Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/02/2023 | ENGR - Drainage Structures | Complete (Recurring) | They set the steel for the walls in the floor for the box culvert good poor | |
05/16/2023 | ENGR - Drainage Structures | Complete (Recurring) | Inspected the rebar for the box culvert and the wing walls good at this time | |
06/01/2023 | ENGR - Drainage Structures | Complete (Recurring) | Look at the Inlet for the box culvert on the east side of that channel in the box. The steel is not completely here contractor send me a photograph when it’s finished. Also looked at the 32 inch HD that’s being installed on the east end of the project. | |
06/09/2023 | ENGR - Drainage Structures | Complete (Recurring) | The contractor is pouring the top of the box culvert today they are pouring the first 20 feet on the eastern end towards West | |
06/20/2023 | ENGR - Drainage Structures | Complete (Recurring) | Contractor poured the second part of the top for the box culvert | |
06/26/2023 | ENGR - Drainage Structures | Complete (Recurring) | Contractors gonna pour the fifth section for the channel good to pour | |
07/05/2023 | ENGR - Drainage Structures | Complete (Recurring) | Contractor install the steel for the channel 9th section of the Channel lid. | |
07/11/2023 | ENGR - Drainage Structures | Partial Pass | contractors pouring the 11th pour for the top of channel.good to pour. | |
07/19/2023 | ENGR - Drainage Structures | Partial Pass | Contractor poured the lid for the channel No. 14 for the poor good at this time | |
07/21/2023 | ENGR - Drainage Structures | Partial Pass | ||
09/20/2023 | ENGR - Drainage Structures | Partial Pass | Spoke with Dan regarding the 2 trash enclosure footers will add (2) vertical rebar at front locations of both enclosures. |
|
09/21/2023 | ENGR - Drainage Structures | Partial Pass |