention basins that are holding water past 12 hours. I have advised the contractor BFL to contact Rick engineering and let them figure out a solution to the problem of the standing water past 12 hours. They will be seeking a TCO for the new building in the next few weeks, but have been advised they will probably get their TC vote, but will not get a final CofO till all the drainage issues have been resolved. | |
07/24/2024 | COT - ENGR - Stormwater | Passed | ||
09/21/2023 | COT - ENGR - Stormwater | Not Ready | ||
09/25/2023 | COT - ENGR - Stormwater | Partial Pass | Good to backfill 71 lineal feet of HD storm drain pipe on the east side of the building | |
09/28/2023 | COT - ENGR - Stormwater | Not Ready | Contractors not ready reschedule for tomorrow | |
11/17/2023 | COT - ENGR - Stormwater | Complete (Recurring) | Viewed 20’ of 18” storm drain pipe located at the SE section of building all bedding material is in place and density test has been completed by Pattison Engineering okay to backfill. | |
11/20/2023 | COT - ENGR - Stormwater | Partial Pass | Base of storm drains look good, rebar is set and forms being placed. form and rebar inspection will be done on the 21st. | |
11/21/2023 | COT - ENGR - Stormwater | Complete (Recurring) | East front section of Building (2) storm drain intakes are formed and all vertical and horizontal rebar is in place per approved plan and inspected by 3rd party Engineer Pattison, ready to pour. |